LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: 080-03-0022
Parish: Lafayette
Routes: LA 94
Description: PINHOOK @ CARMEL (LA 94) INTERSECTION IMPROVEMENTS
Type Const: DRAINAGE STRUCTURES, PAVEMENT PATCHING, PAVEMENT WIDENING, COLD PLANING ASPHALTIC CONCRETE, SUPERPAVE ASPHALTIC CONCRETE OVERLAY AND RELATED WORK.
Estimated Construction Cost: $311,863.63


RankLicenseBidderConstruction Bid
1 51821 Elliott Construction, LLC $241,768.78
2 04089 H & S Construction Co., Inc. $283,272.97
3 33663 Glenn Lege Construction Inc $291,669.00
4 12312 Gilchrist Construction Co. LLC $311,292.63
5 12487 Diamond B Construction Co., L.L.C. $430,677.47


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
Elliott Construction, LLC
- 2 -
H & S Construction Co., Inc.
- 3 -
Glenn Lege Construction Inc
- 4 -
Gilchrist Construction Co. LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 63      CUYD 45.00 2,835.00 100.00 6,300.00 141.00 8,883.00 50.00 3,150.00
0002 502-01-00100 Superpave Asphaltic Concrete 471.5    TON 120.00 56,580.00 100.00 47,150.00 115.00 54,222.50 135.00 63,652.50
0003 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 93.7    TON 150.00 14,055.00 150.00 14,055.00 250.00 23,425.00 275.00 25,767.50
0004 509-01-00100 Cold Planing Asphaltic Pavement 5,455      SQYD 2.50 13,637.50 2.40 13,092.00 5.00 27,275.00 3.00 16,365.00
0005 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -227      CUYD 0.01 -2.27 0.01 -2.27 1.00 -227.00 1.00 -227.00
0006 510-01-00300 Pavement Patching (18" Minimum Thickness) 266.7    SQYD 55.00 14,668.50 200.00 53,340.00 185.00 49,339.50 160.00 42,672.00
0007 510-02-00100 Pavement Widening 279.7    SQYD 109.00 30,487.30 180.00 50,346.00 125.00 34,962.50 168.00 46,989.60
0008 701-03-01040 Storm Drain Pipe (24" RCP/PP) 152      LNFT 63.50 9,652.00 115.00 17,480.00 60.00 9,120.00 80.00 12,160.00
0009 701-15-00100 Concrete Collar 1      EACH 950.00 950.00 520.00 520.00 400.00 400.00 800.00 800.00
0010 702-03-00100 Catch Basins (CB-01) 2      EACH 2,225.00 4,450.00 2,500.00 5,000.00 2,600.00 5,200.00 4,000.00 8,000.00
0011 713-01-00100 Temporary Signs and Barricades 1      LUMP 8,500.00 8,500.00 9,000.00 9,000.00 17,000.00 17,000.00 15,000.00 15,000.00
0012 713-02-00100 Temporary Pavement Markings (4" Width) 60      LNFT 0.14 8.40 0.25 15.00 0.20 12.00 0.20 12.00
0013 713-02-00300 Temporary Pavement Markings (8" Width) 1,268      LNFT 0.26 329.68 0.50 634.00 0.25 317.00 0.30 380.40
0014 713-02-00500 Temporary Pavement Markings (24" Width) 665      LNFT 1.05 698.25 1.15 764.75 1.25 831.25 1.20 798.00
0015 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 0.742  MILE 420.00 311.64 375.00 278.25 1,100.00 816.20 310.00 230.02
0016 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 0.289  MILE 484.00 139.88 530.00 153.17 365.00 105.49 600.00 173.40
0017 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 1.279  MILE 574.00 734.15 610.00 780.19 785.00 1,004.02 695.00 888.91
