| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BARBER BROS. CONTRACTING CO., L.L.C |
- 2 - F.G. SULLIVAN, JR. CONTRACTOR LLC |
- 3 - BARRIERE CONSTRUCTION CO., LLC. |
- 4 - DIAMOND B CONSTRUCTION CO., L.L.C. |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-H |
removal of guard rail
|
1,663   |
LNFT |
6.00 |
9,978.00 |
5.00 |
8,315.00 |
7.00 |
11,641.00 |
8.00 |
13,304.00 |
| 202-02-I |
removal of cross drain pipe
|
107   |
LNFT |
40.00 |
4,280.00 |
5.00 |
535.00 |
25.00 |
2,675.00 |
6.00 |
642.00 |
| 202-02-J |
removal of cross drain pipe arch
|
280   |
LNFT |
40.00 |
11,200.00 |
5.00 |
1,400.00 |
25.00 |
7,000.00 |
6.00 |
1,680.00 |
| 203-07 |
borrow (vehicular measurement)
|
3,450   |
CUYD |
15.00 |
51,750.00 |
5.00 |
17,250.00 |
20.00 |
69,000.00 |
16.00 |
55,200.00 |
| 203-07-A |
borrow (vehicular meas.)(selected soils)
|
325   |
CUYD |
15.00 |
4,875.00 |
7.00 |
2,275.00 |
24.00 |
7,800.00 |
33.00 |
10,725.00 |
| 204-05-A |
temporary sediment check dams (hay)
|
100   |
EACH |
100.00 |
10,000.00 |
8.00 |
800.00 |
170.00 |
17,000.00 |
110.00 |
11,000.00 |
| 204-06 |
temporary silt fencing
|
3,380   |
LNFT |
2.00 |
6,760.00 |
2.00 |
6,760.00 |
4.00 |
13,520.00 |
1.50 |
5,070.00 |
| 304-01 |
lime
|
77.48 |
TON |
180.00 |
13,946.40 |
100.00 |
7,748.00 |
120.00 |
9,297.60 |
186.00 |
14,411.28 |
| 304-03-B |
lime treatment (type c) (8 1/2" thick)
|
2,211   |
SQYD |
1.50 |
3,316.50 |
1.00 |
2,211.00 |
4.00 |
8,844.00 |
14.00 |
30,954.00 |
| 304-04-D |
lime treatment (type d) (12" thick)
|
4,422   |
SQYD |
3.00 |
13,266.00 |
2.00 |
8,844.00 |
5.00 |
22,110.00 |
3.75 |
16,582.50 |
| 308-01-A |
in-place cement treated base course (12" thick)
|
88,438   |
SQYD |
7.50 |
663,285.00 |
8.50 |
751,723.00 |
7.50 |
663,285.00 |
8.25 |
729,613.50 |
| 308-02 |
removal of existing patches
|
25   |
SQYD |
25.00 |
625.00 |
5.00 |
125.00 |
1.00 |
25.00 |
125.00 |
3,125.00 |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
2,514   |
CUYD |
65.00 |
163,410.00 |
40.00 |
100,560.00 |
30.00 |
75,420.00 |
98.00 |
246,372.00 |
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
500.0 |
CUYD |
55.00 |
27,500.00 |
40.00 |
20,000.00 |
60.00 |
30,000.00 |
90.00 |
45,000.00 |
| 502-01 |
superpave asphaltic concrete
|
16,168.1 |
TON |
85.00 |
1,374,288.50 |
70.00 |
1,131,767.00 |
89.00 |
1,438,960.90 |
100.00 |
1,616,810.00 |
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
1,938.7 |
TON |
100.00 |
193,870.00 |
140.00 |
271,418.00 |
10.00 |
19,387.00 |
172.00 |
333,456.40 |
| 701-01-K |
cross drain pipe (30" rcp/pcp)
|
48   |
LNFT |
160.00 |
7,680.00 |
225.00 |
10,800.00 |
190.00 |
9,120.00 |
200.00 |
9,600.00 |
| 701-02-D |
cross drain pipe arch (24" equiv. rcpa)
|
40   |
LNFT |
175.00 |
7,000.00 |
215.00 |
8,600.00 |
170.00 |
6,800.00 |
200.00 |
8,000.00 |
| 701-02-F |
cross drain pipe arch (36" equiv. rcpa)
|
240   |
LNFT |
130.00 |
31,200.00 |
230.00 |
55,200.00 |
185.00 |
44,400.00 |
225.00 |
54,000.00 |
| 701-02-H |
cross drain pipe arch (48" equiv. rcpa)
|
48   |
LNFT |
260.00 |
12,480.00 |
285.00 |
