Letting of 6/25/2008 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 451-09-0023
Parish: MADISON
Routes: I-20
Description: I-20 MISSISSIPPI RIVER BRIDGE AT VICKSBURG
Type Const: bridge modifications for 24" movement and related work.
Estimated Construction Cost: $11,062,748.00
Maximum Number of Days Allowed for Construction: 500
Calculated Daily User Cost: $3,000.00
 
RankLicenseBidderConstruction Bid Bidder's Proposed
Contract Time
Total Bid
1 26435 C.E.C., INC. $13,735,666.00 450 $15,085,666.00
2 47347 KIEWIT LOUISIANA CO $18,322,504.00 492 $19,798,504.00
 
Item Number Item Description Quantity Unit of Measure - 1 -
C.E.C., INC.
- 2 -
KIEWIT LOUISIANA CO

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
713-01 temporary signs & barricades lump      LUMP 400,000.00 400,000.00 740,000.00 740,000.00        
713-08 temporary precast concrete barrier (department
furnished)
230      EACH 1,800.00 414,000.00 1,000.00 230,000.00        
727-01 mobilization lump      LUMP 1,200,000.00 1,200,000.00 1,832,000.00 1,832,000.00        
805-01-F class a concrete (bents) 395.90   CUYD 4,500.00 1,781,550.00 7,000.00 2,771,300.00        
805-03 class aa concrete 9.68   CUYD 20,000.00 193,600.00 47,000.00 454,960.00        
806-01 deformed reinforcing steel 51,172      LB 3.00 153,516.00 2.00 102,344.00        
807-08 structural metalwork lump      LUMP 8,500,000.00 8,500,000.00 7,500,000.00 7,500,000.00        
810-03 pipe railing 180.00   LNFT 350.00 63,000.00 455.00 81,900.00        
S-101 required jacking operation for adjustment of false
chords at panel point 15
lump      LUMP 50,000.00 50,000.00 443,000.00 443,000.00        
S-102 required jacking operation for shortening stringers
between l15'-l14'
lump      LUMP 200,000.00 200,000.00 1,400,000.00 1,400,000.00        
S-103 required jacking operation for modification of false
chords l15-l14'
lump      LUMP 150,000.00 150,000.00 1,100,000.00 1,100,000.00        
S-104 required jacking operation for bearing replacement at
pier e2
lump      LUMP 100,000.00 100,000.00 200,000.00 200,000.00        
S-105 required jacking operation for bearing replacement at
pier e3
lump      LUMP 100,000.00 100,000.00 120,000.00 120,000.00        
S-106 bearings at pier e2 lump      LUMP 150,000.00 150,000.00 600,000.00 600,000.00        
S-107 bearings at pier e3 lump      LUMP 200,000.00 200,000.00 600,000.00 600,000.00        
S-108 removal of piertop concrete at pier e1 lump      LUMP 30,000.00 30,000.00 40,000.00 40,000.00        
S-109 variable message sign unit 2      EACH 20,000.00 40,000.00 35,000.00 70,000.00        
S-110 clearance gauge lump      LUMP 10,000.00 10,000.00 37,000.00 37,000.00        
                       
 ITEM TOTAL (CONSTRUCTION BID)       13,735,666.00   18,322,504.00        
 NUMBER OF DAYS BID AT $3,000 PER DAY.       1,350,000.00   1,476,000.00        
 TOTAL BID       15,085,666.00   19,798,504.00        