| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - JAMES CONSTRUCTION GROUP LLC |
- 2 - HILL BROTHERS CONSTRUCTION CO., INC |
- 3 - BLOUNT BROS. CONSTRUCTION, INC. |
- 4 - AUSTIN BRIDGE & ROAD, LP |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
750,000.00 |
750,000.00 |
500,000.00 |
500,000.00 |
150,000.00 |
150,000.00 |
500,000.00 |
500,000.00 |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
10,000.00 |
10,000.00 |
50,000.00 |
50,000.00 |
200,000.00 |
200,000.00 |
60,000.00 |
60,000.00 |
| 202-02-A-01 |
removal of bridge (sta. 110+00.00; 24' x 95' precast
concrete span bridge) |
1   |
EACH |
25,000.00 |
25,000.00 |
50,000.00 |
50,000.00 |
20,000.00 |
20,000.00 |
90,000.00 |
90,000.00 |
| 202-02-A-02 |
removal of bridge (sta. 122+78.30; 24' x 286' precast
concrete span bridge) |
1   |
EACH |
50,000.00 |
50,000.00 |
125,000.00 |
125,000.00 |
50,000.00 |
50,000.00 |
160,000.00 |
160,000.00 |
| 202-02-A-03 |
removal of bridge (sta. 129+78.36; 24' x 439' precast
concrete span bridge) |
1   |
EACH |
70,000.00 |
70,000.00 |
200,000.00 |
200,000.00 |
80,000.00 |
80,000.00 |
180,000.00 |
180,000.00 |
| 202-02-A-04 |
removal of bridge (sta. 211+96.90; 24' x 248' precast
concrete span bridge) |
1   |
EACH |
45,000.00 |
45,000.00 |
125,000.00 |
125,000.00 |
45,000.00 |
45,000.00 |
85,000.00 |
85,000.00 |
| 202-02-G |
removal of surfacing & stabilized base
|
15,046.0 |
SQYD |
5.00 |
75,230.00 |
5.00 |
75,230.00 |
4.70 |
70,716.20 |
6.60 |
99,303.60 |
| 203-01 |
general excavation
|
21,082   |
CUYD |
5.00 |
105,410.00 |
4.00 |
84,328.00 |
6.00 |
126,492.00 |
8.00 |
168,656.00 |
| 203-02 |
drainage excavation
|
905   |
CUYD |
16.00 |
14,480.00 |
15.00 |
13,575.00 |
12.00 |
10,860.00 |
14.00 |
12,670.00 |
| 203-03 |
embankment
|
142,899   |
CUYD |
8.70 |
1,243,221.30 |
9.50 |
1,357,540.50 |
12.00 |
1,714,788.00 |
15.00 |
2,143,485.00 |
| 204-02 |
temporary hay or straw bales
|
200   |
EACH |
15.00 |
3,000.00 |
20.00 |
4,000.00 |
15.00 |
3,000.00 |
17.00 |
3,400.00 |
| 204-05-A |
temporary sediment check dams (hay)
|
11   |
EACH |
150.00 |
1,650.00 |
250.00 |
2,750.00 |
90.00 |
990.00 |
225.00 |
2,475.00 |
| 204-06 |
temporary silt fencing
|
500   |
LNFT |
3.00 |
1,500.00 |
10.00 |
5,000.00 |
3.00 |
1,500.00 |
6.00 |
3,000.00 |
| 204-07 |
temporary stone construction entrance
|
8   |
EACH |
4,000.00 |
32,000.00 |
10,000.00 |
80,000.00 |
2,600.00 |
20,800.00 |
3,000.00 |
24,000.00 |
| 302-02-D |
class ii base course (8 1/2" thick)
|
15,054.0 |
SQYD |
22.00 |
331,188.00 |
16.00 |
240,864.00 |
18.00 |
270,972.00 |
19.00 |
286,026.00 |
| 304-01 |
lime
|
151.15 |
TON |
1.00 |
