| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - PRAIRIE CONTRACTORS INC. |
- 2 - GILCHRIST CONSTRUCTION CO. LLC |
- 3 - H & S CONSTRUCTION CO., INC. |
- 4 - DIAMOND B CONSTRUCTION CO., L.L.C. |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 203-07 |
borrow (vehicular measurement)
|
4,983   |
CUYD |
20.00 |
99,660.00 |
19.50 |
97,168.50 |
15.00 |
74,745.00 |
12.75 |
63,533.25 |
| 203-07-A |
borrow (vehicular meas.)(selected soils)
|
28   |
CUYD |
20.00 |
560.00 |
30.00 |
840.00 |
16.00 |
448.00 |
12.00 |
336.00 |
| 204-05-A |
temporary sediment check dams (hay)
|
72   |
EACH |
250.00 |
18,000.00 |
165.00 |
11,880.00 |
350.00 |
25,200.00 |
122.00 |
8,784.00 |
| 302-02-B |
class ii base course (6" thick)
|
16,864.0 |
SQYD |
14.00 |
236,096.00 |
12.00 |
202,368.00 |
35.00 |
590,240.00 |
14.75 |
248,744.00 |
| 303-01-B |
in-place cement stabilized base course (8 1/2" thick)
|
39,848   |
SQYD |
12.50 |
498,100.00 |
8.00 |
318,784.00 |
7.50 |
298,860.00 |
13.50 |
537,948.00 |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
100   |
CUYD |
60.00 |
6,000.00 |
140.00 |
14,000.00 |
85.00 |
8,500.00 |
28.00 |
2,800.00 |
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
50.0 |
CUYD |
100.00 |
5,000.00 |
80.00 |
4,000.00 |
85.00 |
4,250.00 |
48.00 |
2,400.00 |
| 502-01 |
superpave asphaltic concrete
|
42,190.9 |
TON |
83.75 |
3,533,487.88 |
83.00 |
3,501,844.70 |
85.00 |
3,586,226.50 |
103.00 |
4,345,662.70 |
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
755.1 |
TON |
300.00 |
226,530.00 |
195.00 |
147,244.50 |
150.00 |
113,265.00 |
187.00 |
141,203.70 |
| 507-01-A |
asphaltic material (crs-2p emulsion)
|
33,831   |
GAL |
2.00 |
67,662.00 |
3.40 |
115,025.40 |
4.00 |
135,324.00 |
2.10 |
71,045.10 |
| 507-02-B |
aggregate (s2)
|
49,752   |
SQYD |
1.10 |
54,727.20 |
0.55 |
27,363.60 |
1.50 |
74,628.00 |
1.25 |
62,190.00 |
| 507-02-C |
aggregate (s3)
|
49,752   |
SQYD |
1.10 |
54,727.20 |
0.55 |
27,363.60 |
1.50 |
74,628.00 |
1.00 |
49,752.00 |
| 509-01 |
cold planing asphaltic pavement
|
45,529   |
SQYD |
2.00 |
91,058.00 |
0.90 |
40,976.10 |
2.50 |
113,822.50 |
3.00 |
136,587.00 |
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 2,577   |
CUYD |
0.01 |
- 25.77 |
0.02 |
- 51.54 |
0.01 |
- 25.77 |
0.10 |
- 257.70 |
| 510-01-B |
pavement patching (12" minimum thickness)
|
50   |
SQYD |
150.00 |
7,500.00 |
200.00 |
10,000.00 |
175.00 |
8,750.00 |
271.00 |
13,550.00 |
| 602-02-A |
cleaning and resealing existing longitudinal pavement
joints |
3,605   |
LNFT |
2.00 |
7,210.00 |
2.20 |
7,931.00 |
3.00 |
10,815.00 |
2.50 |
9,012.50 |
| 602-02-B |
cleaning and resealing existing transverse pavement
joints |
4,392   |
LNFT |
3.00 |
13,176.00 |
2.20 |
9,662.40 |
3.00 |
13,176.00 |
2.50 |
10,980.00 |
| 602-03 |
cleaning and sealing cracks
