| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - RCS CONTRACTORS, INC. |
- 2 - CERES ENVIRONMENTAL SERVICES,INC. |
- 3 - PHYLWAY CONSTRUCTION LLC |
- 4 - BARRIERE CONSTRUCTION CO., LLC. |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-I |
removal of pipe 48'' diameter pipe
|
140   |
LNFT |
8.50 |
1,190.00 |
87.50 |
12,250.00 |
35.00 |
4,900.00 |
122.00 |
17,080.00 |
| 202-02-J |
removal of gabion baskets
|
lump |
LUMP |
2,750.00 |
2,750.00 |
5,625.00 |
5,625.00 |
13,000.00 |
13,000.00 |
24,000.00 |
24,000.00 |
| 203-04 |
nonplastic embankment
|
1,000   |
CUYD |
14.75 |
14,750.00 |
38.75 |
38,750.00 |
40.00 |
40,000.00 |
37.00 |
37,000.00 |
| 203-05 |
excavation and embankment
|
lump |
LUMP |
31,600.00 |
31,600.00 |
37,500.00 |
37,500.00 |
85,000.00 |
85,000.00 |
55,000.00 |
55,000.00 |
| 302-02-F |
class ii base course (12" thick)
|
156.0 |
SQYD |
77.30 |
12,058.80 |
31.25 |
4,875.00 |
75.00 |
11,700.00 |
48.00 |
7,488.00 |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
1,168   |
CUYD |
85.25 |
99,572.00 |
68.75 |
80,300.00 |
125.00 |
146,000.00 |
135.00 |
157,680.00 |
| 510-01-B |
pavement patching (12" minimum thickness)
|
278   |
SQYD |
145.00 |
40,310.00 |
162.50 |
45,175.00 |
190.00 |
52,820.00 |
140.00 |
38,920.00 |
| 701-01-S-01 |
cross drain pipe (72" bccmp)
|
280   |
LNFT |
433.12 |
121,273.60 |
212.50 |
59,500.00 |
625.00 |
175,000.00 |
1,240.00 |
347,200.00 |
| 711-03-C |
riprap (30 lb)
|
75.0 |
TON |
96.12 |
7,209.00 |
75.00 |
5,625.00 |
95.00 |
7,125.00 |
128.00 |
9,600.00 |
| 726-01 |
bedding material
|
104.0 |
CUYD |
81.28 |
8,453.12 |
68.75 |
7,150.00 |
130.00 |
13,520.00 |
86.00 |
8,944.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
19,500.00 |
19,500.00 |
128,075.00 |
128,075.00 |
60,000.00 |
60,000.00 |
28,000.00 |
28,000.00 |
| 731-02 |
reflectorized raised pavement markers
|
5   |
EACH |
5.90 |
29.50 |
7.50 |
37.50 |
10.00 |
50.00 |
7.60 |
38.00 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
0.150 |
MILE |
2,500.00 |
375.00 |
23,750.00 |
3,562.50 |
4,000.00 |
600.00 |
2,660.00 |
399.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
5,000.00 |
5,000.00 |
26,250.00 |
26,250.00 |
30,000.00 |
30,000.00 |
4,700.00 |
4,700.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
364,071.02 |
|
454,675.00 |
|
639,715.00 |
|
736,049.00 |
|