| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BARRIERE CONSTRUCTION CO., LLC. |
- 2 - CERES ENVIRONMENTAL SERVICES,INC. |
- 3 - BOH BROS. CONSTRUCTION CO., LLC. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-D |
removal of concrete walks & drives
|
173   |
SQYD |
15.00 |
2,595.00 |
6.25 |
1,081.25 |
10.00 |
1,730.00 |
|
|
| 202-02-F |
removal of concrete combination curb & gutter
|
500.0 |
LNFT |
15.00 |
7,500.00 |
10.00 |
5,000.00 |
10.00 |
5,000.00 |
|
|
| 202-02-H |
removal of guard rail
|
125   |
LNFT |
10.00 |
1,250.00 |
5.00 |
625.00 |
20.00 |
2,500.00 |
|
|
| 203-05 |
excavation and embankment
|
lump |
LUMP |
30,000.00 |
30,000.00 |
121,250.00 |
121,250.00 |
75,000.00 |
75,000.00 |
|
|
| 203-07 |
borrow (vehicular measurement)
|
330   |
CUYD |
20.00 |
6,600.00 |
26.25 |
8,662.50 |
65.00 |
21,450.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
1,664.5 |
TON |
175.00 |
291,287.50 |
200.00 |
332,900.00 |
140.00 |
233,030.00 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
91.4 |
TON |
175.00 |
15,995.00 |
250.00 |
22,850.00 |
200.00 |
18,280.00 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
11,413   |
SQYD |
3.90 |
44,510.70 |
7.50 |
85,597.50 |
4.00 |
45,652.00 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 476   |
CUYD |
1.00 |
- 476.00 |
FREE |
FREE |
2.00 |
- 952.00 |
|
|
| 510-01-A |
pavement patching (6" minimum thickness)
|
25   |
SQYD |
100.00 |
2,500.00 |
100.00 |
2,500.00 |
140.00 |
3,500.00 |
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
130   |
SQYD |
100.00 |
13,000.00 |
150.00 |
19,500.00 |
180.00 |
23,400.00 |
|
|
| 701-02-D |
cross drain pipe arch (24" equiv. rcpa)
|
130   |
LNFT |
180.00 |
23,400.00 |
162.50 |
21,125.00 |
385.00 |
50,050.00 |
|
|
| 701-06-D |
side drain pipe arch (24" equiv.)
|
145   |
LNFT |
150.00 |
21,750.00 |
162.50 |
23,562.50 |
320.00 |
46,400.00 |
|
|
| 702-03-A |
catch basins (cb-01)
|
3   |
EACH |
5,900.00 |
17,700.00 |
2,500.00 |
7,500.00 |
6,500.00 |
19,500.00 |
|
|
| 704-01-C |
guard rail (double thrie beam)(3'-1 1/2" post spacing)
|
72.0 |
LNFT |
65.00 |
4,680.00 |
85.00 |
6,120.00 |
70.00 |
5,040.00 |
|
|
| 704-03 |
blocked out guard rail
|
200.0 |
LNFT |
24.00 |
4,800.00 |
26.25 |
5,250.00 |
20.00 |
4,000.00 |
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
50.0 |
LNFT |
70.00 |
3,500.00 |
62.50 |
3,125.00 |
60.00 |
3,000.00 |
|
|
| 704-11-A |
guard rail end treatment (flared)
|
1   |
EACH |
3,400.00 |
3,400.00 |
3,750.00 |
3,750.00 |
2,500.00 |
2,500.00 |
|
|
| 704-11-B |
guard rail end treatment (tangent)
|
1   |
EACH |
3,900.00 |
3,900.00 |
4,375.00 |
4,375.00 |
2,800.00 |
2,800.00 |
|
|
| 706-03-A |
incidental concrete paving (4" thick)
|
258.4 |
SQYD |
70.00 |
18,088.00 |
75.00 |
19,380.00 |
60.00 |
15,504.00 |
|
|
| 707-03 |
combination concrete curb & gutter
|
1,000.0 |
LNFT |
50.00 |
50,000.00 |
11.25 |
11,250.00 |
75.00 |
75,000.00 |
|
|
| 710-01 |
flowable fill
|
77   |
CUYD |
140.00 |
10,780.00 |
437.50 |
33,687.50 |
200.00 |
15,400.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
36,000.00 |
36,000.00 |
25,000.00 |
25,000.00 |
100,000.00 |
100,000.00 |
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
1.240 |
MILE |
1,200.00 |
1,488.00 |
375.00 |
465.00 |
2,000.00 |
2,480.00 |
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
0.620 |
MILE |
500.00 |
310.00 |
387.50 |
240.25 |
300.00 |
186.00 |
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
1.240 |
MILE |
900.00 |
1,116.00 |
1,000.00 |
1,240.00 |
400.00 |
496.00 |
|
|
| 717-01 |
seeding
|
14   |
LB |
60.00 |
840.00 |
62.50 |
875.00 |
20.00 |
280.00 |
|
|
| 718-01 |
fertilizer
|
294   |
LB |
4.00 |
1,176.00 |
6.25 |
1,837.50 |
3.00 |
882.00 |
|
|
| 726-01 |
bedding material
|
120.8 |
CUYD |
87.00 |
10,509.60 |
75.00 |
9,060.00 |
90.00 |
10,872.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
92,000.00 |
92,000.00 |
100,000.00 |
100,000.00 |
95,000.00 |
95,000.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
2   |
EACH |
98.00 |
196.00 |
112.50 |
225.00 |
80.00 |
160.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
164   |
EACH |
6.00 |
984.00 |
6.25 |
1,025.00 |
6.00 |
984.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
1.240 |
MILE |
2,300.00 |
2,852.00 |
4,000.00 |
4,960.00 |
2,400.00 |
2,976.00 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
0.620 |
MILE |
700.00 |
434.00 |
750.00 |
465.00 |
700.00 |
434.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
7,000.00 |
7,000.00 |
25,000.00 |
25,000.00 |
15,000.00 |
15,000.00 |
|
|
| S-001 |
concrete barrier wall
|
202   |
LNFT |
630.00 |
127,260.00 |
106.25 |
21,462.50 |
300.00 |
60,600.00 |
|
|
| S-002 |
removal of dotd traffic control devices
|
lump |
LUMP |
35,000.00 |
35,000.00 |
6,250.00 |
6,250.00 |
40,000.00 |
40,000.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
893,925.80 |
|
937,196.50 |
|
998,134.00 |
|
|
|