151.15 |
175.00 |
26,451.25 |
160.00 |
24,184.00 |
180.00 |
27,207.00 |
| 304-04-B |
lime treatment (type d) (8 1/2" thick)
|
15,054   |
SQYD |
0.01 |
150.54 |
2.75 |
41,398.50 |
3.50 |
52,689.00 |
6.00 |
90,324.00 |
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
132.0 |
CUYD |
70.00 |
9,240.00 |
100.00 |
13,200.00 |
50.00 |
6,600.00 |
60.00 |
7,920.00 |
| 502-01 |
superpave asphaltic concrete
|
9,390.2 |
TON |
100.00 |
939,020.00 |
100.00 |
939,020.00 |
100.00 |
939,020.00 |
105.00 |
985,971.00 |
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
373.6 |
TON |
130.00 |
48,568.00 |
130.00 |
48,568.00 |
110.00 |
41,096.00 |
130.00 |
48,568.00 |
| 701-01-M |
cross drain pipe (36" rcp/pcp)
|
160   |
LNFT |
116.00 |
18,560.00 |
100.00 |
16,000.00 |
110.00 |
17,600.00 |
220.00 |
35,200.00 |
| 701-05-G |
side drain pipe (18")
|
90   |
LNFT |
48.00 |
4,320.00 |
30.00 |
2,700.00 |
35.00 |
3,150.00 |
50.00 |
4,500.00 |
| 701-05-I |
side drain pipe (24")
|
28   |
LNFT |
65.00 |
1,820.00 |
45.00 |
1,260.00 |
45.00 |
1,260.00 |
80.00 |
2,240.00 |
| 701-05-K |
side drain pipe (30")
|
56   |
LNFT |
79.00 |
4,424.00 |
70.00 |
3,920.00 |
100.00 |
5,600.00 |
90.00 |
5,040.00 |
| 701-05-M |
side drain pipe (36")
|
250   |
LNFT |
92.00 |
23,000.00 |
75.00 |
18,750.00 |
90.00 |
22,500.00 |
125.00 |
31,250.00 |
| 701-05-N |
side drain pipe (42")
|
30   |
LNFT |
112.00 |
3,360.00 |
125.00 |
3,750.00 |
120.00 |
3,600.00 |
200.00 |
6,000.00 |
| 704-03 |
blocked out guard rail
|
750.0 |
LNFT |
17.00 |
12,750.00 |
18.50 |
13,875.00 |
19.50 |
14,625.00 |
20.00 |
15,000.00 |
| 704-08-B |
guard rail transitions (double thrie beam)
|
400.0 |
LNFT |
50.00 |
20,000.00 |
55.00 |
22,000.00 |
58.00 |
23,200.00 |
55.00 |
22,000.00 |
| 704-11-A |
guard rail end treatment (flared)
|
16   |
EACH |
2,000.00 |
32,000.00 |
2,100.00 |
33,600.00 |
2,500.00 |
40,000.00 |
1,950.00 |
31,200.00 |
| 705-01 |
barbed wire fence
|
1,698   |
LNFT |
4.60 |
7,810.80 |
5.00 |
8,490.00 |
6.00 |
10,188.00 |
4.75 |
8,065.50 |
| 705-02 |
combination mesh & barbed wire fence
|
1,764   |
LNFT |
5.00 |
8,820.00 |
5.50 |
9,702.00 |
12.00 |
21,168.00 |
5.25 |
9,261.00 |
| 705-04 |
single swinging driveway gates
|
1   |
EACH |
540.00 |
540.00 |
600.00 |
600.00 |
600.00 |
600.00 |
550.00 |
550.00 |
| 708-01 |
right-of-way monument
|
48   |
EACH |
150.00 |
7,200.00 |
150.00 |
7,200.00 |
187.00 |
8,976.00 |
250.00 |
12,000.00 |
| 708-02 |
right-of-way monument witness post
|
48   |
EACH |
150.00 |
7,200.00 |
125.00 |
6,000.00 |
200.00 |
9,600.00 |
180.00 |
8,640.00 |
| 711-01-E |
riprap (130 lb, 24" thick)
|
10,796   |
SQYD |
