| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 2 - BARRIERE CONSTRUCTION CO., LLC. |
- 3 - DICKERSON & BOWEN, INC. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
500,000.00 |
500,000.00 |
300,000.00 |
300,000.00 |
950,000.00 |
950,000.00 |
|
|
| 202-02-C |
removal of portland cement concrete pavement
|
984   |
SQYD |
21.00 |
20,664.00 |
12.00 |
11,808.00 |
25.67 |
25,259.28 |
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
18,641.9 |
SQYD |
1.85 |
34,487.52 |
3.00 |
55,925.70 |
2.37 |
44,181.30 |
|
|
| 202-02-H |
removal of guard rail
|
5,411   |
LNFT |
12.00 |
64,932.00 |
3.00 |
16,233.00 |
3.48 |
18,830.28 |
|
|
| 202-02-K |
removal of asphalt curb
|
4,088   |
LNFT |
1.00 |
4,088.00 |
2.00 |
8,176.00 |
1.35 |
5,518.80 |
|
|
| 202-02-L |
removal of incidental asphalt pavement
|
614   |
SQYD |
4.50 |
2,763.00 |
8.00 |
4,912.00 |
17.42 |
10,695.88 |
|
|
| 203-01-A |
general excavation (plan quantity measurement)
|
5,000   |
CUYD |
7.50 |
37,500.00 |
12.00 |
60,000.00 |
22.98 |
114,900.00 |
|
|
| 203-04-A |
embankment (plan quantity measurement)
|
100,000   |
CUYD |
14.50 |
1,450,000.00 |
17.00 |
1,700,000.00 |
21.67 |
2,167,000.00 |
|
|
| 204-02 |
temporary baled hay or straw
|
500   |
EACH |
9.00 |
4,500.00 |
11.00 |
5,500.00 |
9.01 |
4,505.00 |
|
|
| 204-06 |
temporary silt fencing
|
2,000   |
LNFT |
6.50 |
13,000.00 |
3.00 |
6,000.00 |
1.70 |
3,400.00 |
|
|
| 302-02-F |
class ii base course (12" thick)
|
11,268.8 |
SQYD |
30.00 |
338,064.00 |
23.40 |
263,689.92 |
35.07 |
395,196.82 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
700   |
CUYD |
22.00 |
15,400.00 |
90.00 |
63,000.00 |
69.02 |
48,314.00 |
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
500.0 |
CUYD |
12.00 |
6,000.00 |
50.00 |
25,000.00 |
29.03 |
14,515.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
198,462.5 |
TON |
60.50 |
12,006,981.25 |
62.50 |
12,403,906.25 |
94.64 |
18,782,491.00 |
|
|
| 509-01-A |
cold planing asphaltic pavement (2"thick)
|
47,326   |
SQYD |
2.60 |
123,047.60 |
1.00 |
47,326.00 |
1.63 |
77,141.38 |
|
|
| 509-01-B |
cold planing asphaltic pavement (3.85" avg. thick)
|
77,670   |
SQYD |
1.90 |
147,573.00 |
2.40 |
186,408.00 |
1.77 |
137,475.90 |
|
|
| 509-01-C |
cold planing asphaltic pavement (4" thick)
|
8,255   |
SQYD |
2.75 |
22,701.25 |
4.00 |
33,020.00 |
2.32 |
19,151.60 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 8,936   |
CUYD |
0.10 |
- 893.60 |
0.10 |
- 893.60 |
0.10 |
- 893.60 |
|
|
| 510-01-A |
pavement patching (6" minimum thickness)
|
5,000   |
SQYD |
1.00 |
5,000.00 |
12.00 |
60,000.00 |
34.76 |
173,800.00 |
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
10,000   |
SQYD |
1.00 |
10,000.00 |
16.00 |
160,000.00 |
64.38 |
643,800.00 |
|
|
| 602-02-A |
cleaning and resealing existing longitudinal joints
|
20,032   |
LNFT |
1.85 |
37,059.20 |
1.60 |
32,051.20 |
1.86 |
37,259.52 |
|
|
| 602-02-B |
cleaning and resealing existing transverse joints
|
20,684   |
LNFT |
2.25 |
46,539.00 |
1.60 |
33,094.40 |
2.12 |
43,850.08 |
|
|
| 602-03 |
cleaning and sealing random cracks
|
13,000   |
LNFT |
3.00 |
39,000.00 |
2.60 |
33,800.00 |
2.92 |
37,960.00 |
|
|
| 602-04 |
full depth corner patching of jointed concrete
pavement |
100.0 |
SQYD |
325.00 |
32,500.00 |
320.00 |
32,000.00 |
334.06 |
33,406.00 |
|
|
| 602-05-I-02 |
full depth patching of jointed concrete pavement
(16.1 sq yds to 48.0 sq yds) |
340.0 |
SQYD |
190.00 |
64,600.00 |
220.00 |
74,800.00 |
190.89 |
64,902.60 |
|
|
