| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - RMK CONSTRUCTION CO. LLC |
- 2 - C W & W CONTRACTORS, INC. |
- 3 - JOHN BAILEY, INC. |
- 4 - JEFF MERCER LLC |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
5,000.00 |
5,000.00 |
5,000.00 |
5,000.00 |
5,000.00 |
5,000.00 |
20,000.00 |
20,000.00 |
| 202-02-D |
removal of concrete walks & drives
|
83   |
SQYD |
5.00 |
415.00 |
10.00 |
830.00 |
20.00 |
1,660.00 |
20.00 |
1,660.00 |
| 202-02-F |
removal of concrete combination curb & gutter
|
254.4 |
LNFT |
3.00 |
763.20 |
10.00 |
2,544.00 |
15.00 |
3,816.00 |
1.00 |
254.40 |
| 203-05 |
excavation & embankment
|
lump |
LUMP |
11,000.00 |
11,000.00 |
10,000.00 |
10,000.00 |
35,000.00 |
35,000.00 |
32,000.00 |
32,000.00 |
| 204-02 |
temporary hay or straw bales
|
5   |
EACH |
25.00 |
125.00 |
5.00 |
25.00 |
35.00 |
175.00 |
15.00 |
75.00 |
| 204-06 |
temporary silt fencing
|
270   |
LNFT |
5.00 |
1,350.00 |
3.00 |
810.00 |
5.00 |
1,350.00 |
5.00 |
1,350.00 |
| 302-02-D-01 |
class ii base course (8 1/2" thick)(stone or recycled
pccp) |
354.7 |
SQYD |
45.00 |
15,961.50 |
25.00 |
8,867.50 |
40.00 |
14,188.00 |
35.00 |
12,414.50 |
| 601-01-K |
portland cement concrete pavement (10" thick)
|
328.1 |
SQYD |
75.00 |
24,607.50 |
140.00 |
45,934.00 |
95.00 |
31,169.50 |
230.00 |
75,463.00 |
| 701-03-G |
storm drain pipe (18" rcp/pcp)
|
8   |
LNFT |
75.00 |
600.00 |
200.00 |
1,600.00 |
130.00 |
1,040.00 |
300.00 |
2,400.00 |
| 702-03-A |
catch basins (cb-01)
|
1   |
EACH |
3,000.00 |
3,000.00 |
4,500.00 |
4,500.00 |
6,500.00 |
6,500.00 |
1,500.00 |
1,500.00 |
| 702-03-D |
catch basins (cb-07)
|
1   |
EACH |
5,500.00 |
5,500.00 |
5,000.00 |
5,000.00 |
9,500.00 |
9,500.00 |
4,500.00 |
4,500.00 |
| 706-01-C |
concrete walk (6" thick)
|
150.6 |
SQYD |
45.00 |
6,777.00 |
75.00 |
11,295.00 |
65.00 |
9,789.00 |
120.00 |
18,072.00 |
| 707-03 |
combination concrete curb & gutter
|
239.4 |
LNFT |
10.00 |
2,394.00 |
35.00 |
8,379.00 |
50.00 |
11,970.00 |
60.00 |
14,364.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
7,000.00 |
7,000.00 |
10,000.00 |
10,000.00 |
45,000.00 |
45,000.00 |
4,500.00 |
4,500.00 |
| 713-02-C |
temporary pavement markings (8" width)
|
50   |
LNFT |
6.50 |
325.00 |
2.50 |
125.00 |
2.40 |
120.00 |
2.20 |
110.00 |
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
0.090 |
MILE |
5,000.00 |
450.00 |
8,000.00 |
720.00 |
7,200.00 |
648.00 |
6,600.00 |
594.00 |
| 713-05-A |
temporary pavement legends and symbols (arrow)
|
1   |
EACH |
250.00 |
250.00 |
500.00 |
500.00 |
480.00 |
480.00 |
440.00 |
440.00 |
| 713-05-C |
temporary pavement legends and symbols (only)
|
1   |
EACH |
250.00 |
250.00 |
500.00 |
500.00 |
480.00 |
480.00 |
440.00 |
440.00 |
| 726-01 |
bedding material
|
5.8 |
CUYD |
85.00 |
493.00 |
250.00 |
1,450.00 |
200.00 |
1,160.00 |
250.00 |
1,450.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
10,000.00 |
10,000.00 |
30,000.00 |
30,000.00 |
25,000.00 |
25,000.00 |
30,000.00 |
30,000.00 |
| 731-02 |
reflectorized raised pavement markers
|
9   |
EACH |
10.00 |
90.00 |
160.00 |
1,440.00 |
18.00 |
162.00 |
16.50 |
148.50 |
| 732-01-C |
plastic pavement striping (8" width)
|
50   |
LNFT |
7.25 |
362.50 |
4.00 |
200.00 |
3.60 |
180.00 |
3.30 |
165.00 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
0.045 |
MILE |
6,000.00 |
270.00 |
10,000.00 |
450.00 |
9,360.00 |
421.20 |
8,300.00 |
373.50 |
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
1   |
EACH |
250.00 |
250.00 |
700.00 |
700.00 |
630.00 |
630.00 |
600.00 |
600.00 |
| 732-04-C |
plastic pavement legends & symbols (only)
|
1   |
EACH |
250.00 |
250.00 |
750.00 |
750.00 |
702.00 |
702.00 |
625.00 |
625.00 |
| 732-05 |
removal of existing markings
|
0.045 |
MILE |
6,700.00 |
301.50 |
9,500.00 |
427.50 |
9,000.00 |
405.00 |
8,500.00 |
382.50 |
| 739-01 |
hydro-seeding
|
0.50 |
ACRE |
1,100.00 |
550.00 |
5,000.00 |
2,500.00 |
5,000.00 |
2,500.00 |
2,500.00 |
1,250.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
5,900.00 |
5,900.00 |
7,500.00 |
7,500.00 |
4,500.00 |
4,500.00 |
20,000.00 |
20,000.00 |
| S-001 |
saw cutting
|
260   |
INFT |
10.00 |
2,600.00 |
2.00 |
520.00 |
2.00 |
520.00 |
5.00 |
1,300.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
106,835.20 |
|
162,567.00 |
|
214,065.70 |
|
246,431.40 |
|