73.00 |
788,108.00 |
50.00 |
539,800.00 |
80.00 |
863,680.00 |
90.00 |
971,640.00 |
| 711-04 |
geotextile fabric
|
10,796   |
SQYD |
4.00 |
43,184.00 |
2.50 |
26,990.00 |
3.20 |
34,547.20 |
3.10 |
33,467.60 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
60,000.00 |
60,000.00 |
75,000.00 |
75,000.00 |
75,000.00 |
75,000.00 |
65,000.00 |
65,000.00 |
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
5.923 |
MILE |
550.00 |
3,257.65 |
550.00 |
3,257.65 |
825.00 |
4,886.48 |
550.00 |
3,257.65 |
| 713-06 |
temporary reflectorized raised pavement markers
|
785   |
EACH |
5.00 |
3,925.00 |
6.00 |
4,710.00 |
10.00 |
7,850.00 |
6.00 |
4,710.00 |
| 716-01-A |
mulch (vegetative)
|
31.6 |
TON |
750.00 |
23,700.00 |
665.00 |
21,014.00 |
520.00 |
16,432.00 |
570.00 |
18,012.00 |
| 720-01-A |
erosion control system, slope protection (type a)
|
5,995   |
SQYD |
1.20 |
7,194.00 |
1.10 |
6,594.50 |
3.00 |
17,985.00 |
2.00 |
11,990.00 |
| 720-01-B |
erosion control system, slope protection (type b)
|
4,199   |
SQYD |
1.20 |
5,038.80 |
1.70 |
7,138.30 |
3.00 |
12,597.00 |
1.70 |
7,138.30 |
| 720-01-C |
erosion control system, flexible channel liner (type c)
|
658   |
SQYD |
1.90 |
1,250.20 |
1.70 |
1,118.60 |
4.00 |
2,632.00 |
3.20 |
2,105.60 |
| 720-01-D |
erosion control system, flexible channel liner (type d)
|
3,880   |
SQYD |
1.90 |
7,372.00 |
2.00 |
7,760.00 |
5.00 |
19,400.00 |
3.20 |
12,416.00 |
| 720-01-F |
erosion control system, flexible channel liner (type f)
|
592   |
SQYD |
3.00 |
1,776.00 |
3.00 |
1,776.00 |
5.00 |
2,960.00 |
3.20 |
1,894.40 |
| 722-01 |
project site laboratory
|
1   |
EACH |
15,000.00 |
15,000.00 |
20,000.00 |
20,000.00 |
40,000.00 |
40,000.00 |
20,000.00 |
20,000.00 |
| 725-01 |
temporary detour roads
|
4,377.5 |
SQYD |
90.00 |
393,975.00 |
70.00 |
306,425.00 |
75.00 |
328,312.50 |
105.00 |
459,637.50 |
| 725-03 |
temporary detour bridging
|
120.00 |
LNFT |
1,500.00 |
180,000.00 |
3,500.00 |
420,000.00 |
3,160.00 |
379,200.00 |
2,500.00 |
300,000.00 |
| 726-01 |
bedding material
|
60.0 |
CUYD |
125.00 |
7,500.00 |
100.00 |
6,000.00 |
80.00 |
4,800.00 |
120.00 |
7,200.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
1,000,000.00 |
1,000,000.00 |
500,000.00 |
500,000.00 |
850,000.00 |
850,000.00 |
1,300,000.00 |
1,300,000.00 |
| 729-01 |
sign (type a)
|
6.0 |
SQFT |
40.00 |
240.00 |
45.00 |
270.00 |
18.50 |
111.00 |
30.00 |
180.00 |
| 729-08-A |
mounting (2 1/2" post)
|
2   |
EACH |
850.00 |
1,700.00 |
950.00 |
1,900.00 |
600.00 |
1,200.00 |
150.00 |
300.00 |
| 729-16-C |
object marker assembly (type 3)
|
16   |
EACH |
75.00 |
1,200.00 |
80.00 |
