Letting of 3/26/2008 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 001-05-0017
Parish: WEBSTER
Routes: US 79, US 80
Description: MINDEN SIDEWALK IMPROVEMENTS
Type Const: class ii bc, concrete walks and drives, street lights, water system, sewer system,
brick pavers, additive alternate a1, bi, and c1, and related work.
Estimated Construction Cost: $903,422.75
 
RankLicenseBidderConstruction Bid
1 18546 C W & W CONTRACTORS, INC. $1,393,615.75
2 28218 F. J. BURNELL, INC. $1,787,223.25
3 44289 JEFF MERCER LLC $2,400,088.25
 37477 VANTEL, INC IRREGULAR
 
Item Number Item Description Quantity Unit of Measure - 1 -
C W & W CONTRACTORS, INC.
- 2 -
F. J. BURNELL, INC.
- 3 -
JEFF MERCER LLC

VANTEL, INC
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-01 removal of structures and obstructions lump      LUMP 10,000.00 10,000.00 65,000.00 65,000.00 20,000.00 20,000.00 10,000.00 10,000.00
202-02-C removal of portland cement concrete pavement 265      SQYD 10.00 2,650.00 20.00 5,300.00 15.00 3,975.00 15.00 3,975.00
202-02-D removal of concrete walks & drives 1,850      SQYD 5.00 9,250.00 12.00 22,200.00 20.00 37,000.00 15.00 27,750.00
202-02-F removal of concrete combination curb & gutter 2,575.0    LNFT 5.00 12,875.00 10.00 25,750.00 5.00 12,875.00 9.00 23,175.00
203-05 excavation and embankment lump      LUMP 15,000.00 15,000.00 35,000.00 35,000.00 35,000.00 35,000.00 2,500.00 2,500.00
302-02-A class ii base course (4" thick) 1,565.0    SQYD 10.00 15,650.00 30.00 46,950.00 30.00 46,950.00 16.00 25,040.00
302-02-B class ii base course (6" thick) 975.0    SQYD 15.00 14,625.00 40.00 39,000.00 35.00 34,125.00 24.00 23,400.00
510-01-B pavement patching (12" minimum thickness) 70      SQYD 135.00 9,450.00 225.00 15,750.00 250.00 17,500.00 100.00 7,000.00
702-04-A adjusting manholes 6      EACH 500.00 3,000.00 1,500.00 9,000.00 4,000.00 24,000.00 1,000.00 6,000.00
706-01-B concrete walk (5" thick) 1,340.0    SQYD 70.00 93,800.00 65.00 87,100.00 125.00 167,500.00 60.00 80,400.00
706-02-C concrete drive (6" thick) 435.0    SQYD 70.00 30,450.00 75.00 32,625.00 125.00 54,375.00 93.00 40,455.00
707-03 combination concrete curb & gutter 2,800.0    LNFT 30.00 84,000.00 40.00 112,000.00 50.00 140,000.00 22.00 61,600.00
713-01 temporary signs & barricades lump      LUMP 20,000.00 20,000.00 100,000.00 100,000.00 15,000.00 15,000.00 15,000.00 15,000.00
727-01 mobilization lump      LUMP 100,000.00 100,000.00 140,000.00 140,000.00 160,000.00 160,000.00 98,500.00 98,500.00
729-01 sign (type a) 85.0    SQFT 50.00 4,250.00 60.00 5,100.00 100.00 8,500.00 500.00 42,500.00
729-02 sign (type b) 30.0    SQFT 50.00 1,500.00 60.00 1,800.00 100.00 3,000.00 500.00 15,000.00
730-01 trenching and backfilling 1,885      LNFT 3.50 6,597.50 4.60 8,671.00 3.45 6,503.25 20.00 37,700.00
730-02-A conduit with conductors (2#8 xhhw-2, 1#8 bare solid
