| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - RCS CONTRACTORS, INC. |
|
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
20,000.00 |
20,000.00 |
|
|
|
|
|
|
| 202-02-C |
removal of portland cement concrete pavement
|
515   |
SQYD |
15.00 |
7,725.00 |
|
|
|
|
|
|
| 202-02-E |
removal of concrete curbs
|
701.0 |
LNFT |
5.00 |
3,505.00 |
|
|
|
|
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
2,124.2 |
SQYD |
7.00 |
14,869.40 |
|
|
|
|
|
|
| 202-02-01 |
removal of existing traffic signal equipment & related
items |
lump |
LUMP |
4,812.00 |
4,812.00 |
|
|
|
|
|
|
| 203-01 |
general excavation
|
2,497   |
CUYD |
7.50 |
18,727.50 |
|
|
|
|
|
|
| 203-03 |
embankment
|
1,499   |
CUYD |
25.00 |
37,475.00 |
|
|
|
|
|
|
| 302-02-D |
class ii base course (8 1/2" thick)
|
8,599.0 |
SQYD |
37.50 |
322,462.50 |
|
|
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
1,989.5 |
TON |
145.00 |
288,477.50 |
|
|
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
6,745   |
SQYD |
5.50 |
37,097.50 |
|
|
|
|
|
|
| 510-01 |
pavement patching
|
180   |
SQYD |
165.00 |
29,700.00 |
|
|
|
|
|
|
| 601-01-I |
portland cement concrete pavement (9" thick)
|
5,602.7 |
SQYD |
85.00 |
476,229.50 |
|
|
|
|
|
|
| 602-02 |
cleaning and resealing existing longitudinal and
transverse pavement joints |
762   |
LNFT |
2.00 |
1,524.00 |
|
|
|
|
|
|
| 602-03 |
cleaning and sealing cracks
|
1,750   |
LNFT |
3.50 |
6,125.00 |
|
|
|
|
|
|
| 602-05-I-01 |
full depth patching of jointed conc pvmt (9" thick)
(16.0 sq yds & under) |
229.0 |
SQYD |
175.00 |
40,075.00 |
|
|
|
|
|
|
| 602-05-I-02 |
full depth patching of jointed conc pvmt (9" thick)
(16.1 - 48.0 sq yds) |
459.1 |
SQYD |
169.00 |
77,587.90 |
|
|
|
|
|
|
| 602-05-I-03 |
full depth patching of jointed conc pvmt (9" thick)
(48.1 sq yds & over) |
164.7 |
SQYD |
165.00 |
27,175.50 |
|
|
|
|
|
|
| 701-01-H |
cross drain pipe (21" cmp)
|
60   |
LNFT |
120.00 |
7,200.00 |
|
|
|
|
|
|
| 701-03-F |
storm drain pipe (15" rcp/pcp)
|
8   |
LNFT |
80.00 |
640.00 |
|
|
|
|
|
|
| 701-03-G |
storm drain pipe (18" rcp/pcp)
|
201   |
LNFT |
79.00 |
15,879.00 |
|
|
|
|
|
|
| 701-03-I |
storm drain pipe (24" rcp/pcp)
|
1,116   |
LNFT |
89.00 |
99,324.00 |
|
|
|
|
|
|
| 701-03-K |
storm drain pipe (30" rcp/pcp)
|
16   |
LNFT |
115.00 |
1,840.00 |
|
|
|
|
|
|
| 701-03-O |
storm drain pipe (48" rcp/pcp)
|
14   |
LNFT |
200.00 |
2,800.00 |
|
|
|
|
|
|
| 701-09 |
fabricating pipe fittings
|
6   |
EACH |
3,700.00 |
22,200.00 |
|
|
|
|
|
|
| 701-12-I |
corrugated metal pipe (extension)(24")
|
12   |
LNFT |
80.00 |
960.00 |
|
|
|
|
|
|
| 701-15 |
concrete collar (collar - 01)
|
13   |
EACH |
1,000.00 |
13,000.00 |
|
|
|
|
|
|
| 702-03-A |
catch basins (cb-01)
|
8   |
EACH |
2,250.00 |
18,000.00 |
|
|
|
|
|
|
| 702-03-B |
catch basins (cb-02)