1,280.00 |
80.00 |
1,280.00 |
72.00 |
1,152.00 |
| 729-19-A |
dead end road installations(type a)
|
1   |
EACH |
1,500.00 |
1,500.00 |
1,700.00 |
1,700.00 |
2,000.00 |
2,000.00 |
1,500.00 |
1,500.00 |
| 731-02 |
reflectorized raised pavement markers
|
661   |
EACH |
5.00 |
3,305.00 |
6.00 |
3,966.00 |
10.00 |
6,610.00 |
5.00 |
3,305.00 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
4.990 |
MILE |
3,000.00 |
14,970.00 |
3,350.00 |
16,716.50 |
2,700.00 |
13,473.00 |
3,000.00 |
14,970.00 |
| 732-05 |
removal of existing markings
|
1.307 |
MILE |
6,000.00 |
7,842.00 |
6,650.00 |
8,691.55 |
6,000.00 |
7,842.00 |
6,000.00 |
7,842.00 |
| 739-01 |
hydro-seeding
|
18.03 |
ACRE |
1,050.00 |
18,931.50 |
1,200.00 |
21,636.00 |
2,000.00 |
36,060.00 |
2,000.00 |
36,060.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
125,000.00 |
125,000.00 |
400,000.00 |
400,000.00 |
180,000.00 |
180,000.00 |
250,000.00 |
250,000.00 |
| 804-01-C |
precast concrete piles (16")
|
1,690   |
LNFT |
75.00 |
126,750.00 |
95.00 |
160,550.00 |
80.00 |
135,200.00 |
80.00 |
135,200.00 |
| 804-01-F |
precast concrete piles (24")
|
7,500   |
LNFT |
105.00 |
787,500.00 |
175.00 |
1,312,500.00 |
120.00 |
900,000.00 |
119.00 |
892,500.00 |
| 804-01-G |
precast concrete piles (30")
|
3,380   |
LNFT |
128.00 |
432,640.00 |
195.00 |
659,100.00 |
150.00 |
507,000.00 |
150.00 |
507,000.00 |
| 804-12 |
loading permanent piles
|
4   |
EACH |
2,500.00 |
10,000.00 |
5,500.00 |
22,000.00 |
15,000.00 |
60,000.00 |
30,000.00 |
120,000.00 |
| 805-01-F |
class a concrete (bents)
|
664.94 |
CUYD |
950.00 |
631,693.00 |
650.00 |
432,211.00 |
700.00 |
465,458.00 |
1,100.00 |
731,434.00 |
| 805-03 |
class aa concrete
|
1,764.32 |
CUYD |
850.00 |
1,499,672.00 |
900.00 |
1,587,888.00 |
800.00 |
1,411,456.00 |
1,200.00 |
2,117,184.00 |
| 805-08-B |
precast-prestressed concrete girders (type ii)
|
2,672.9 |
LNFT |
160.00 |
427,664.00 |
100.00 |
267,290.00 |
110.00 |
294,019.00 |
130.00 |
347,477.00 |
| 805-11 |
strip seal joints
|
132.00 |
LNFT |
225.00 |
29,700.00 |
140.00 |
18,480.00 |
200.00 |
26,400.00 |
180.00 |
23,760.00 |
| 806-01 |
deformed reinforcing steel
|
460,347   |
LB |
1.00 |
460,347.00 |
1.00 |
460,347.00 |
1.50 |
690,520.50 |
1.25 |
575,433.75 |
| 807-08 |
structural metalwork
|
lump |
LUMP |
5,000.00 |
5,000.00 |
5,000.00 |
5,000.00 |
30,000.00 |
30,000.00 |
17,000.00 |
17,000.00 |
| 810-01 |
concrete railing (barrier)
|
2,199.26 |
LNFT |
48.10 |
105,784.41 |
75.00 |
164,944.50 |
150.00 |
329,889.00 |
95.00 |
208,929.70 |
| 813-01 |
concrete approach slabs
|
1,591.12 |
SQYD |
210.00 |
334,135.20 |
200.00 |
