Letting of 12/12/2007 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 046-03-0070
Parish: ST BERNARD
Routes: LA 46
Description: ST. BERNARD HIGHWAY DRAINAGE IMPROVEMENTS PHASE II
Type Const: drainage structures, cold planing ashpaltic concrete, superpave asphaltic concrete
pavement, and related work.
Estimated Construction Cost: $2,827,382.45
 
RankLicenseBidderConstruction Bid
1 02179 BOH BROS. CONSTRUCTION CO., LLC. $3,004,254.00
2 45210 CERES ENVIRONMENTAL SERVICES,INC. $3,480,976.20
3 25088 RCS CONTRACTORS, INC. $3,899,132.90
4 27634 PHYLWAY CONSTRUCTION LLC $4,352,676.50
5 06276 BARRIERE CONSTRUCTION CO., LLC. $4,749,631.50
6 35678 BEVERLY CONSTRUCTION CO. LLC $4,876,899.37
 
Item Number Item Description Quantity Unit of Measure - 1 -
BOH BROS. CONSTRUCTION CO., LLC.
- 2 -
CERES ENVIRONMENTAL SERVICES,INC.
- 3 -
RCS CONTRACTORS, INC.
- 4 -
PHYLWAY CONSTRUCTION LLC
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-01 removal of structures & obstructions lump      LUMP 10,000.00 10,000.00 9,600.00 9,600.00 5,000.00 5,000.00 26,000.00 26,000.00
202-02-C removal of portland cement concrete pavement 75      SQYD 45.00 3,375.00 15.60 1,170.00 15.00 1,125.00 25.00 1,875.00
202-02-I removal of steel sheet piling 106      LNFT 10.00 1,060.00 108.00 11,448.00 12.00 1,272.00 60.00 6,360.00
202-02-L removal of abandoned (12x6x7) telephone vault 8      EACH 7,500.00 60,000.00 960.00 7,680.00 500.00 4,000.00 3,500.00 28,000.00
202-02-M removal of abandoned (16x6x9) telephone vault 2      EACH 8,000.00 16,000.00 960.00 1,920.00 500.00 1,000.00 3,500.00 7,000.00
203-05 excavation and embankment lump      LUMP 100,000.00 100,000.00 156,000.00 156,000.00 5,000.00 5,000.00 75,000.00 75,000.00
203-07-A borrow (vehicular meas.)(selected soils) 1,350      CUYD 10.00 13,500.00 19.20 25,920.00 20.00 27,000.00 25.00 33,750.00
204-06 temporary silt fencing 336      LNFT 2.00 672.00 3.00 1,008.00 4.00 1,344.00 4.00 1,344.00
502-01 superpave asphaltic concrete 587.5    TON 190.00 111,625.00 142.80 83,895.00 120.00 70,500.00 125.00 73,437.50
509-01 cold planing asphaltic pavement 2,671      SQYD 1.00 2,671.00 4.80 12,820.80 4.40 11,752.40 5.00 13,355.00
509-02 contractor retained reclaimed asphaltic pavement - 111      CUYD 15.00 - 1,665.00 FREE FREE 1.00 - 111.00 1.00 - 111.00
601-02-O portland cement concrete pavement (12" thick)
(crossovers & turnouts)
75.0    SQYD 200.00 15,000.00 138.00 10,350.00 100.00 7,500.00 140.00 10,500.00
701-10-E reinforced concrete pipe (extension)(12") 86      LNFT 125.00 10,750.00 69.60 5,985.60 57.00 4,902.00 80.00 6,880.00
701-10-I reinforced concrete pipe (extension)(24") 52      LNFT 150.00 7,800.00 102.00 5,304.00 81.00 4,212.00 140.00 7,280.00
701-10-M reinforced concrete pipe (extension)(36") 32      LNFT 240.00 7,680.00 198.00 6,336.00 92.50 2,960.00 220.00 7,040.00
702-03-A catch basins (cb-01) 19      EACH 3,000.00 57,000.00 2,400.00 45,600.00 2,300.00 43,700.00 2,800.00 53,200.00
702-03-B catch basins (cb-02) 2      EACH 5,500.00 11,000.00 3,720.00 7,440.00 3,100.00 6,200.00 5,000.00 10,000.00
713-01 temporary signs & barricades lump      LUMP 25,000.00 25,000.00 28,800.00 28,800.00 34,000.00 34,000.00 45,000.00 45,000.00
717-01 seeding 105      LB 5.00 525.00 13.20 1,386.00 11.10 1,165.50 12.00 1,260.00
718-01 fertilizer 3,500      LB 0.50 1,750.00 0.60 2,100.00 0.40 1,400.00 0.60 2,100.00
726-01 bedding material 1,600.0    CUYD 60.00 96,000.00 74.40 119,040.00 0.01 16.00 90.00 144,000.00
727-01 mobilization lump      LUMP 135,000.00 135,000.00 296,520.00 296,520.00 280,250.00 280,250.00 360,000.00 360,000.00
729-19-C dead end road installations(type c) 2      EACH 1,100.00 2,200.00 2,400.00 4,800.00 800.00 1,600.00 800.00 1,600.00
732-02-A plastic pavement striping (solid line) (4" width) 0.570  MILE 3,500.00 1,995.00 7,200.00 4,104.00 3,300.00 1,881.00 3,400.00 1,938.00
740-01 construction layout lump      LUMP 30,000.00 30,000.00 54,000.00 54,000.00 148,000.00 148,000.00 40,000.00 40,000.00
S-001 rumble strips (ground-in) 1.8    MILE 1,500.00 2,700.00 3,600.00 6,480.00 1,530.00 2,754.00 1,800.00 3,240.00
S-003 reinforced concrete box culvert (10x5) 2,924      LNFT 775.00 2,266,100.00 870.00 2,543,880.00 1,090.00 3,187,160.00 1,150.00 3,362,600.00
S-004 cleaning existing ditches 300      LNFT 15.00 4,500.00 19.20 5,760.00 20.00 6,000.00 30.00 9,000.00
S-005 roadway joint reinforcing mesh (detail repair system) 3,004      LNFT 4.00 12,016.00 7.20 21,628.80 12.50 37,550.00 7.00 21,028.00
                       