|
1   |
EACH |
4,500.00 |
4,500.00 |
|
|
|
|
|
|
| 702-03-C |
catch basins (cb-06)
|
1   |
EACH |
4,700.00 |
4,700.00 |
|
|
|
|
|
|
| 702-05-A |
cross drain end treatment (type 1 )
|
4   |
EACH |
2,900.00 |
11,600.00 |
|
|
|
|
|
|
| 702-06-A |
side drain end treatment (type 1 )
|
2   |
EACH |
2,700.00 |
5,400.00 |
|
|
|
|
|
|
| 706-02-C |
concrete drive (6" thick)
|
264.0 |
SQYD |
70.00 |
18,480.00 |
|
|
|
|
|
|
| 706-03-B |
incidental concrete paving (5" thick)
|
30.0 |
SQYD |
60.00 |
1,800.00 |
|
|
|
|
|
|
| 707-01 |
concrete curb
|
441.7 |
LNFT |
15.00 |
6,625.50 |
|
|
|
|
|
|
| 707-03 |
combination concrete curb & gutter
|
1,600.0 |
LNFT |
25.00 |
40,000.00 |
|
|
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
31,000.00 |
31,000.00 |
|
|
|
|
|
|
| 713-02-A |
temporary pavement markings (4" width)
|
136   |
LNFT |
11.00 |
1,496.00 |
|
|
|
|
|
|
| 717-01 |
seeding
|
58   |
LB |
10.00 |
580.00 |
|
|
|
|
|
|
| 718-01 |
fertilizer
|
1,650   |
LB |
0.60 |
990.00 |
|
|
|
|
|
|
| 722-01 |
project site laboratory
|
1   |
EACH |
10,000.00 |
10,000.00 |
|
|
|
|
|
|
| 726-01 |
bedding material
|
150.0 |
CUYD |
90.00 |
13,500.00 |
|
|
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
155,244.00 |
155,244.00 |
|
|
|
|
|
|
| 729-01 |
sign (type a)
|
246.4 |
SQFT |
44.00 |
10,841.60 |
|
|
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
185   |
EACH |
5.40 |
999.00 |
|
|
|
|
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
1,030   |
LNFT |
0.66 |
679.80 |
|
|
|
|
|
|
| 732-01-D |
plastic pavement striping (12" width)
|
60   |
LNFT |
1.00 |
60.00 |
|
|
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
1,030   |
LNFT |
2.50 |
2,575.00 |
|
|
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
2.783 |
MILE |
2,035.00 |
5,663.41 |
|
|
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
1.193 |
MILE |
684.00 |
816.01 |
|
|
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
17   |
EACH |
200.00 |
3,400.00 |
|
|
|
|
|
|
| 732-04-B |
plastic pavement legends & symbols (double arrow)
|
5   |
EACH |
215.00 |
1,075.00 |
|
|
|
|
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
6   |
EACH |
215.00 |
1,290.00 |
|
|
|
|
|
|
| 736-01 |
trenching and backfilling
|
3,650   |
LNFT |
4.13 |
15,074.50 |
|
|
|
|
|
|
| 736-03 |
jacked or bored conduit (3" hdpe)
|
1,000   |
LNFT |
21.35 |
21,350.00 |
|
|
|
|
|
|
| 736-04-B |
signal support (35' mast arm pole)
|
3   |
EACH |
10,000.00 |
30,000.00 |
|
|
|
|
|
|
| 736-04-C |
signal support (40' mast arm pole)
|
2   |
EACH |
11,000.00 |
22,000.00 |
|
|
|
|
|
|
| 736-04-D |
signal support (50' mast arm pole)
|
2   |
EACH |
13,000.00 |
26,000.00 |
|
|
|
|
|
|
| 736-04-E |
signal support (45' mast arm pole)
|
1   |
EACH |
12,000.00 |
12,000.00 |
|
|
|
|
|
|
| 736-04-F |
signal support (25' mast arm pole)
