| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - C W & W CONTRACTORS, INC. |
- 2 - APECK CONSTRUCTION, INC. |
- 3 - T.L. CONSTRUCTION INC |
- 4 - JEFF MERCER LLC |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
5,000.00 |
5,000.00 |
600.00 |
600.00 |
7,500.00 |
7,500.00 |
6,000.00 |
6,000.00 |
| 202-02-C |
removal of portland cement concrete pavement
|
295   |
SQYD |
10.00 |
2,950.00 |
17.00 |
5,015.00 |
25.00 |
7,375.00 |
15.00 |
4,425.00 |
| 202-02-D |
removal of concrete walks & drives
|
37   |
SQYD |
10.00 |
370.00 |
10.00 |
370.00 |
25.00 |
925.00 |
15.00 |
555.00 |
| 202-02-E |
removal of concrete curbs
|
61.0 |
LNFT |
10.00 |
610.00 |
9.00 |
549.00 |
25.00 |
1,525.00 |
10.00 |
610.00 |
| 202-02-G |
removal of surfacing & stabilized base
|
504.8 |
SQYD |
10.00 |
5,048.00 |
14.00 |
7,067.20 |
20.00 |
10,096.00 |
5.00 |
2,524.00 |
| 203-05 |
excavation & embankment
|
lump |
LUMP |
5,000.00 |
5,000.00 |
6,500.00 |
6,500.00 |
6,000.00 |
6,000.00 |
17,000.00 |
17,000.00 |
| 204-06 |
temporary silt fencing
|
200   |
LNFT |
1.00 |
200.00 |
3.50 |
700.00 |
5.00 |
1,000.00 |
1.50 |
300.00 |
| 302-02-D-01 |
class ii base course (8 1/2" thick) (crushed stone)
|
736.5 |
SQYD |
23.00 |
16,939.50 |
15.68 |
11,548.32 |
36.00 |
26,514.00 |
35.00 |
25,777.50 |
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
50.0 |
CUYD |
100.00 |
5,000.00 |
69.20 |
3,460.00 |
70.00 |
3,500.00 |
25.00 |
1,250.00 |
| 601-02-K |
portland cement concrete pavement (10" thick)
(crossovers & turnouts) |
710.3 |
SQYD |
80.00 |
56,824.00 |
166.74 |
118,435.42 |
100.00 |
71,030.00 |
165.00 |
117,199.50 |
| 702-04-B |
adjusting catch basins
|
1   |
EACH |
2,500.00 |
2,500.00 |
1,500.00 |
1,500.00 |
2,500.00 |
2,500.00 |
5,800.00 |
5,800.00 |
| 707-01 |
concrete curb
|
238.4 |
LNFT |
12.00 |
2,860.80 |
20.00 |
4,768.00 |
15.00 |
3,576.00 |
25.00 |
5,960.00 |
| 708-01 |
right-of-way monument
|
4   |
EACH |
300.00 |
1,200.00 |
200.00 |
800.00 |
100.00 |
400.00 |
250.00 |
1,000.00 |
| 708-02 |
right-of-way monument witness post
|
4   |
EACH |
300.00 |
1,200.00 |
150.00 |
600.00 |
400.00 |
1,600.00 |
250.00 |
1,000.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
15,000.00 |
15,000.00 |
6,000.00 |
6,000.00 |
20,000.00 |
20,000.00 |
5,000.00 |
5,000.00 |
| 713-02-A |
temporary pavement markings (4" width)
|
500   |
LNFT |
1.00 |
500.00 |
1.00 |
500.00 |
1.00 |
500.00 |
0.50 |
250.00 |
| 713-02-E |
temporary pavement markings (24" width)
|
12   |
LNFT |
20.00 |
240.00 |
5.00 |
60.00 |
10.00 |
120.00 |
1.50 |
18.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
30,000.00 |
30,000.00 |
1,500.00 |
1,500.00 |
10,000.00 |
10,000.00 |
39,000.00 |
39,000.00 |
| 731-02 |
reflectorized raised pavement markers
|
3   |
EACH |
500.00 |
1,500.00 |
10.00 |
30.00 |
25.00 |
75.00 |
15.00 |
45.00 |
| 732-01-A |
plastic pavement striping (4" width)
|
500   |
LNFT |
10.00 |
5,000.00 |
12.00 |
6,000.00 |
15.00 |
7,500.00 |
0.50 |
250.00 |
| 732-01-E |