ground in 1 1/4" sch 40 pvc, underground)
580      LNFT 6.50 3,770.00 17.00 9,860.00 7.00 4,060.00 5.00 2,900.00
730-02-B conduit with conductors (2#6 xhhw-2, 1#6 bare solid
ground in 1 1/4" sch 40 pvc, underground)
1,800      LNFT 7.25 13,050.00 18.25 32,850.00 7.50 13,500.00 6.00 10,800.00
730-02-C conduit with conductors (4#6 xhhw-2, 1#6 bare solid
ground in 1 1/4" sch 40 pvc, underground)
600      LNFT 11.50 6,900.00 25.00 15,000.00 10.50 6,300.00 9.00 5,400.00
730-02-D conduit with conductors (2#3 xhhw-2, 1#3 bare solid
ground in 1 1/2" sch 40 pvc, underground)
100      LNFT 14.50 1,450.00 27.00 2,700.00 14.00 1,400.00 10.00 1,000.00
730-04 jacked or bored casing (6", sch 80 pvc) 210      LNFT 35.00 7,350.00 71.00 14,910.00 35.00 7,350.00 65.00 13,650.00
730-08 electrical service point (service entrance) 2      EACH 2,500.00 5,000.00 2,100.00 4,200.00 2,500.00 5,000.00 3,000.00 6,000.00
730-16 underground junction box (12" x 12" x 8" min) 10      EACH 400.00 4,000.00 350.00 3,500.00 400.00 4,000.00 1,000.00 10,000.00
730-17 structure junction box (12" x 12" x 8" min) 11      EACH 600.00 6,600.00 685.00 7,535.00 525.00 5,775.00 1,500.00 16,500.00
730-18 service pole 2      EACH 1,200.00 2,400.00 575.00 1,150.00 1,050.00 2,100.00 2,500.00 5,000.00
731-02 reflectorized raised pavement markers 22      EACH 10.00 220.00 6.00 132.00 55.00 1,210.00 55.00 1,210.00
732-04-A plastic pavement legends & symbols (arrow) 2      EACH 400.00 800.00 200.00 400.00 450.00 900.00 440.00 880.00
732-04-C plastic pavement legends & symbols (only) 2      EACH 400.00 800.00 225.00 450.00 450.00 900.00 440.00 880.00
737-02-A painted traffic striping (broken line)(4" width) 0.050  MILE 500.00 25.00 500.00 25.00 1,200.00 60.00 1,500.00 75.00
737-03-A painted traffic striping (solid line)(4" width) 3,065      LNFT 0.30 919.50 0.20 613.00 1.25 3,831.25 1.10 3,371.50
737-03-C painted traffic striping (solid line)(8" width) 150      LNFT 1.00 150.00 0.50 75.00 0.50 75.00 0.35 52.50
737-03-D painted traffic striping (solid line)(12" width) 620      LNFT 1.00 620.00 0.60 372.00 1.00 620.00 2.00 1,240.00
737-03-E painted traffic striping (solid line)(24" width) 80      LNFT 5.00 400.00 2.00 160.00 3.50 280.00 3.30 264.00
740-01 construction layout lump      LUMP 20,000.00 20,000.00 24,000.00 24,000.00 50,000.00 50,000.00 15,000.00 15,000.00
741-01-A water main (8" c900 sdr 19) 373      LNFT 75.00 27,975.00 165.00 61,545.00 65.00 24,245.00 50.00 18,650.00
741-01-B water main (12" c900 sdr 19) 412      LNFT 100.00 41,200.00 175.00 72,100.00 115.00 47,380.00 59.00 24,308.00
741-04 fire hydrant 2      EACH 3,500.00 7,000.00 3,500.00 7,000.00 6,800.00 13,600.00 5,000.00 10,000.00
741-05 water service line (1" copper, type k) 1,000      LNFT 15.00 15,000.00 15.00 15,000.00 48.00 48,000.00 10.00 10,000.00