0018 713-05-00100 Temporary Pavement Legends & Symbols (Arrow) 6      EACH 52.50 315.00 56.00 336.00 60.00 360.00 64.00 384.00
0019 713-05-00300 Temporary Pavement Legends & Symbols (ONLY) 6      EACH 52.50 315.00 56.00 336.00 60.00 360.00 64.00 384.00
0020 713-06-00100 Temporary Reflectorized Raised Pavement Markers 719      EACH 5.51 3,961.69 5.85 4,206.15 4.70 3,379.30 6.00 4,314.00
0021 727-01-00100 Mobilization 1      LUMP 49,400.00 49,400.00 19,000.00 19,000.00 25,125.00 25,125.00 31,000.00 31,000.00
0022 731-02-00100 Reflectorized Raised Pavement Markers 285      EACH 5.51 1,570.35 5.85 1,667.25 5.70 1,624.50 6.60 1,881.00
0023 732-01-01000 Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) 60      LNFT 0.53 31.80 0.56 33.60 0.60 36.00 0.70 42.00
0024 732-01-01040 Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 1,268      LNFT 1.42 1,800.56 1.50 1,902.00 1.25 1,585.00 1.70 2,155.60
0025 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 0.593  MILE 2,612.00 1,548.92 2,775.00 1,645.58 3,100.00 1,838.30 3,100.00 1,838.30
0026 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 0.074  MILE 845.00 62.53 950.00 70.30 810.00 59.94 1,100.00 81.40
0027 732-04-01080 Plastic Pavement Legends and Symbols (Arrow - Left Turn) 5      EACH 226.00 1,130.00 240.00 1,200.00 220.00 1,100.00 275.00 1,375.00
0028 732-04-01100 Plastic Pavement Legends and Symbols (Arrow - Right Turn) 1      EACH 226.00 226.00 240.00 240.00 220.00 220.00 275.00 275.00
0029 732-04-15020 Plastic Pavement Legends and Symbols (ONLY) 6      EACH 236.25 1,417.50 250.00 1,500.00 230.00 1,380.00 385.00 2,310.00
0030 732-05-00100 Removal of Existing Markings 0.1    MILE 5,250.00 525.00 5,550.00 555.00 5,400.00 540.00 6,500.00 650.00
0031 735-01-00100 Mailboxes 6      EACH 5.25 31.50 10.00 60.00 1.00 6.00 10.00 60.00
0032 735-02-00100 Mailbox Supports (Single) 6      EACH 173.25 1,039.50 165.00 990.00 200.00 1,200.00 200.00 1,200.00
0033 736-09-00100 Loop Detector 470      LNFT 10.50 4,935.00 25.00 11,750.00 11.75 5,522.50 13.00 6,110.00
0034 736-12-01000 Conductor (2c, Loop Lead in, imsa 50-2, #19 awg, Twisted Pair) 980      LNFT 1.58 1,548.40 1.40 1,372.00 1.75 1,715.00 1.80 1,764.00
0035 740-01-00100 Construction Layout 1      LUMP 1,500.00 1,500.00 3,500.00 3,500.00 4,500.00 4,500.00 8,000.00 8,000.00
0036 NS-201-00001 Tree and Stump Removal (Under 36" - 36" Diameter) 3      EACH 2,415.00 7,245.00 2,500.00 7,500.00 1,175.00 3,525.00 1,000.00 3,000.00
0037 NS-201-00002 Tree and Stump Removal (Over 36" - 48" Diameter) 1      EACH 3,675.00 3,675.00 3,500.00 3,500.00 3,160.00 3,160.00 3,000.00 3,000.00
0038 NS-500-00340 Saw Cutting Asphaltic Concrete Pavement 264      INLF 1.25 330.00 2.00 528.00 1.50 396.00 4.00 1,056.00
0039 NS-600-00220 Saw Cutting Portland Cement Concrete Pavement 900      INLF 1.25 1,125.00 2.75 2,475.00 1.50 1,350.00 4.00 3,600.00
                         