plastic pavement striping (24" width)
|
12   |
LNFT |
100.00 |
1,200.00 |
10.00 |
120.00 |
15.00 |
180.00 |
0.50 |
6.00 |
| 739-01 |
hydro-seeding
|
0.50 |
ACRE |
5,000.00 |
2,500.00 |
2,600.00 |
1,300.00 |
4,000.00 |
2,000.00 |
1,250.00 |
625.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
10,000.00 |
10,000.00 |
1,500.00 |
1,500.00 |
7,500.00 |
7,500.00 |
3,500.00 |
3,500.00 |
| S-001 |
sawcuts in asphaltic concrete lifts
|
327   |
LNFT |
4.00 |
1,308.00 |
24.00 |
7,848.00 |
15.00 |
4,905.00 |
5.00 |
1,635.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
172,950.30 |
|
186,770.94 |
|
196,321.00 |
|
239,730.00 |
|
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 5 - DENTON-JAMES LLC |
|
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
65,000.00 |
65,000.00 |
|
|
|
|
|
|
| 202-02-C |
removal of portland cement concrete pavement
|
295   |
SQYD |
15.00 |
4,425.00 |
|
|
|
|
|
|
| 202-02-D |
removal of concrete walks & drives
|
37   |
SQYD |
20.00 |
740.00 |
|
|
|
|
|
|
| 202-02-E |
removal of concrete curbs
|
61.0 |
LNFT |
9.00 |
549.00 |
|
|
|
|
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
504.8 |
SQYD |
7.00 |
3,533.60 |
|
|
|
|
|
|
| 203-05 |
excavation & embankment
|
lump |
LUMP |
23,000.00 |
23,000.00 |
|
|
|
|
|
|
| 204-06 |
temporary silt fencing
|
200   |
LNFT |
4.00 |
800.00 |
|
|
|
|
|
|
| 302-02-D-01 |
class ii base course (8 1/2" thick) (crushed stone)
|
736.5 |
SQYD |
32.00 |
23,568.00 |
|
|
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
50.0 |
CUYD |
80.00 |
4,000.00 |
|
|
|
|
|
|
| 601-02-K |
portland cement concrete pavement (10" thick)
(crossovers & turnouts) |
710.3 |
SQYD |
90.00 |
63,927.00 |
|
|
|
|
|
|
| 702-04-B |
adjusting catch basins
|
1   |
EACH |
2,000.00 |
2,000.00 |
|
|
|
|
|
|
| 707-01 |
concrete curb
|
238.4 |
LNFT |
12.00 |
2,860.80 |
|
|
|
|
|
|
| 708-01 |
right-of-way monument
|
4   |
EACH |
250.00 |
1,000.00 |
|
|
|
|
|
|
| 708-02 |
right-of-way monument witness post
|
4   |
EACH |
250.00 |
1,000.00 |
|
|
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
7,000.00 |
7,000.00 |
|
|
|
|
|
|
| 713-02-A |
temporary pavement markings (4" width)
|
500   |
LNFT |
2.70 |
1,350.00 |
|
|
|
|
|
|
| 713-02-E |
temporary pavement markings (24" width)
|
12   |
LNFT |
16.00 |
192.00 |
|
|
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
25,000.00 |
25,000.00 |
|
|
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
3   |
EACH |
46.00 |
138.00 |
|
|
|
|
|
|
| 732-01-A |
plastic pavement striping (4" width)
|
500   |
LNFT |
4.00 |
2,000.00 |
|
|
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
12   |
LNFT |
32.00 |
384.00 |
|
|
|
|
|
|
| 739-01 |
hydro-seeding
|
0.50 |
ACRE |
3,000.00 |
1,500.00 |
|
|
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
7,000.00 |
7,000.00 |
|
|
|
|
|
|
| S-001 |
sawcuts in asphaltic concrete lifts
|
327   |
LNFT |
10.00 |
3,270.00 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
244,237.40 |
|
|
|
|
|
|
|