318,224.00 |
160.00 |
254,579.20 |
275.00 |
437,558.00 |
| S-001 |
sawcutting existing bituminous pavement
|
100   |
LNFT |
10.00 |
1,000.00 |
11.00 |
1,100.00 |
10.00 |
1,000.00 |
40.00 |
4,000.00 |
| S-101 |
retroreflective sheeting panels
|
lump |
LUMP |
2,500.00 |
2,500.00 |
20,000.00 |
20,000.00 |
2,500.00 |
2,500.00 |
2,500.00 |
2,500.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | ITEM TOTAL (CONSTRUCTION BID) |
|
|
|
11,476,968.55 |
|
11,963,150.85 |
|
12,027,654.08 |
|
14,822,706.60 |
| | NUMBER OF DAYS BID AT $1,000 PER DAY. |
|
|
|
650,000.00 |
|
650,000.00 |
|
600,000.00 |
|
650,000.00 |
| | TOTAL BID |
|
|
|
12,126,968.55 |
|
12,613,150.85 |
|
12,627,654.08 |
|
15,472,706.60 |
|
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 5 - CERES ENVIRONMENTAL SERVICES,INC. |
|
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
45,000.00 |
45,000.00 |
|
|
|
|
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
2,500.00 |
2,500.00 |
|
|
|
|
|
|
| 202-02-A-01 |
removal of bridge (sta. 110+00.00; 24' x 95' precast
concrete span bridge) |
1   |
EACH |
36,250.00 |
36,250.00 |
|
|
|
|
|
|
| 202-02-A-02 |
removal of bridge (sta. 122+78.30; 24' x 286' precast
concrete span bridge) |
1   |
EACH |
106,250.00 |
106,250.00 |
|
|
|
|
|
|
| 202-02-A-03 |
removal of bridge (sta. 129+78.36; 24' x 439' precast
concrete span bridge) |
1   |
EACH |
166,250.00 |
166,250.00 |
|
|
|
|
|
|
| 202-02-A-04 |
removal of bridge (sta. 211+96.90; 24' x 248' precast
concrete span bridge) |
1   |
EACH |
105,000.00 |
105,000.00 |
|
|
|
|
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
15,046.0 |
SQYD |
3.13 |
47,093.98 |
|
|
|
|
|
|
| 203-01 |
general excavation
|
21,082   |
CUYD |
3.13 |
65,986.66 |
|
|
|
|
|
|
| 203-02 |
drainage excavation
|
905   |
CUYD |
4.69 |
4,244.45 |
|
|
|
|
|
|
| 203-03 |
embankment
|
142,899   |
CUYD |
11.88 |
1,697,640.12 |
|
|
|
|
|
|
| 204-02 |
temporary hay or straw bales
|
200   |
EACH |
12.50 |
2,500.00 |
|
|
|
|
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
11   |
EACH |
187.50 |
2,062.50 |
|
|
|
|
|
|
| 204-06 |
temporary silt fencing
|
500   |
LNFT |
1.88 |
940.00 |
|
|
|
|
|
|
| 204-07 |
temporary stone construction entrance
|
8   |
EACH |
375.00 |
3,000.00 |
|
|
|
|
|
|
| 302-02-D |
class ii base course (8 1/2" thick)
|
15,054.0 |
SQYD |
28.75 |
432,802.50 |
|
|
|
|
|
|
| 304-01 |
lime
|
151.15 |
TON |
187.50 |
28,340.63 |
|
|
|
|
|
|
| 304-04-B |
lime treatment (type d) (8 1/2" thick)
|
15,054   |
SQYD |
10.00 |
150,540.00 |
|
|
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
132.0 |
CUYD |
87.50 |
11,550.00 |
|
|