|
300   |
LNFT |
4.00 |
1,200.00 |
4.50 |
1,350.00 |
4.20 |
1,260.00 |
5.00 |
1,500.00 |
| 602-05-K-02 |
full depth patching of jointed conc pvmt (10" thick)
(16.1-48.0 sq yds) |
50.0 |
SQYD |
200.00 |
10,000.00 |
250.00 |
12,500.00 |
210.00 |
10,500.00 |
250.00 |
12,500.00 |
| 602-05-K-03 |
full depth patching of jointed conc pvmt (10" thick)
(48.1 sq yds & over) |
50.0 |
SQYD |
200.00 |
10,000.00 |
230.00 |
11,500.00 |
190.00 |
9,500.00 |
225.00 |
11,250.00 |
| 602-08 |
grinding concrete pavement
|
266.7 |
SQYD |
30.00 |
8,001.00 |
28.00 |
7,467.60 |
75.00 |
20,002.50 |
75.00 |
20,002.50 |
| 602-10 |
longitudinal shoulder joints
|
4,270   |
LNFT |
2.00 |
8,540.00 |
2.40 |
10,248.00 |
2.35 |
10,034.50 |
2.50 |
10,675.00 |
| 703-01 |
shoulder underdrain systems
|
51,889   |
LNFT |
7.00 |
363,223.00 |
11.25 |
583,751.25 |
7.00 |
363,223.00 |
8.25 |
428,084.25 |
| 703-02 |
shoulder outlet underdrains
|
176   |
EACH |
650.00 |
114,400.00 |
625.00 |
110,000.00 |
650.00 |
114,400.00 |
700.00 |
123,200.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
50,000.00 |
50,000.00 |
150,000.00 |
150,000.00 |
250,000.00 |
250,000.00 |
250,000.00 |
250,000.00 |
| 713-02-C |
temporary pavement markings (8" width)
|
514   |
LNFT |
0.20 |
102.80 |
0.35 |
179.90 |
0.36 |
185.04 |
0.25 |
128.50 |
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
23.235 |
MILE |
400.00 |
9,294.00 |
375.00 |
8,713.13 |
350.00 |
8,132.25 |
150.00 |
3,485.25 |
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
14.441 |
MILE |
325.00 |
4,693.33 |
535.00 |
7,725.94 |
570.00 |
8,231.37 |
275.00 |
3,971.28 |
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
29.300 |
MILE |
700.00 |
20,510.00 |
625.00 |
18,312.50 |
706.00 |
20,685.80 |
600.00 |
17,580.00 |
| 713-05-A |
temporary pavement legends and symbols (arrow)
|
2   |
EACH |
60.00 |
120.00 |
55.00 |
110.00 |
60.00 |
120.00 |
65.00 |
130.00 |
| 713-05-C |
temporary pavement legends and symbols (only)
|
2   |
EACH |
60.00 |
120.00 |
55.00 |
110.00 |
60.00 |
120.00 |
65.00 |
130.00 |
| 713-06-A |
temporary reflectorized raised pavement markers (tabs)
|
898   |
EACH |
2.00 |
1,796.00 |
1.20 |
1,077.60 |
1.20 |
1,077.60 |
2.00 |
1,796.00 |
| 722-02 |
project site laboratory (equipped)
|
1   |
EACH |
10,000.00 |
10,000.00 |
20,000.00 |
20,000.00 |
14,500.00 |
14,500.00 |
9,000.00 |
9,000.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
150,000.00 |
150,000.00 |
450,000.00 |
450,000.00 |
300,000.00 |
300,000.00 |
705,000.00 |
705,000.00 |
| 729-16-C |
object marker assembly (type 3)
|
4   |
EACH |
150.00 |
600.00 |
85.00 |
340.00 |
98.00 |
392.00 |
96.69 |
386.76 |
| 731-01 |
nonreflectorized raised pavement markers
|
176   |
EACH |
15.00 |
2,640.00 |
17.00 |
2,992.00 |
18.00 |
3,168.00 |
14.00 |
2,464.00 |