| 602-11 |
removal of existing shoulder underdrain systems
|
77,567   |
LNFT |
2.15 |
166,769.05 |
1.00 |
77,567.00 |
3.66 |
283,895.22 |
|
|
| 701-15 |
concrete collars
|
12   |
EACH |
700.00 |
8,400.00 |
1,000.00 |
12,000.00 |
689.33 |
8,271.96 |
|
|
| 702-04-B |
adjusting catch basins
|
13   |
EACH |
1,250.00 |
16,250.00 |
1,500.00 |
19,500.00 |
1,272.60 |
16,543.80 |
|
|
| 702-07-A |
cross drain safety end (type
|
3   |
EACH |
2,300.00 |
6,900.00 |
3,000.00 |
9,000.00 |
2,386.13 |
7,158.39 |
|
|
| 703-01 |
shoulder underdrains systems
|
78,067   |
LNFT |
4.00 |
312,268.00 |
8.00 |
624,536.00 |
4.38 |
341,933.46 |
|
|
| 703-02 |
shoulder outlet underdrains
|
170   |
EACH |
590.00 |
100,300.00 |
300.00 |
51,000.00 |
556.76 |
94,649.20 |
|
|
| 704-01-A |
guard rail (single thrie beam)(3'-1 1/2" post spacing)
|
125.0 |
LNFT |
31.00 |
3,875.00 |
32.00 |
4,000.00 |
31.82 |
3,977.50 |
|
|
| 704-01-B |
guard rail (single thrie beam)(6'-3" post spacing)
|
2,012.5 |
LNFT |
31.00 |
62,387.50 |
32.00 |
64,400.00 |
31.82 |
64,037.75 |
|
|
| 704-03 |
blocked out guard rail
|
3,112.5 |
LNFT |
20.00 |
62,250.00 |
19.00 |
59,137.50 |
19.62 |
61,067.25 |
|
|
| 704-06-A |
guard rail anchor sections (trailing end)(single thrie
beam) |
37.5 |
LNFT |
90.00 |
3,375.00 |
90.00 |
3,375.00 |
90.14 |
3,380.25 |
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
400.0 |
LNFT |
60.00 |
24,000.00 |
60.00 |
24,000.00 |
58.33 |
23,332.00 |
|
|
| 704-11-A |
guard rail end treatment (flared)
|
22   |
EACH |
2,000.00 |
44,000.00 |
2,000.00 |
44,000.00 |
2,014.95 |
44,328.90 |
|
|
| 706-03-A |
incidental concrete paving (4" thick)
|
1,305.6 |
SQYD |
50.00 |
65,280.00 |
50.00 |
65,280.00 |
51.17 |
66,807.55 |
|
|
| 710-01 |
flowable fill
|
100   |
CUYD |
130.00 |
13,000.00 |
150.00 |
15,000.00 |
219.14 |
21,914.00 |
|
|
| 711-01-C |
riprap (30 lb,1 foot)
|
307   |
SQYD |
80.00 |
24,560.00 |
120.00 |
36,840.00 |
79.54 |
24,418.78 |
|
|
| 712-01-A |
concrete cast-in-place revetment ( 4" thick)
|
487   |
SQYD |
60.00 |
29,220.00 |
55.00 |
26,785.00 |
62.04 |
30,213.48 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
400,000.00 |
400,000.00 |
380,000.00 |
380,000.00 |
208,000.00 |
208,000.00 |
|
|
| 713-02-C |
temporary pavement markings (8" width)
|
750   |
LNFT |
0.40 |
300.00 |
0.40 |
300.00 |
0.37 |
277.50 |
|
|
| 713-02-E |
temporary pavement markings (24" width)
|
100   |
LNFT |
1.00 |
100.00 |
1.00 |
100.00 |
1.00 |
100.00 |
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
43.720 |
MILE |
130.00 |
5,683.60 |
370.00 |
16,176.40 |
253.21 |
11,070.34 |
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
193.388 |
MILE |
900.00 |
174,049.20 |
800.00 |
154,710.40 |
837.80 |
162,020.47 |
|
|
| 713-04-A-01 |
temporary pavement markings (solid line)(4" width)
(type 1 removable) |
1.252 |
MILE |
16,000.00 |
20,032.00 |
17,000.00 |
21,284.00 |
16,490.78 |
20,646.46 |
|
|
| 713-08 |
temporary precast barrier (dotd furnished)
|
30   |
EACH |
75.00 |
2,250.00 |
1,000.00 |
30,000.00 |
586.05 |
17,581.50 |
|
|
| 720-01-A |
erosion control system, slope protection (type a)
|
150,000   |
SQYD |
1.10 |
165,000.00 |
0.20 |
30,000.00 |
1.06 |
159,000.00 |
|
|
| 720-01-D |
erosion control sysyem, flexible channel liner (type d)
|
250   |
SQYD |
1.75 |
437.50 |
3.00 |
750.00 |
1.75 |
437.50 |
|
|
| 721-01 |
mowing
|
264.0 |
ACRE |
60.00 |
15,840.00 |
170.00 |
44,880.00 |
102.67 |
27,104.88 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
835,000.00 |
835,000.00 |
