| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - DENTON-JAMES LLC |
- 2 - GILCHRIST CONSTRUCTION CO. LLC |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
100,000.00 |
100,000.00 |
100,000.00 |
100,000.00 |
|
|
|
|
| 202-02-C |
removal of portland cement concrete pavement
|
11,810   |
SQYD |
6.00 |
70,860.00 |
7.00 |
82,670.00 |
|
|
|
|
| 202-02-D |
removal of concrete walks & drives
|
2,049   |
SQYD |
10.00 |
20,490.00 |
9.00 |
18,441.00 |
|
|
|
|
| 202-02-E |
removal of concrete curbs
|
7,650.5 |
LNFT |
3.00 |
22,951.50 |
2.00 |
15,301.00 |
|
|
|
|
| 202-02-I |
removal of existing trunklines
|
602   |
LNFT |
20.00 |
12,040.00 |
28.00 |
16,856.00 |
|
|
|
|
| 202-02-J |
removal of asphalt drives
|
653   |
SQYD |
5.00 |
3,265.00 |
8.60 |
5,615.80 |
|
|
|
|
| 203-05 |
excavation and embankment
|
lump |
LUMP |
400,000.00 |
400,000.00 |
400,000.00 |
400,000.00 |
|
|
|
|
| 204-02 |
temporary hay or straw bales
|
240   |
EACH |
9.00 |
2,160.00 |
40.00 |
9,600.00 |
|
|
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
12   |
EACH |
130.00 |
1,560.00 |
200.00 |
2,400.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
60   |
LNFT |
4.00 |
240.00 |
10.00 |
600.00 |
|
|
|
|
| 302-02-C |
class ii base course (8" thick)
|
14,742.3 |
SQYD |
25.00 |
368,557.50 |
21.00 |
309,588.30 |
|
|
|
|
| 305-01-D |
subgrade layer (12" thick)
|
14,742   |
SQYD |
10.00 |
147,420.00 |
11.00 |
162,162.00 |
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
5,000.0 |
CUYD |
60.00 |
300,000.00 |
56.00 |
280,000.00 |
|
|
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
131   |
SQYD |
130.00 |
17,030.00 |
200.00 |
26,200.00 |
|
|
|
|
| 601-01-G |
portland cement concrete pavement (8" thick)
|
13,692.3 |
SQYD |
54.00 |
739,384.20 |
62.00 |
848,922.60 |
|
|
|
|
| 701-03-F |
storm drain pipe (15" rcp/pcp)
|
291   |
LNFT |
55.00 |
16,005.00 |
165.00 |
48,015.00 |
|
|
|
|
| 701-03-G |
storm drain pipe (18" rcp/pcp)
|
936   |
LNFT |
80.00 |
74,880.00 |
168.00 |
157,248.00 |
|
|
|
|
| 701-03-I |
storm drain pipe (24" rcp/pcp)
|
196   |
LNFT |
88.00 |
17,248.00 |
175.00 |
34,300.00 |
|
|
|
|
| 701-03-K |
storm drain pipe (30" rcp/pcp)
|
68   |
LNFT |
100.00 |
6,800.00 |
230.00 |
15,640.00 |
|
|
|
|
| 701-05-I |
side drain pipe (24")
|
160   |
LNFT |
72.00 |
11,520.00 |
100.00 |
16,000.00 |
|
|
|
|
| 701-15 |
concrete collar
|
20   |
EACH |
700.00 |
14,000.00 |
1,000.00 |
20,000.00 |
|
|
|
|
| 702-03-A |
catch basins (cb-01)
|
5   |
EACH |
3,000.00 |
15,000.00 |
3,300.00 |
16,500.00 |
|
|
|
|
| 702-03-C |
catch basins (cb-06)
|
49   |
EACH |
4,500.00 |
220,500.00 |
3,600.00 |
176,400.00 |
|
|
|
|
| 702-04-A |
adjusting manholes
|
5   |
EACH |
1,200.00 |
6,000.00 |
1,200.00 |
6,000.00 |
|
|
|
|
| 703-02 |
shoulder outlet underdrains
|
7   |
EACH |
500.00 |
3,500.00 |
1,000.00 |
7,000.00 |
|
|
|
|
| 703-03 |
perforated pipe underdrains
|
9,000   |
LNFT |
10.00 |
90,000.00 |
12.00 |
108,000.00 |
|
|
|
|
| 703-06 |
underdrain video inspection
|
3,010   |
LNFT |
2.50 |
7,525.00 |
6.00 |
18,060.00 |
|
|
|
|
| 706-01-A |
concrete walk (4" thick)
|
19.4 |