| 731-02 |
reflectorized raised pavement markers
|
998   |
EACH |
6.00 |
5,988.00 |
5.80 |
5,788.40 |
6.35 |
6,337.30 |
6.00 |
5,988.00 |
| 732-01-C |
plastic pavement striping (8" width)
|
257   |
LNFT |
2.00 |
514.00 |
0.95 |
244.15 |
1.00 |
257.00 |
1.25 |
321.25 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
14.580 |
MILE |
2,500.00 |
36,450.00 |
3,000.00 |
43,740.00 |
3,150.00 |
45,927.00 |
2,600.00 |
37,908.00 |
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
7.220 |
MILE |
800.00 |
5,776.00 |
750.00 |
5,415.00 |
770.00 |
5,559.40 |
800.00 |
5,776.00 |
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
2   |
EACH |
200.00 |
400.00 |
200.00 |
400.00 |
210.00 |
420.00 |
165.00 |
330.00 |
| 732-04-C |
plastic pavement legends & symbols (only)
|
2   |
EACH |
200.00 |
400.00 |
225.00 |
450.00 |
240.00 |
480.00 |
165.00 |
330.00 |
| 732-05 |
removal of existing markings
|
0.063 |
MILE |
15,000.00 |
945.00 |
6,200.00 |
390.60 |
6,800.00 |
428.40 |
10,500.00 |
661.50 |
| 734-01 |
rubblizing portland cement concrete pavement
|
44,144   |
SQYD |
3.50 |
154,504.00 |
3.00 |
132,432.00 |
6.00 |
264,864.00 |
3.65 |
161,125.60 |
| 735-01 |
mailboxes
|
42   |
EACH |
1.00 |
42.00 |
10.00 |
420.00 |
1.20 |
50.40 |
1.00 |
42.00 |
| 735-02 |
mailbox supports (single)
|
32   |
EACH |
115.00 |
3,680.00 |
130.00 |
4,160.00 |
140.00 |
4,480.00 |
125.00 |
4,000.00 |
| 735-03 |
mailbox supports (double)
|
3   |
EACH |
150.00 |
450.00 |
175.00 |
525.00 |
190.00 |
570.00 |
175.00 |
525.00 |
| 735-04 |
mailbox supports (multiple)
|
1   |
EACH |
250.00 |
250.00 |
280.00 |
280.00 |
300.00 |
300.00 |
275.00 |
275.00 |
| 739-01 |
hydro-seeding
|
24.51 |
ACRE |
1,100.00 |
26,961.00 |
1,000.00 |
24,510.00 |
1,160.00 |
28,431.60 |
1,000.00 |
24,510.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
12,000.00 |
12,000.00 |
30,000.00 |
30,000.00 |
67,850.00 |
67,850.00 |
31,000.00 |
31,000.00 |
| S-001 |
dynamic message sign unit
|
2   |
EACH |
10,500.00 |
21,000.00 |
15,000.00 |
30,000.00 |
18,500.00 |
37,000.00 |
25,000.00 |
50,000.00 |
| S-002 |
rumble strips (ground-in)
|
14.0 |
MILE |
1,000.00 |
14,000.00 |
650.00 |
9,100.00 |
1,100.00 |
15,400.00 |
1,100.00 |
15,400.00 |
| S-922 |
sawing and sealing longitudinal joints in asphaltic
concrete overlay |
246   |
LNFT |
3.00 |
738.00 |
8.00 |
1,968.00 |
2.40 |
590.40 |
8.00 |
1,968.00 |
| S-923 |
sawing and sealing transverse joints in asphaltic
concrete overlay |
312   |
LNFT |
3.00 |
936.00 |
8.00 |
2,496.00 |
2.40 |
748.80 |
8.00 |
2,496.00 |
| S-927 |
sawcuts in asphaltic concrete lifts
|
1,116   |
LNFT |
3.00 |
3,348.00 |
4.50 |
5,022.00 |
2.00 |
2,232.00 |
5.00 |
5,580.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
5,973,090.64 |
|
6,230,119.33 |
|
6,750,310.59 |
|
7,653,790.44 |
|