740,000.00 |
740,000.00 |
905,000.00 |
905,000.00 |
|
|
| 729-16-B |
object marker assembly(type b)
|
94   |
EACH |
62.00 |
5,828.00 |
65.00 |
6,110.00 |
63.63 |
5,981.22 |
|
|
| 729-16-C |
object marker assembly(type c)
|
24   |
EACH |
77.00 |
1,848.00 |
80.00 |
1,920.00 |
79.54 |
1,908.96 |
|
|
| 731-01 |
nonreflectorized raised pavement markers
|
169   |
EACH |
16.00 |
2,704.00 |
20.00 |
3,380.00 |
15.91 |
2,688.79 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
2,000   |
EACH |
6.00 |
12,000.00 |
6.00 |
12,000.00 |
5.83 |
11,660.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
32.261 |
MILE |
3,000.00 |
96,783.00 |
2,800.00 |
90,330.80 |
2,916.38 |
94,085.34 |
|
|
| 732-02-C |
plastic pavement striping (solid line) (8" width)
|
1.515 |
MILE |
6,200.00 |
9,393.00 |
6,000.00 |
9,090.00 |
6,256.95 |
9,479.28 |
|
|
| 732-02-E |
plastic pavement striping (solid line) (24" width)
|
0.227 |
MILE |
18,500.00 |
4,199.50 |
18,000.00 |
4,086.00 |
18,982.95 |
4,309.13 |
|
|
| 732-03-A-01 |
plastic pavement striping (broken line)(4" width)
(marking tape performed type v) |
8.200 |
MILE |
4,700.00 |
38,540.00 |
4,600.00 |
37,720.00 |
4,772.25 |
39,132.45 |
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
6   |
EACH |
210.00 |
1,260.00 |
400.00 |
2,400.00 |
206.80 |
1,240.80 |
|
|
| 732-05 |
removal of existing markings
|
7.332 |
MILE |
6,200.00 |
45,458.40 |
6,400.00 |
46,924.80 |
6,256.95 |
45,875.96 |
|
|
| 734-01 |
rubblizing portland cement concrete pavement
|
198,435   |
SQYD |
3.04 |
603,242.40 |
3.30 |
654,835.50 |
4.00 |
793,740.00 |
|
|
| 739-01 |
hydro-seeding
|
76.00 |
ACRE |
1,000.00 |
76,000.00 |
1,000.00 |
76,000.00 |
954.45 |
72,538.20 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
100,000.00 |
100,000.00 |
130,000.00 |
130,000.00 |
520,000.00 |
520,000.00 |
|
|
| S-001 |
rumble strips (ground-in)
|
29.1 |
MILE |
475.00 |
13,822.50 |
610.00 |
17,751.00 |
713.10 |
20,751.21 |
|
|
| S-002 |
milling concrete pavement
|
9,338   |
SQYD |
8.00 |
74,704.00 |
5.00 |
46,690.00 |
4.32 |
40,340.16 |
|
|
| S-003 |
concrete apron
|
38   |
EACH |
800.00 |
30,400.00 |
1,000.00 |
38,000.00 |
795.38 |
30,224.44 |
|
|
| S-004 |
exposing existing pipe (size varies)
|
148   |
LNFT |
21.00 |
3,108.00 |
100.00 |
14,800.00 |
21.21 |
3,139.08 |
|
|
| S-005 |
remove and relocate sign posts and footings
|
48   |
EACH |
900.00 |
43,200.00 |
1,000.00 |
48,000.00 |
927.94 |
44,541.12 |
|
|
| S-006 |
traffic maintenance superpave asphaltic concrete
|
500.0 |
TON |
86.00 |
43,000.00 |
130.00 |
65,000.00 |
119.62 |
59,810.00 |
|
|
| S-007 |
dynamic message sign unit
|
4   |
each |
11,000.00 |
44,000.00 |
27,000.00 |
108,000.00 |
26,424.13 |
105,696.52 |
|
|
| S-008 |
surface preparation
|
lump |
LUMP |
38,300.00 |
38,300.00 |
30,000.00 |
30,000.00 |
18,377.83 |
18,377.83 |
|
|
| S-009 |
adjusting guard rail
|
2,243.5 |
LNFT |
12.00 |
26,922.00 |
12.00 |
26,922.00 |
12.20 |
27,370.70 |
|
|
| S-922 |
sawing and sealing longitudinal joints in asphaltic
concrete overlay |
53,930   |
LNFT |
1.30 |
70,109.00 |
1.70 |
91,681.00 |
1.80 |
97,074.00 |
|
|
| S-923 |
sawing and sealing transverse joints in asphaltic
concrete overlay |
11,736   |
LNFT |
1.60 |
18,777.60 |
1.70 |
19,951.20 |
1.80 |
21,124.80 |
|
|
| S-927 |
sawcuts in asphaltic concrete lifts
|
110,830   |
LNFT |
1.00 |
110,830.00 |
0.20 |
22,166.00 |
0.74 |
82,014.20 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
19,101,462.47 |
|
19,774,136.47 |
|
28,612,933.17 |
|
|
|