| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - GILCHRIST CONSTRUCTION CO. LLC |
- 2 - SOIL STABILIZERS, INC. |
- 3 - DIAMOND B CONSTRUCTION CO., L.L.C. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
15,000.00 |
15,000.00 |
35,000.00 |
35,000.00 |
30,000.00 |
30,000.00 |
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
7,500.00 |
7,500.00 |
10,000.00 |
10,000.00 |
1,600.00 |
1,600.00 |
|
|
| 202-02-D |
removal of concrete walks & drives
|
34   |
SQYD |
8.00 |
272.00 |
25.00 |
850.00 |
37.00 |
1,258.00 |
|
|
| 202-02-H |
removal of guard rail
|
113   |
LNFT |
15.00 |
1,695.00 |
20.00 |
2,260.00 |
13.00 |
1,469.00 |
|
|
| 203-07 |
borrow (vehicular measurement)
|
320   |
CUYD |
17.00 |
5,440.00 |
20.00 |
6,400.00 |
25.00 |
8,000.00 |
|
|
| 203-07-A |
borrow (vehicular meas.)(selected soils)
|
85   |
CUYD |
40.00 |
3,400.00 |
25.00 |
2,125.00 |
25.00 |
2,125.00 |
|
|
| 303-01-B |
in-place cement stabilized base course (8 1/2" thick)
|
53,665   |
SQYD |
6.50 |
348,822.50 |
9.00 |
482,985.00 |
10.50 |
563,482.50 |
|
|
| 303-02 |
removal of existing patches
|
150   |
SQYD |
11.00 |
1,650.00 |
20.00 |
3,000.00 |
23.82 |
3,573.00 |
|
|
| 304-05 |
lime treatment (type e)
|
119.73 |
TON |
400.00 |
47,892.00 |
300.00 |
35,919.00 |
350.00 |
41,905.50 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
2,722   |
CUYD |
45.00 |
122,490.00 |
35.00 |
95,270.00 |
25.00 |
68,050.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
10,327.7 |
TON |
100.00 |
1,032,770.00 |
110.00 |
1,136,047.00 |
113.00 |
1,167,030.10 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
795.8 |
TON |
155.00 |
123,349.00 |
175.00 |
139,265.00 |
178.00 |
141,652.40 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
56,987   |
SQYD |
0.10 |
5,698.70 |
1.71 |
97,447.77 |
1.65 |
94,028.55 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 2,931   |
CUYD |
0.01 |
- 29.31 |
0.01 |
- 29.31 |
0.10 |
- 293.10 |
|
|
| 701-01-I |
cross drain pipe (24" rcp/pcp)
|
32   |
LNFT |
250.00 |
8,000.00 |
125.00 |
4,000.00 |
110.00 |
3,520.00 |
|
|
| 701-01-K |
cross drain pipe (30" rcp/pcp)
|
72   |
LNFT |
325.00 |
23,400.00 |
145.00 |
10,440.00 |
130.00 |
9,360.00 |
|
|
| 701-01-N |
cross drain pipe (42" rcp/pcp)
|
144   |
LNFT |
300.00 |
43,200.00 |
210.00 |
30,240.00 |
200.00 |
28,800.00 |
|
|
| 701-05-I |
side drain pipe (24")
|
48   |
LNFT |
150.00 |
7,200.00 |
100.00 |
4,800.00 |
110.00 |
5,280.00 |
|
|
| 701-05-N |
side drain pipe (42")
|
80   |
LNFT |
170.00 |
13,600.00 |
175.00 |
14,000.00 |
220.00 |
17,600.00 |
|
|
| 701-08 |
relaying pipe
|
8   |
LNFT |
200.00 |
1,600.00 |
200.00 |
1,600.00 |
220.00 |
1,760.00 |
|
|
| 701-15 |
concrete collar
|
9   |
EACH |
1,000.00 |
9,000.00 |
900.00 |
8,100.00 |
2,000.00 |
18,000.00 |
|
|
| 704-11-A |
guard rail end treatment (flared)
|
3   |
EACH |
2,300.00 |
6,900.00 |
3,500.00 |
10,500.00 |
2,500.00 |
7,500.00 |
|
|
| 712-04 |
flexible revetment
|
60   |
SQYD |
90.00 |
5,400.00 |
100.00 |
6,000.00 |
85.00 |
5,100.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
7,500.00 |
7,500.00 |
60,000.00 |
60,000.00 |
13,000.00 |
13,000.00 |
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
14.035 |
MILE |
50.00 |
701.75 |
300.00 |
4,210.50 |
150.00 |
2,105.25 |
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
5.782 |
MILE |
50.00 |
289.10 |
250.00 |
1,445.50 |
300.00 |
1,734.60 |
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
31.214 |
MILE |
250.00 |
7,803.50 |
300.00 |
9,364.20 |
500.00 |
15,607.00 |
|
|
| 716-01-A |
mulch (vegetative)
|
1.0 |
TON |
1,000.00 |
1,000.00 |
1,000.00 |
1,000.00 |
1,100.00 |
1,100.00 |
|
|
| 717-01 |
seeding
|
15   |
LB |
20.00 |
300.00 |
40.00 |
600.00 |
22.00 |
330.00 |
|
|
| 718-01 |
fertilizer
|
500   |
LB |
2.00 |
1,000.00 |
3.00 |
1,500.00 |
3.00 |
1,500.00 |
|
|
| 722-01 |
project site laboratory
|
1   |
EACH |
5,500.00 |
5,500.00 |
5,000.00 |
5,000.00 |
45,000.00 |
45,000.00 |
|
|
| 726-01 |
bedding material
|
100.0 |
CUYD |
72.00 |
7,200.00 |
100.00 |
10,000.00 |
165.00 |
16,500.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
55,000.00 |
55,000.00 |
65,000.00 |
65,000.00 |
115,000.00 |
115,000.00 |
|
|
| 729-16-B |
object marker assembly (type 2)
|
13   |
EACH |
75.00 |
975.00 |
100.00 |
1,300.00 |
85.00 |
1,105.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
618   |
EACH |
5.00 |
3,090.00 |
8.00 |
4,944.00 |
5.00 |
3,090.00 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
15   |
LNFT |
3.00 |
45.00 |
50.00 |
750.00 |
3.50 |
52.50 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
10.405 |
MILE |
2,000.00 |
20,810.00 |
2,900.00 |
30,174.50 |
2,200.00 |
22,891.00 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
1.927 |
MILE |
600.00 |
1,156.20 |
1,500.00 |
2,890.50 |
650.00 |
1,252.55 |
|
|
| 735-01 |
mailboxes
|
47   |
EACH |
5.00 |
235.00 |
1.00 |
47.00 |
1.00 |
47.00 |
|
|
| 735-02 |
mailbox supports (single)
|
45   |
EACH |
110.00 |
4,950.00 |
120.00 |
5,400.00 |
125.00 |
5,625.00 |
|
|
| 735-03 |
mailbox supports (double)
|
2   |
EACH |
150.00 |
300.00 |
200.00 |
400.00 |
160.00 |
320.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
7,500.00 |
7,500.00 |
50,000.00 |
50,000.00 |
20,000.00 |
20,000.00 |
|
|
| S-001 |
cleaning existing ditches
|
600   |
LNFT |
10.00 |
6,000.00 |
10.00 |
6,000.00 |
30.00 |
18,000.00 |
|
|
| S-002 |
saw cutting
|
808   |
INFT |
2.60 |
2,100.80 |
10.00 |
8,080.00 |
1.50 |
1,212.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,967,706.24 |
|
2,404,325.66 |
|
2,506,272.85 |
|
|
|