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
9,390.2 |
TON |
100.00 |
939,020.00 |
|
|
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
373.6 |
TON |
100.00 |
37,360.00 |
|
|
|
|
|
|
| 701-01-M |
cross drain pipe (36" rcp/pcp)
|
160   |
LNFT |
156.25 |
25,000.00 |
|
|
|
|
|
|
| 701-05-G |
side drain pipe (18")
|
90   |
LNFT |
56.25 |
5,062.50 |
|
|
|
|
|
|
| 701-05-I |
side drain pipe (24")
|
28   |
LNFT |
87.50 |
2,450.00 |
|
|
|
|
|
|
| 701-05-K |
side drain pipe (30")
|
56   |
LNFT |
95.00 |
5,320.00 |
|
|
|
|
|
|
| 701-05-M |
side drain pipe (36")
|
250   |
LNFT |
131.25 |
32,812.50 |
|
|
|
|
|
|
| 701-05-N |
side drain pipe (42")
|
30   |
LNFT |
206.25 |
6,187.50 |
|
|
|
|
|
|
| 704-03 |
blocked out guard rail
|
750.0 |
LNFT |
26.25 |
19,687.50 |
|
|
|
|
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
400.0 |
LNFT |
68.75 |
27,500.00 |
|
|
|
|
|
|
| 704-11-A |
guard rail end treatment (flared)
|
16   |
EACH |
2,812.50 |
45,000.00 |
|
|
|
|
|
|
| 705-01 |
barbed wire fence
|
1,698   |
LNFT |
15.00 |
25,470.00 |
|
|
|
|
|
|
| 705-02 |
combination mesh & barbed wire fence
|
1,764   |
LNFT |
17.50 |
30,870.00 |
|
|
|
|
|
|
| 705-04 |
single swinging driveway gates
|
1   |
EACH |
625.00 |
625.00 |
|
|
|
|
|
|
| 708-01 |
right-of-way monument
|
48   |
EACH |
162.50 |
7,800.00 |
|
|
|
|
|
|
| 708-02 |
right-of-way monument witness post
|
48   |
EACH |
162.50 |
7,800.00 |
|
|
|
|
|
|
| 711-01-E |
riprap (130 lb, 24" thick)
|
10,796   |
SQYD |
62.50 |
674,750.00 |
|
|
|
|
|
|
| 711-04 |
geotextile fabric
|
10,796   |
SQYD |
2.63 |
28,393.48 |
|
|
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
56,250.00 |
56,250.00 |
|
|
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
5.923 |
MILE |
625.00 |
3,701.88 |
|
|
|
|
|
|
| 713-06 |
temporary reflectorized raised pavement markers
|
785   |
EACH |
6.25 |
4,906.25 |
|
|
|
|
|
|
| 716-01-A |
mulch (vegetative)
|
31.6 |
TON |
687.50 |
21,725.00 |
|
|
|
|
|
|
| 720-01-A |
erosion control system, slope protection (type a)
|
5,995   |
SQYD |
1.88 |
11,270.60 |
|
|
|
|
|
|
| 720-01-B |
erosion control system, slope protection (type b)
|
4,199   |
SQYD |
1.88 |
7,894.12 |
|
|
|
|
|
|
| 720-01-C |
erosion control system, flexible channel liner (type c)
|
658   |
SQYD |
2.50 |
1,645.00 |
|
|
|
|
|
|
| 720-01-D |
erosion control system, flexible channel liner (type d)
|
3,880   |
SQYD |
2.50 |
9,700.00 |
|
|
|
|
|
|
| 720-01-F |
erosion control system, flexible channel liner (type f)
|
592   |
SQYD |
3.75 |
2,220.00 |
|
|
|
|
|
|
| 722-01 |
project site laboratory
|
1   |
EACH |
31,250.00 |
31,250.00 |
|
|
|
|
|
|
| 725-01 |