741-11 adjusting water valve and meter box 15      EACH 500.00 7,500.00 700.00 10,500.00 1,570.00 23,550.00 500.00 7,500.00
741-13 removing fire hydrant 2      EACH 1,500.00 3,000.00 575.00 1,150.00 2,600.00 5,200.00 1,000.00 2,000.00
742-01 sanitary sewer pipe (4" c900 sdr 35) 1,000      LNFT 15.00 15,000.00 15.00 15,000.00 25.00 25,000.00 18.00 18,000.00
805-01 class a concrete 15.00   CUYD 1,200.00 18,000.00 1,500.00 22,500.00 1,500.00 22,500.00 200.00 3,000.00
S-001 brick pavers 2,505      SQFT 16.00 40,080.00 12.50 31,312.50 48.00 120,240.00 15.00 37,575.00
S-002 temporary business entrances lump      LUMP 20,000.00 20,000.00 1,000.00 1,000.00 8,000.00 8,000.00 1,500.00 1,500.00
S-003 decorative street light assembly 35      EACH 5,700.00 199,500.00 4,300.00 150,500.00 5,500.00 192,500.00 5,300.00 185,500.00
S-004 sawcut (per 1" depth) 34,135      INFT 2.00 68,270.00 2.00 68,270.00 5.00 170,675.00 6.00 204,810.00
S-005 sidewalk drain cover 7      EACH 500.00 3,500.00 1,200.00 8,400.00 500.00 3,500.00 500.00 3,500.00
S-006 roof drain downspouts 4      EACH 500.00 2,000.00 1,200.00 4,800.00 1,000.00 4,000.00 1,000.00 4,000.00
S-007 utility access cover 2      EACH 1,000.00 2,000.00 10,000.00 20,000.00 5,000.00 10,000.00 1,500.00 3,000.00
S-008 manhole rehabilitation 6      EACH 5,000.00 30,000.00 4,600.00 27,600.00 3,800.00 22,800.00 1,000.00 6,000.00
S-009 sewer main cured-in-place liner (8") 700      LNFT 100.00 70,000.00 70.00 49,000.00 95.00 66,500.00 60.00 42,000.00
S-010 adjusting gas valves and meters 4      EACH 500.00 2,000.00 200.00 800.00 1,000.00 4,000.00 200.00 800.00
S-011 adjusting sewer cleanouts 2      EACH 500.00 1,000.00 300.00 600.00 1,375.00 2,750.00 250.00 500.00
S-012 wheel stops 6      EACH 200.00 1,200.00 150.00 900.00 750.00 4,500.00 250.00 1,500.00
 SUBTOTAL GENERAL       1,081,777.00   1,437,155.50   1,712,604.50   1,198,361.00
                       
ALTERNATE A additive alternate a1                    
                       
ALTERNATE A1                      
202-01-A removal of structures and obstructions (add alt a1) lump      LUMP 5,000.00 5,000.00 10,000.00 10,000.00 25,000.00 25,000.00 10,000.00 10,000.00
202-02-D-A removal of concrete walks & drives (add alt a1) 425      SQYD 5.00 2,125.00 12.00 5,100.00 15.00 6,375.00 15.00 6,375.00
202-02-F-A removal of concrete combination curb & gutter (add alt
a1)
540.0    LNFT 5.00 2,700.00 10.00 5,400.00 5.00 2,700.00 9.00 4,860.00
203-05-A excavation and embankment (add alt a1) lump      LUMP 3,000.00 3,000.00 5,000.00 5,000.00 25,000.00 25,000.00 2,000.00 2,000.00
302-02-A-A class ii base course (4" thick)(add alt a1) 425.0    SQYD 10.00 4,250.00 30.00 12,750.00 40.00 17,000.00 16.00 6,800.00
302-02-B-A class ii base course (6" thick)(add alt a1) 120.0    SQYD 15.00 1,800.00 40.00 4,800.00 50.00 6,000.00 24.00 2,880.00