    CONTRACTOR TOTAL       241,768.78   283,272.97   291,669.00   311,292.63



Line
Number
Item Number Item Description Quantity Unit of
Measure
- 5 -
Diamond B Construction Co., L.L.C.
Unit PriceTotal
Amount
0001 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 63      CUYD 200.00 12,600.00
0002 502-01-00100 Superpave Asphaltic Concrete 471.5    TON 210.00 99,015.00
0003 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 93.7    TON 210.00 19,677.00
0004 509-01-00100 Cold Planing Asphaltic Pavement 5,455      SQYD 5.00 27,275.00
0005 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -227      CUYD 0.10 -22.70
0006 510-01-00300 Pavement Patching (18" Minimum Thickness) 266.7    SQYD 250.00 66,675.00
0007 510-02-00100 Pavement Widening 279.7    SQYD 120.00 33,564.00
0008 701-03-01040 Storm Drain Pipe (24" RCP/PP) 152      LNFT 250.00 38,000.00
0009 701-15-00100 Concrete Collar 1      EACH 2,500.00 2,500.00
0010 702-03-00100 Catch Basins (CB-01) 2      EACH 6,800.00 13,600.00
0011 713-01-00100 Temporary Signs and Barricades 1      LUMP 11,500.00 11,500.00
0012 713-02-00100 Temporary Pavement Markings (4" Width) 60      LNFT 0.25 15.00
0013 713-02-00300 Temporary Pavement Markings (8" Width) 1,268      LNFT 0.35 443.80
0014 713-02-00500 Temporary Pavement Markings (24" Width) 665      LNFT 1.70 1,130.50
0015 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 0.742  MILE 335.00 248.57
0016 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 0.289  MILE 500.00 144.50
0017 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 1.279  MILE 1,100.00 1,406.90
0018 713-05-00100 Temporary Pavement Legends & Symbols (Arrow) 6      EACH 100.00 600.00
0019 713-05-00300 Temporary Pavement Legends & Symbols (ONLY) 6      EACH 100.00 600.00
0020 713-06-00100 Temporary Reflectorized Raised Pavement Markers 719      EACH 7.00 5,033.00
0021 727-01-00100 Mobilization 1      LUMP 43,000.00 43,000.00
0022 731-02-00100 Reflectorized Raised Pavement Markers 285      EACH 8.00 2,280.00
0023 732-01-01000 Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) 60      LNFT 1.00 60.00
0024 732-01-01040 Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 1,268      LNFT 1.50 1,902.00
0025 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 0.593  MILE 4,500.00 2,668.50
0026 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 0.074  MILE 1,100.00 81.40
0027 732-04-01080 Plastic Pavement Legends and Symbols (Arrow - Left Turn) 5      EACH 300.00 1,500.00
0028 732-04-01100 Plastic Pavement Legends and Symbols (Arrow - Right Turn) 1      EACH 300.00 300.00
0029 732-04-15020 Plastic Pavement Legends and Symbols (ONLY) 6      EACH 300.00 1,800.00
0030 732-05-00100 Removal of Existing Markings 0.1    MILE 7,500.00 750.00
0031 735-01-00100 Mailboxes 6      EACH 25.00 150.00
0032 735-02-00100 Mailbox Supports (Single) 6      EACH 275.00 1,650.00
0033 736-09-00100 Loop Detector 470      LNFT 18.00 8,460.00
0034 736-12-01000 Conductor (2c, Loop Lead in, imsa 50-2, #19 awg, Twisted Pair) 980      LNFT 3.00 2,940.00
0035 740-01-00100 Construction Layout 1      LUMP 15,000.00 15,000.00
0036 NS-201-00001 Tree and Stump Removal (Under 36" - 36" Diameter) 3      EACH 2,000.00 6,000.00
0037 NS-201-00002 Tree and Stump Removal (Over 36" - 48" Diameter) 1      EACH 6,000.00 6,000.00
0038 NS-500-00340 Saw Cutting Asphaltic Concrete Pavement 264      INLF 1.25 330.00
0039 NS-600-00220 Saw Cutting Portland Cement Concrete Pavement 900      INLF 2.00 1,800.00
             
    CONTRACTOR TOTAL       430,677.47