|
2   |
EACH |
9,000.00 |
18,000.00 |
|
|
|
|
|
|
| 736-04-G |
signal support (double mast arms 50' and 50'pole)
|
2   |
EACH |
18,000.00 |
36,000.00 |
|
|
|
|
|
|
| 736-05-B |
signal heads (3-section, 12" lens)(r,y,g)
|
24   |
EACH |
867.50 |
20,820.00 |
|
|
|
|
|
|
| 736-05-C |
signal heads (5-section, 12" lens, r, lt.y, y, lt.g, g)
|
5   |
EACH |
1,362.50 |
6,812.50 |
|
|
|
|
|
|
| 736-05-D |
signal heads (4-section, 12" lens, r, y, lt.g, g)
|
2   |
EACH |
1,250.00 |
2,500.00 |
|
|
|
|
|
|
| 736-05-E |
signal heads (3-section, 12" lens, r, lt.y, lt.g)
|
3   |
EACH |
800.00 |
2,400.00 |
|
|
|
|
|
|
| 736-05-F |
signal heads (5-section, 12" lens, r, y, rt.y, g, rt.g)
|
1   |
EACH |
1,362.50 |
1,362.50 |
|
|
|
|
|
|
| 736-06 |
signal service
|
4   |
EACH |
881.25 |
3,525.00 |
|
|
|
|
|
|
| 736-08 |
signal controller
|
3   |
EACH |
25,312.50 |
75,937.50 |
|
|
|
|
|
|
| 736-09 |
loop detector
|
680   |
LNFT |
11.00 |
7,480.00 |
|
|
|
|
|
|
| 736-10-A |
underground junction box(type d)
|
14   |
EACH |
377.50 |
5,285.00 |
|
|
|
|
|
|
| 736-10-B |
underground junction box(type f)
|
23   |
EACH |
377.50 |
8,682.50 |
|
|
|
|
|
|
| 736-10-C |
underground junction box(type h)
|
3   |
EACH |
900.00 |
2,700.00 |
|
|
|
|
|
|
| 736-10-D |
underground junction box(type j)
|
3   |
EACH |
1,200.00 |
3,600.00 |
|
|
|
|
|
|
| 736-11-A |
conduit (1" hdpe)
|
2,304   |
LNFT |
3.50 |
8,064.00 |
|
|
|
|
|
|
| 736-11-B |
conduit (2" hdpe)
|
195   |
LNFT |
4.30 |
838.50 |
|
|
|
|
|
|
| 736-11-C |
conduit (3" hdpe)
|
1,920   |
LNFT |
6.45 |
12,384.00 |
|
|
|
|
|
|
| 736-11-D |
conduit (4" hdpe)
|
10   |
LNFT |
9.00 |
90.00 |
|
|
|
|
|
|
| 736-12-A |
conductor (2c loop lead-in, 14 awg, 19x27 class c)
|
2,850   |
LNFT |
1.50 |
4,275.00 |
|
|
|
|
|
|
| 736-12-B |
conductor (3c signal, 14awg, stranded)
|
870   |
LNFT |
1.40 |
1,218.00 |
|
|
|
|
|
|
| 736-12-C |
conductor (6c, signal, 14 awg, stranded)
|
2,592   |
LNFT |
2.00 |
5,184.00 |
|
|
|
|
|
|
| 736-12-D |
conductor (10c, signal, 14 awg, stranded)
|
6,415   |
LNFT |
2.50 |
16,037.50 |
|
|
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
15,000.00 |
15,000.00 |
|
|
|
|
|
|
| S-001 |
full-depth sawcut pavement
|
205   |
LNFT |
10.00 |
2,050.00 |
|
|
|
|
|
|
| S-002 |
paved gutter drains
|
6   |
EACH |
2,750.00 |
16,500.00 |
|
|
|
|
|
|
| S-003 |
video detection system
|
4   |
EACH |
4,350.00 |
17,400.00 |
|
|
|
|
|
|
| S-004 |
video detector device and connection
|
12   |
EACH |
7,262.00 |
87,144.00 |
|
|
|
|
|
|
| S-005 |
conductor, fiber optic signal interconnect trunk line
cable (36 sm) |
1,400   |
LNFT |
5.10 |
7,140.00 |
|
|
|
|
|
|
| S-006 |
fiber optic drop cable, 12 fiber, (single mode)
|
30   |
LNFT |
8.00 |
240.00 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
2,443,821.12 |
|
|
|
|
|
|
|