702-04-A-A adjusting manholes (add alt a1) 1      EACH 500.00 500.00 1,500.00 1,500.00 8,000.00 8,000.00 1,000.00 1,000.00
706-01-B-A concrete walk (5" thick)(add alt a1) 355.0    SQYD 70.00 24,850.00 65.00 23,075.00 125.00 44,375.00 60.00 21,300.00
707-03-A combination concrete curb & gutter (add alt a1) 540.0    LNFT 30.00 16,200.00 40.00 21,600.00 50.00 27,000.00 22.00 11,880.00
713-01-A temporary signs & barricades (add alt a1) lump      LUMP 5,000.00 5,000.00 3,000.00 3,000.00 4,500.00 4,500.00 10,000.00 10,000.00
729-01-A sign (type a)(add alt a1) 5.0    SQFT 50.00 250.00 60.00 300.00 100.00 500.00 500.00 2,500.00
729-02-A sign (type b)(add alt a1) 15.0    SQFT 50.00 750.00 60.00 900.00 100.00 1,500.00 500.00 7,500.00
730-01-A trenching and backfilling (add alt a1) 500      LNFT 3.50 1,750.00 4.60 2,300.00 3.50 1,750.00 20.00 10,000.00
730-02-A-A conduit with conductors (2#8 xhhw-2, 1#8 bare solid
ground in 1 1/4" sch 40 pvc, underground)(add alt
a1)
300      LNFT 6.50 1,950.00 17.00 5,100.00 6.00 1,800.00 5.00 1,500.00
730-02-B-A conduit with conductors (2#6 xhhw-2, 1#6 bare solid
ground in 1 1/4" sch 40 pvc, underground)(add alt
a1)
360      LNFT 7.25 2,610.00 18.25 6,570.00 7.00 2,520.00 6.00 2,160.00
730-04-A jacked or bored casing (6", sch 80 pvc)(add alt a1) 40      LNFT 35.00 1,400.00 71.00 2,840.00 35.00 1,400.00 65.00 2,600.00
730-16-A underground junction box (12" x 12" x 8" min) (add alt
a1)
2      EACH 400.00 800.00 350.00 700.00 375.00 750.00 1,000.00 2,000.00
730-17-A structure junction box (12" x 12" x 8" min)(add alt a1) 1      EACH 600.00 600.00 685.00 685.00 600.00 600.00 1,500.00 1,500.00
737-03-A-A painted traffic striping (solid line)(4" width)(add
alt a1)
250      LNFT 1.00 250.00 0.75 187.50 2.00 500.00 1.20 300.00
737-03-D-A painted traffic striping (solid line)(12" width)(add
alt a1)
75      LNFT 2.00 150.00 2.00 150.00 2.00 150.00 2.00 150.00
737-03-E-A painted traffic striping (solid line)(24" width)(add
alt a1)
15      LNFT 5.00 75.00 5.00 75.00 4.00 60.00 3.50 52.50
740-01-A construction layout (add alt a1) lump      LUMP 5,000.00 5,000.00 3,000.00 3,000.00 6,500.00 6,500.00 15,000.00 15,000.00
S-001-A brick pavers (add alt a1) 605      SQFT 16.00 9,680.00 12.50 7,562.50 48.00 29,040.00 15.00 9,075.00
S-003-A decorative street light assembly (add alt a1) 10      EACH 5,700.00 57,000.00 4,300.00 43,000.00 5,500.00 55,000.00 5,300.00 53,000.00
S-004-A sawcut (per 1" depth)(add alt a1) 5,380      LNFT 2.00 10,760.00 2.00 10,760.00 5.00 26,900.00 9.00 48,420.00
S-005-A sidewalk drain cover (add alt a1) 2      EACH 500.00 1,000.00 1,200.00 2,400.00 500.00 1,000.00 500.00 1,000.00
 SUBTOTAL ALT A1       159,450.00   178,755.00   295,920.00   233,852.50
                       
ALTERNATE B additive alternate b1                    
                       
ALTERNATE B1                      