13,680.00 |
280.00 |
13,440.00 |
325.00 |
15,600.00 |
| 701-10-I |
reinforced concrete pipe (extension)(24")
|
12   |
LNFT |
400.00 |
4,800.00 |
150.00 |
1,800.00 |
400.00 |
4,800.00 |
175.00 |
2,100.00 |
| 701-15 |
concrete collar
|
2   |
EACH |
1,200.00 |
2,400.00 |
1,200.00 |
2,400.00 |
1,200.00 |
2,400.00 |
1,000.00 |
2,000.00 |
| 702-07-A |
cross drain safety end (type 1)
|
1   |
EACH |
7,500.00 |
7,500.00 |
2,200.00 |
2,200.00 |
4,500.00 |
4,500.00 |
5,000.00 |
5,000.00 |
| 704-01-A |
guard rail (single thrie beam)(3'-1 1/2" post spacing)
|
506.3 |
LNFT |
40.00 |
20,252.00 |
40.00 |
20,252.00 |
60.00 |
30,378.00 |
35.00 |
17,720.50 |
| 704-01-B |
guard rail (single thrie beam)(6'-3" post spacing)
|
692.6 |
LNFT |
65.00 |
45,019.00 |
60.00 |
41,556.00 |
70.00 |
48,482.00 |
60.00 |
41,556.00 |
| 704-03 |
blocked out guard rail
|
932.2 |
LNFT |
22.00 |
20,508.40 |
20.00 |
18,644.00 |
21.00 |
19,576.20 |
20.00 |
18,644.00 |
| 704-11-B |
guard rail end treatment (tangent)
|
19   |
EACH |
3,000.00 |
57,000.00 |
2,700.00 |
51,300.00 |
2,400.00 |
45,600.00 |
2,500.00 |
47,500.00 |
| 711-01-C |
riprap (30 lb,24" thick)
|
45   |
SQYD |
150.00 |
6,750.00 |
80.00 |
3,600.00 |
140.00 |
6,300.00 |
120.00 |
5,400.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
80,000.00 |
80,000.00 |
160,000.00 |
160,000.00 |
200,000.00 |
200,000.00 |
25,000.00 |
25,000.00 |
| 713-02-E |
temporary pavement markings (24" width)
|
33   |
LNFT |
2.00 |
66.00 |
0.10 |
3.30 |
1.00 |
33.00 |
1.00 |
33.00 |
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
19.200 |
MILE |
400.00 |
7,680.00 |
600.00 |
11,520.00 |
10.00 |
192.00 |
130.00 |
2,496.00 |
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
7.308 |
MILE |
350.00 |
2,557.80 |
10.00 |
73.08 |
10.00 |
73.08 |
315.00 |
2,302.02 |
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
55.132 |
MILE |
300.00 |
16,539.60 |
10.00 |
551.32 |
20.00 |
1,102.64 |
600.00 |
33,079.20 |
| 720-01-B |
erosion control system, slope protection (type b)
|
334   |
SQYD |
5.00 |
1,670.00 |
400.00 |
133,600.00 |
3.00 |
1,002.00 |
2.20 |
734.80 |
| 722-02 |
project site laboratory (equipped)
|
1   |
EACH |
12,000.00 |
12,000.00 |
1,500.00 |
1,500.00 |
1,000.00 |
1,000.00 |
10,000.00 |
10,000.00 |
| 726-01 |
bedding material
|
220.8 |
CUYD |
1.00 |
220.80 |
0.01 |
2.21 |
65.00 |
14,352.00 |
70.00 |
15,456.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
100,000.00 |
100,000.00 |
200,000.00 |
200,000.00 |
300,000.00 |
300,000.00 |
179,000.00 |
179,000.00 |
| 729-16-B |
object marker assembly (type 2)
|
10   |
EACH |
55.00 |
550.00 |
60.00 |
600.00 |
60.00 |
600.00 |
70.00 |
700.00 |
| 729-16-C |
object marker assembly (type 3)
|
20   |
EACH |
85.00 |
1,700.00 |
70.00 |
1,400.00 |
100.00 |
2,000.00 |
80.00 |
1,600.00 |
| 731-02 |
reflectorized raised pavement markers
|
845   |
EACH |
6.00 |
5,070.00 |
5.00 |
4,225.00 |
6.00 |
5,070.00 |
6.00 |
5,070.00 |
| 732-01-E |
plastic pavement striping (24" width)
|
11   |
LNFT |
4.00 |
44.00 |
3.00 |
33.00 |
6.00 |
66.00 |
3.50 |
