Letting of 5/28/2008 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 335-02-0017
Parish: CLAIBORNE
Routes: LA 540
Description: 0.57 MILES WEST OF JUNCTION US 79 - JUNCTION LA 534
Type Const: drainage structures, in-place cement treated base course, superpave asphaltic concrete
overlay, and related work
Estimated Construction Cost: $2,425,267.73
 
RankLicenseBidderConstruction Bid
1 08584 MADDEN CONTRACTING CO., INC. $2,660,664.79
 
Item Number Item Description Quantity Unit of Measure - 1 -
MADDEN CONTRACTING CO., INC.

 

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-02-D removal of concrete walks & drives 64      SQYD 20.00 1,280.00            
202-02-H removal of guard rail 330      LNFT 6.00 1,980.00            
202-02-I removal of culvert pipe 96      LNFT 10.00 960.00            
202-02-J removal of asphaltic surfacing from bridge deck 228      SQYD 15.00 3,420.00            
203-07 borrow (vehicular measurement) 8,000      CUYD 14.00 112,000.00            
203-07-A borrow (vehicular meas.)(selected soils) 4,000      CUYD 14.00 56,000.00            
303-02 removal of existing patches 400      SQYD 10.00 4,000.00            
308-01-A in-place cement treated base course (12" thick) 112,152      SQYD 8.55 958,899.60            
401-02 aggregate surface course (adjusted vehicular
measurement)
570      CUYD 1.00 570.00            
502-01 superpave asphaltic concrete 12,744.0    TON 84.60 1,078,142.40            
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
675.0    TON 55.00 37,125.00            
701-08 relaying pipe 44      LNFT 150.00 6,600.00            
701-10-I reinforced concrete pipe (extension)(24") 8      LNFT 200.00 1,600.00            
701-15 concrete collar 7      EACH 975.00 6,825.00            
704-01-A guard rail (single thrie beam)(3'-1 1/2" post spacing) 100.0    LNFT 50.00 5,000.00            
704-01-B guard rail (single thrie beam)(6'-3" post spacing) 114.0    LNFT 59.00 6,726.00            
704-03 blocked out guard rail 100.0    LNFT 20.00 2,000.00            
704-11-A guard rail end treatment (flared) 4      EACH 2,100.00 8,400.00            
712-02 sacked concrete revetment 60      SQYD 80.00 4,800.00            
712-03 stone revetment 260      SQYD 80.00 20,800.00            
713-01 temporary signs & barricades lump      LUMP 97,100.00 97,100.00            
713-02-E temporary pavement markings (24" width) 60      LNFT 0.90 54.00            
713-03-A temporary pavement markings (broken line)(4" width)(4'
length)
8.782  MILE 400.00 3,512.80            
713-03-B temporary pavement markings (broken line)(4" width)
(10' length)
1.750  MILE 1.00 1.75            
713-04-A temporary pavement markings (solid line)(4" width) 28.242  MILE 1.00 28.24            
716-01-A mulch (vegetative) 32.4    TON 600.00 19,440.00            
722-02 project site laboratory (equipped) 1      EACH 2,500.00 2,500.00            
727-01 mobilization lump      LUMP 97,100.00 97,100.00            
729-16-C object marker assembly (type 3) 4      EACH 75.00 300.00            
731-02 reflectorized raised pavement markers 1,008      EACH 4.50 4,536.00            
732-01-E plastic pavement striping (24" width) 60      LNFT 3.00 180.00            
732-02-A plastic pavement striping (solid line) (4" width) 28.242  MILE 2,500.00 70,605.00            
732-03-A plastic pavement striping (broken line)(4" width) 1.750  MILE 700.00 1,225.00            
739-01 hydro-seeding 18.52   ACRE 1,200.00 22,224.00            
740-01 construction layout lump      LUMP 22,450.00 22,450.00            
S-001 saw cutting existing concrete drives 190      LNFT 12.00 2,280.00            
                       
 CONTRACTOR TOTAL       2,660,664.79            