202-01-B removal of structures and obstructions (add alt b1) lump      LUMP 4,000.00 4,000.00 10,000.00 10,000.00 25,000.00 25,000.00 10,000.00 10,000.00
202-02-D-B removal of concrete walks & drives (add alt b1) 220      SQYD 5.00 1,100.00 12.00 2,640.00 10.00 2,200.00 15.00 3,300.00
202-02-F-B removal of concrete combination curb & gutter (add alt
b1)
215.0    LNFT 5.00 1,075.00 10.00 2,150.00 5.00 1,075.00 9.00 1,935.00
203-05-B excavation and embankment (add alt b1) lump      LUMP 2,000.00 2,000.00 5,000.00 5,000.00 25,000.00 25,000.00 300.00 300.00
302-02-A-B class ii base course (4" thick)(add alt b1) 50.0    SQYD 10.00 500.00 30.00 1,500.00 40.00 2,000.00 16.00 800.00
302-02-B-B class ii base course (6" thick)(add alt b1) 220.0    SQYD 15.00 3,300.00 40.00 8,800.00 45.00 9,900.00 24.00 5,280.00
702-04-A-B adjusting manholes (add alt b1) 1      EACH 500.00 500.00 1,500.00 1,500.00 8,000.00 8,000.00 1,000.00 1,000.00
706-01-B-B concrete walk (5" thick)(add alt b1) 200.0    SQYD 70.00 14,000.00 65.00 13,000.00 200.00 40,000.00 60.00 12,000.00
707-03-B combination concrete curb & gutter (add alt b1) 220.0    LNFT 30.00 6,600.00 40.00 8,800.00 50.00 11,000.00 22.00 4,840.00
713-01-B temporary signs & barricades (add alt b1) lump      LUMP 5,000.00 5,000.00 3,000.00 3,000.00 7,500.00 7,500.00 10,000.00 10,000.00
729-01-B sign (type a)(add alt b1) 6.0    SQFT 50.00 300.00 60.00 360.00 100.00 600.00 500.00 3,000.00
730-01-B trenching and backfilling (add alt b1) 225      LNFT 3.50 787.50 4.60 1,035.00 3.75 843.75 20.00 4,500.00
730-02-B-B conduit with conductors (2#6 xhhw-2, 1#6 bare solid
ground in 1 1/4" sch 40 pvc, underground)(add alt
b1)
225      LNFT 7.25 1,631.25 18.25 4,106.25 65.00 14,625.00 6.00 1,350.00
730-04-B jacked or bored casing (6", sch 80 pvc)(add alt b1) 40      LNFT 35.00 1,400.00 71.00 2,840.00 40.00 1,600.00 65.00 2,600.00
730-16-B underground junction box (12" x 12" x 8" min) (add alt
b1)
2      EACH 400.00 800.00 350.00 700.00 450.00 900.00 1,000.00 2,000.00
737-03-A-B painted traffic striping (solid line)(4" width)(add
alt b1)
210      LNFT 1.00 210.00 0.75 157.50 2.00 420.00 1.10 231.00
740-01-B construction layout (add alt b1) lump      LUMP 5,000.00 5,000.00 3,000.00 3,000.00 7,500.00 7,500.00 10,000.00 10,000.00
S-001-B brick pavers (add alt b1) 210      SQFT 16.00 3,360.00 12.50 2,625.00 48.00 10,080.00 15.00 3,150.00
S-002-B temporary business entrances (add alt b1) lump      LUMP 5,000.00 5,000.00 1,000.00 1,000.00 30,000.00 30,000.00 9,000.00 9,000.00
S-003-B decorative street light assembly (add alt b1) 3      EACH 5,700.00 17,100.00 4,300.00 12,900.00 5,500.00 16,500.00 5,300.00 15,900.00
S-004-B sawcut (per 1" depth)(add alt b1) 2,130      LNFT 2.00 4,260.00 2.00 4,260.00 6.00 12,780.00 9.00 19,170.00
 SUBTOTAL ALT B1       77,923.75   89,373.75   227,523.75   120,356.00
                       