38.50 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
22.644 |
MILE |
2,850.00 |
64,535.40 |
2,500.00 |
56,610.00 |
2,800.00 |
63,403.20 |
2,750.00 |
62,271.00 |
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
2.436 |
MILE |
700.00 |
1,705.20 |
600.00 |
1,461.60 |
600.00 |
1,461.60 |
650.00 |
1,583.40 |
| 735-01 |
mailboxes
|
89   |
EACH |
2.00 |
178.00 |
5.00 |
445.00 |
5.00 |
445.00 |
1.00 |
89.00 |
| 735-02 |
mailbox supports (single)
|
75   |
EACH |
100.00 |
7,500.00 |
150.00 |
11,250.00 |
100.00 |
7,500.00 |
95.00 |
7,125.00 |
| 735-03 |
mailbox supports (double)
|
4   |
EACH |
150.00 |
600.00 |
200.00 |
800.00 |
140.00 |
560.00 |
125.00 |
500.00 |
| 735-04 |
mailbox supports (multiple)
|
2   |
EACH |
250.00 |
500.00 |
250.00 |
500.00 |
240.00 |
480.00 |
200.00 |
400.00 |
| 739-01 |
hydro-seeding
|
7.76 |
ACRE |
1,500.00 |
11,640.00 |
1,100.00 |
8,536.00 |
1,600.00 |
12,416.00 |
1,200.00 |
9,312.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
25,000.00 |
25,000.00 |
69,000.00 |
69,000.00 |
50,000.00 |
50,000.00 |
20,000.00 |
20,000.00 |
| S-002 |
special anchor section
|
1   |
EACH |
1,500.00 |
1,500.00 |
2,000.00 |
2,000.00 |
600.00 |
600.00 |
1,200.00 |
1,200.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
3,116,196.60 |
|
3,225,873.51 |
|
3,294,118.22 |
|
3,739,056.10 |
|
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 5 - COASTAL BRIDGE CO., L.L.C. |
|
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-H |
removal of guard rail
|
1,663   |
LNFT |
10.00 |
16,630.00 |
|
|
|
|
|
|
| 202-02-I |
removal of cross drain pipe
|
107   |
LNFT |
25.00 |
2,675.00 |
|
|
|
|
|
|
| 202-02-J |
removal of cross drain pipe arch
|
280   |
LNFT |
50.00 |
14,000.00 |
|
|
|
|
|
|
| 203-07 |
borrow (vehicular measurement)
|
3,450   |
CUYD |
25.00 |
86,250.00 |
|
|
|
|
|
|
| 203-07-A |
borrow (vehicular meas.)(selected soils)
|
325   |
CUYD |
25.00 |
8,125.00 |
|
|
|
|
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
100   |
EACH |
125.00 |
12,500.00 |
|
|
|
|
|
|
| 204-06 |
temporary silt fencing
|
3,380   |
LNFT |
2.00 |
6,760.00 |
|
|
|
|
|
|
| 304-01 |
lime
|
77.48 |
TON |
175.00 |
13,559.00 |
|
|
|
|
|
|
| 304-03-B |
lime treatment (type c) (8 1/2" thick)
|
2,211   |
SQYD |
5.00 |
11,055.00 |
|
|
|
|
|
|
| 304-04-D |
lime treatment (type d) (12" thick)
|
4,422   |
SQYD |
5.00 |
22,110.00 |
|
|
|
|
|
|
| 308-01-A |
in-place cement treated base course (12" thick)
|
88,438   |
SQYD |
10.00 |
884,380.00 |
|
|
|
|
|
|
| 308-02 |
removal of existing patches
|
25   |
SQYD |
20.00 |
500.00 |
|
|
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
2,514   |
CUYD |
95.00 |
238,830.00 |
|
|
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
500.0 |
CUYD |
50.00 |
25,000.00 |
|
|
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
16,168.1 |
TON |
105.00 |
1,697,650.50 |
|
|
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
1,938.7 |
TON |
195.00 |
378,046.50 |
|
|
|
|
|
|
| 701-01-K |
cross drain pipe (30" rcp/pcp)
|
48   |
LNFT |
275.00 |
13,200.00 |
|
|
|
|
|
|