SQYD |
70.00 |
1,358.00 |
100.00 |
1,940.00 |
|
|
|
|
| 706-02-C |
concrete drive (6" thick)
|
2,017.3 |
SQYD |
52.00 |
104,899.60 |
78.00 |
157,349.40 |
|
|
|
|
| 706-03-C |
incidental concrete paving (6" thick)
|
50.0 |
SQYD |
75.00 |
3,750.00 |
100.00 |
5,000.00 |
|
|
|
|
| 707-01 |
concrete curb
|
8,394.7 |
LNFT |
5.00 |
41,973.50 |
10.00 |
83,947.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
100,000.00 |
100,000.00 |
450,000.00 |
450,000.00 |
|
|
|
|
| 713-02-E |
temporary pavement markings (24" width)
|
84   |
LNFT |
1.00 |
84.00 |
1.20 |
100.80 |
|
|
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
0.855 |
MILE |
800.00 |
684.00 |
1,200.00 |
1,026.00 |
|
|
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
0.855 |
MILE |
400.00 |
342.00 |
400.00 |
342.00 |
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
2.083 |
MILE |
500.00 |
1,041.50 |
550.00 |
1,145.65 |
|
|
|
|
| 713-05-E |
temporary pavement legends and symbols (school
crossing) |
1   |
EACH |
200.00 |
200.00 |
230.00 |
230.00 |
|
|
|
|
| 720-01-A |
erosion control system, slope protection (type a)
|
2,600   |
SQYD |
1.30 |
3,380.00 |
1.50 |
3,900.00 |
|
|
|
|
| 722-02 |
project site laboratory (equipped)
|
1   |
EACH |
20,000.00 |
20,000.00 |
30,000.00 |
30,000.00 |
|
|
|
|
| 726-01 |
bedding material
|
508.1 |
CUYD |
80.00 |
40,648.00 |
90.00 |
45,729.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
340,000.00 |
340,000.00 |
425,000.00 |
425,000.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
115   |
EACH |
5.50 |
632.50 |
5.25 |
603.75 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
84   |
LNFT |
4.00 |
336.00 |
4.00 |
336.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
2.083 |
MILE |
2,600.00 |
5,415.80 |
2,600.00 |
5,415.80 |
|
|
|
|
| 732-03-A |
plastic pvmt striping (broken line)(4"width)
|
0.819 |
MILE |
800.00 |
655.20 |
850.00 |
696.15 |
|
|
|
|
| 732-04-E |
plastic pavement legends & symbols (school crossing)
|
1   |
EACH |
430.00 |
430.00 |
500.00 |
500.00 |
|
|
|
|
| 735-01 |
mailboxes
|
3   |
EACH |
1.00 |
3.00 |
20.00 |
60.00 |
|
|
|
|
| 735-02 |
mailbox supports (single)
|
3   |
EACH |
250.00 |
750.00 |
150.00 |
450.00 |
|
|
|
|
| 739-01 |
hydro-seeding
|
4.00 |
ACRE |
1,200.00 |
4,800.00 |
1,200.00 |
4,800.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
50,000.00 |
50,000.00 |
200,000.00 |
200,000.00 |
|
|
|
|
| 741-11 |
adjusting water valve and meter box
|
3   |
EACH |
800.00 |
2,400.00 |
300.00 |
900.00 |
|
|
|
|
| S-001 |
sawcuts in asphaltic concrete
|
2,994   |
INFT |
0.80 |
2,395.20 |
1.70 |
5,089.80 |
|
|
|
|
| S-002 |
sawcuts in concrete pavement
|
8,634   |
INFT |
1.10 |
9,497.40 |
1.90 |
16,404.60 |
|
|
|
|
| S-003 |
paved gutter drains
|
7   |
EACH |
2,500.00 |
17,500.00 |
4,000.00 |
28,000.00 |
|
|
|
|
| S-004 |
adjusting sewer blowouts
|
1   |
EACH |
1,000.00 |
1,000.00 |
300.00 |
300.00 |
|
|
|
|
| S-005 |
dynamic message sign unit
|
2   |
EACH |
20,000.00 |
40,000.00 |
10,000.00 |
20,000.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
3,483,111.90 |
|
4,390,785.65 |
|
|
|
|
|