ALTERNATE C additive alternate c1                    
                       
ALTERNATE C1                      
202-01-C removal of structures and obstructions (add alt c1) lump      LUMP 3,000.00 3,000.00 5,000.00 5,000.00 25,000.00 25,000.00 10,000.00 10,000.00
202-02-D-C removal of concrete walks & drives (add alt c1) 120      SQYD 5.00 600.00 12.00 1,440.00 10.00 1,200.00 15.00 1,800.00
202-02-F-C removal of concrete combination curb & gutter (add alt
c1)
225.0    LNFT 5.00 1,125.00 10.00 2,250.00 5.00 1,125.00 12.00 2,700.00
203-05-C excavation and embankment (add alt c1) lump      LUMP 2,000.00 2,000.00 5,000.00 5,000.00 25,000.00 25,000.00 300.00 300.00
302-02-A-C class ii base course (4" thick)(add alt c1) 120.0    SQYD 10.00 1,200.00 30.00 3,600.00 40.00 4,800.00 16.00 1,920.00
302-02-B-C class ii base course (6" thick)(add alt c1) 50.0    SQYD 15.00 750.00 40.00 2,000.00 45.00 2,250.00 24.00 1,200.00
706-01-B-C concrete walk (5" thick)(add alt c1) 100.0    SQYD 70.00 7,000.00 65.00 6,500.00 150.00 15,000.00 60.00 6,000.00
707-03-C combination concrete curb & gutter (add alt c1) 225.0    LNFT 30.00 6,750.00 40.00 9,000.00 50.00 11,250.00 22.00 4,950.00
713-01-C temporary signs & barricades (add alt c1) lump      LUMP 5,000.00 5,000.00 3,000.00 3,000.00 9,000.00 9,000.00 10,000.00 10,000.00
730-01-C trenching and backfilling (add alt c1) 190      LNFT 3.50 665.00 4.60 874.00 3.50 665.00 20.00 3,800.00
730-02-A-C conduit with conductors (2#8 xhhw-2, 1#8 bare solid
ground in 1 1/4" sch 40 pvc, underground)(add alt
c1)
250      LNFT 6.50 1,625.00 17.00 4,250.00 6.00 1,500.00 5.00 1,250.00
730-04-C jacked or bored casing (6", sch 80 pvc)(add alt c1) 100      LNFT 35.00 3,500.00 71.00 7,100.00 35.00 3,500.00 65.00 6,500.00
730-16-C underground junction box (12" x 12" x 8" min) (add alt
c1)
2      EACH 400.00 800.00 350.00 700.00 400.00 800.00 1,000.00 2,000.00
740-01-C construction layout (add alt c1) lump      LUMP 5,000.00 5,000.00 3,000.00 3,000.00 8,500.00 8,500.00 10,000.00 10,000.00
741-04-C fire hydrant (add alt c1) 1      EACH 3,500.00 3,500.00 3,500.00 3,500.00 6,500.00 6,500.00 5,000.00 5,000.00
741-13-C removing fire hydrant (add alt c1) 1      EACH 1,500.00 1,500.00 575.00 575.00 3,000.00 3,000.00 1,500.00 1,500.00
S-001-C brick pavers (add alt c1) 200      SQFT 16.00 3,200.00 12.50 2,500.00 48.00 9,600.00 15.00 3,000.00
S-003-C decorative street light assembly (add alt c1) 4      EACH 5,700.00 22,800.00 4,300.00 17,200.00 5,500.00 22,000.00 5,300.00 21,200.00
S-004-C sawcut (per 1" depth)(add alt c1) 2,225      LNFT 2.00 4,450.00 2.00 4,450.00 6.00 13,350.00 9.00 20,025.00
 SUBTOTAL ALT C1       74,465.00   81,939.00   164,040.00   113,145.00
                       
 CONTRACTOR TOTAL       1,393,615.75   1,787,223.25   2,400,088.25   IRREGULAR