| 701-02-D |
cross drain pipe arch (24" equiv. rcpa)
|
40   |
LNFT |
275.00 |
11,000.00 |
|
|
|
|
|
|
| 701-02-F |
cross drain pipe arch (36" equiv. rcpa)
|
240   |
LNFT |
275.00 |
66,000.00 |
|
|
|
|
|
|
| 701-02-H |
cross drain pipe arch (48" equiv. rcpa)
|
48   |
LNFT |
225.00 |
10,800.00 |
|
|
|
|
|
|
| 701-10-I |
reinforced concrete pipe (extension)(24")
|
12   |
LNFT |
500.00 |
6,000.00 |
|
|
|
|
|
|
| 701-15 |
concrete collar
|
2   |
EACH |
1,100.00 |
2,200.00 |
|
|
|
|
|
|
| 702-07-A |
cross drain safety end (type 1)
|
1   |
EACH |
4,500.00 |
4,500.00 |
|
|
|
|
|
|
| 704-01-A |
guard rail (single thrie beam)(3'-1 1/2" post spacing)
|
506.3 |
LNFT |
55.00 |
27,846.50 |
|
|
|
|
|
|
| 704-01-B |
guard rail (single thrie beam)(6'-3" post spacing)
|
692.6 |
LNFT |
65.00 |
45,019.00 |
|
|
|
|
|
|
| 704-03 |
blocked out guard rail
|
932.2 |
LNFT |
28.00 |
26,101.60 |
|
|
|
|
|
|
| 704-11-B |
guard rail end treatment (tangent)
|
19   |
EACH |
3,000.00 |
57,000.00 |
|
|
|
|
|
|
| 711-01-C |
riprap (30 lb,24" thick)
|
45   |
SQYD |
150.00 |
6,750.00 |
|
|
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
60,000.00 |
60,000.00 |
|
|
|
|
|
|
| 713-02-E |
temporary pavement markings (24" width)
|
33   |
LNFT |
1.00 |
33.00 |
|
|
|
|
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
19.200 |
MILE |
450.00 |
8,640.00 |
|
|
|
|
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
7.308 |
MILE |
350.00 |
2,557.80 |
|
|
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
55.132 |
MILE |
1.00 |
55.13 |
|
|
|
|
|
|
| 720-01-B |
erosion control system, slope protection (type b)
|
334   |
SQYD |
5.00 |
1,670.00 |
|
|
|
|
|
|
| 722-02 |
project site laboratory (equipped)
|
1   |
EACH |
10,000.00 |
10,000.00 |
|
|
|
|
|
|
| 726-01 |
bedding material
|
220.8 |
CUYD |
1.00 |
220.80 |
|
|
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
350,000.00 |
350,000.00 |
|
|
|
|
|
|
| 729-16-B |
object marker assembly (type 2)
|
10   |
EACH |
75.00 |
750.00 |
|
|
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
20   |
EACH |
90.00 |
1,800.00 |
|
|
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
845   |
EACH |
6.00 |
5,070.00 |
|
|
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
11   |
LNFT |
3.00 |
33.00 |
|
|
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
22.644 |
MILE |
2,500.00 |
56,610.00 |
|
|
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
2.436 |
MILE |
800.00 |
1,948.80 |
|
|
|
|
|
|
| 735-01 |
mailboxes
|
89   |
EACH |
1.00 |
89.00 |
|
|
|
|
|
|
| 735-02 |
mailbox supports (single)
|
75   |
EACH |
200.00 |
15,000.00 |
|
|
|
|
|
|
| 735-03 |
mailbox supports (double)
|
4   |
EACH |
350.00 |
1,400.00 |
|
|
|
|
|
|
| 735-04 |
mailbox supports (multiple)
|
2   |
EACH |
550.00 |
1,100.00 |
|
|
|
|
|
|
| 739-01 |
hydro-seeding
|
7.76 |
ACRE |
1,300.00 |
10,088.00 |
|
|
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
35,000.00 |
35,000.00 |
|
|
|
|
|
|
| S-002 |
special anchor section
|
1   |
EACH |
1,500.00 |
1,500.00 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|