| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - GILCHRIST CONSTRUCTION CO. LLC |
- 2 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 3 - D & J CONSTRUCTION CO., INC. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 203-07 |
borrow (vehicular measurement)
|
700   |
CUYD |
20.00 |
14,000.00 |
20.00 |
14,000.00 |
10.00 |
7,000.00 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
3   |
CUYD |
125.00 |
375.00 |
150.00 |
450.00 |
300.00 |
900.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
3,836.3 |
TON |
82.00 |
314,576.60 |
89.00 |
341,430.70 |
95.00 |
364,448.50 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
28.0 |
TON |
200.00 |
5,600.00 |
200.00 |
5,600.00 |
295.00 |
8,260.00 |
|
|
| 507-01-A |
asphaltic material (crs-2p emulsion)
|
17,883   |
GAL |
3.20 |
57,225.60 |
2.50 |
44,707.50 |
2.15 |
38,448.45 |
|
|
| 507-02-B |
aggregate (s2)
|
26,299   |
SQYD |
1.00 |
26,299.00 |
1.50 |
39,448.50 |
1.40 |
36,818.60 |
|
|
| 507-02-C |
aggregate (s3)
|
26,299   |
SQYD |
0.85 |
22,354.15 |
1.50 |
39,448.50 |
1.40 |
36,818.60 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
847   |
SQYD |
7.00 |
5,929.00 |
16.00 |
13,552.00 |
12.00 |
10,164.00 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 26   |
CUYD |
0.02 |
- 0.52 |
0.10 |
- 2.60 |
0.01 |
- 0.26 |
|
|
| 510-01-A |
pavement patching (6" minimum thickness)
|
50   |
SQYD |
98.00 |
4,900.00 |
200.00 |
10,000.00 |
75.00 |
3,750.00 |
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
700   |
SQYD |
110.00 |
77,000.00 |
120.00 |
84,000.00 |
125.00 |
87,500.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
18,000.00 |
18,000.00 |
10,000.00 |
10,000.00 |
20,000.00 |
20,000.00 |
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
1.464 |
MILE |
350.00 |
512.40 |
150.00 |
219.60 |
250.00 |
366.00 |
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
2.589 |
MILE |
350.00 |
906.15 |
325.00 |
841.43 |
300.00 |
776.70 |
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
6.194 |
MILE |
1.00 |
6.19 |
550.00 |
3,406.70 |
1.00 |
6.19 |
|
|
| 713-06-A |
temporary reflectorized raised pavement markers (tabs)
|
773   |
EACH |
1.60 |
1,236.80 |
2.00 |
1,546.00 |
1.60 |
1,236.80 |
|
|
| 716-01-A |
mulch (vegetative)
|
3.6 |
TON |
525.00 |
1,890.00 |
500.00 |
1,800.00 |
500.00 |
1,800.00 |
|
|
| 717-01 |
seeding
|
54   |
LB |
8.00 |
432.00 |
8.00 |
432.00 |
8.00 |
432.00 |
|
|
| 718-01 |
fertilizer
|
1,804   |
LB |
0.60 |
1,082.40 |
0.60 |
1,082.40 |
0.60 |
1,082.40 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
70,000.00 |
70,000.00 |
70,000.00 |
70,000.00 |
70,000.00 |
70,000.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
521   |
EACH |
5.50 |
2,865.50 |
6.00 |
3,126.00 |
8.00 |
4,168.00 |
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
2,807   |
LNFT |
1.00 |
2,807.00 |
1.25 |
3,508.75 |
3.50 |
9,824.50 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
741   |
LNFT |
3.50 |
2,593.50 |
3.25 |
2,408.25 |
6.00 |
4,446.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
3.211 |
MILE |
2,800.00 |
8,990.80 |
2,500.00 |
8,027.50 |
3,000.00 |
9,633.00 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
1.294 |
MILE |
850.00 |
1,099.90 |
750.00 |
970.50 |
1,000.00 |
1,294.00 |
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
5   |
EACH |
190.00 |
950.00 |
165.00 |
825.00 |
400.00 |
2,000.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
8,000.00 |
8,000.00 |
5,000.00 |
5,000.00 |
3,300.00 |
3,300.00 |
|
|
| S-001 |
saw cutting
|
19,710   |
INFT |
1.20 |
23,652.00 |
0.30 |
5,913.00 |
0.40 |
7,884.00 |
|
|
| S-002 |
surface preparation
|
lump |
LUMP |
35,000.00 |
35,000.00 |
15,000.00 |
15,000.00 |
25,000.00 |
25,000.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
708,283.47 |
|
726,741.73 |
|
757,357.48 |
|
|
|