temporary detour roads
|
4,377.5 |
SQYD |
100.00 |
437,750.00 |
|
|
|
|
|
|
| 725-03 |
temporary detour bridging
|
120.00 |
LNFT |
2,405.00 |
288,600.00 |
|
|
|
|
|
|
| 726-01 |
bedding material
|
60.0 |
CUYD |
81.25 |
4,875.00 |
|
|
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
930,625.00 |
930,625.00 |
|
|
|
|
|
|
| 729-01 |
sign (type a)
|
6.0 |
SQFT |
62.50 |
375.00 |
|
|
|
|
|
|
| 729-08-A |
mounting (2 1/2" post)
|
2   |
EACH |
1,000.00 |
2,000.00 |
|
|
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
16   |
EACH |
93.75 |
1,500.00 |
|
|
|
|
|
|
| 729-19-A |
dead end road installations(type a)
|
1   |
EACH |
1,875.00 |
1,875.00 |
|
|
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
661   |
EACH |
6.25 |
4,131.25 |
|
|
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
4.990 |
MILE |
3,750.00 |
18,712.50 |
|
|
|
|
|
|
| 732-05 |
removal of existing markings
|
1.307 |
MILE |
7,500.00 |
9,802.50 |
|
|
|
|
|
|
| 739-01 |
hydro-seeding
|
18.03 |
ACRE |
1,375.00 |
24,791.25 |
|
|
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
293,750.00 |
293,750.00 |
|
|
|
|
|
|
| 804-01-C |
precast concrete piles (16")
|
1,690   |
LNFT |
151.25 |
255,612.50 |
|
|
|
|
|
|
| 804-01-F |
precast concrete piles (24")
|
7,500   |
LNFT |
250.00 |
1,875,000.00 |
|
|
|
|
|
|
| 804-01-G |
precast concrete piles (30")
|
3,380   |
LNFT |
322.50 |
1,090,050.00 |
|
|
|
|
|
|
| 804-12 |
loading permanent piles
|
4   |
EACH |
6,250.00 |
25,000.00 |
|
|
|
|
|
|
| 805-01-F |
class a concrete (bents)
|
664.94 |
CUYD |
1,500.00 |
997,410.00 |
|
|
|
|
|
|
| 805-03 |
class aa concrete
|
1,764.32 |
CUYD |
1,250.00 |
2,205,400.00 |
|
|
|
|
|
|
| 805-08-B |
precast-prestressed concrete girders (type ii)
|
2,672.9 |
LNFT |
125.00 |
334,112.50 |
|
|
|
|
|
|
| 805-11 |
strip seal joints
|
132.00 |
LNFT |
137.50 |
18,150.00 |
|
|
|
|
|
|
| 806-01 |
deformed reinforcing steel
|
460,347   |
LB |
1.25 |
575,433.75 |
|
|
|
|
|
|
| 807-08 |
structural metalwork
|
lump |
LUMP |
5,000.00 |
5,000.00 |
|
|
|
|
|
|
| 810-01 |
concrete railing (barrier)
|
2,199.26 |
LNFT |
50.00 |
109,963.00 |
|
|
|
|
|
|
| 813-01 |
concrete approach slabs
|
1,591.12 |
SQYD |
225.00 |
358,002.00 |
|
|
|
|
|
|
| S-001 |
sawcutting existing bituminous pavement
|
100   |
LNFT |
15.00 |
1,500.00 |
|
|
|
|
|
|
| S-101 |
retroreflective sheeting panels
|
lump |
LUMP |
312.50 |
312.50 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | ITEM TOTAL (CONSTRUCTION BID) |
|
|
|
14,849,355.92 |
|
|
|
|
|
|
| | NUMBER OF DAYS BID AT $1,000 PER DAY. |
|
|
|
450,000.00 |
|
|
|
|
|
|
| | TOTAL BID |
|
|
|
15,299,355.92 |
|
|
|
|
|
|
|