 CONTRACTOR TOTAL       3,004,254.00   3,480,976.20   3,899,132.90   4,352,676.50
 
Item Number Item Description Quantity Unit of Measure - 5 -
BARRIERE CONSTRUCTION CO., LLC.
- 6 -
BEVERLY CONSTRUCTION CO. LLC

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-01 removal of structures & obstructions lump      LUMP 25,000.00 25,000.00 71,000.00 71,000.00        
202-02-C removal of portland cement concrete pavement 75      SQYD 11.00 825.00 62.00 4,650.00        
202-02-I removal of steel sheet piling 106      LNFT 80.00 8,480.00 100.00 10,600.00        
202-02-L removal of abandoned (12x6x7) telephone vault 8      EACH 2,000.00 16,000.00 2,600.00 20,800.00        
202-02-M removal of abandoned (16x6x9) telephone vault 2      EACH 3,000.00 6,000.00 5,000.00 10,000.00        
203-05 excavation and embankment lump      LUMP 30,000.00 30,000.00 84,000.00 84,000.00        
203-07-A borrow (vehicular meas.)(selected soils) 1,350      CUYD 22.00 29,700.00 20.00 27,000.00        
204-06 temporary silt fencing 336      LNFT 3.00 1,008.00 3.75 1,260.00        
502-01 superpave asphaltic concrete 587.5    TON 109.00 64,037.50 132.50 77,843.75        
509-01 cold planing asphaltic pavement 2,671      SQYD 4.00 10,684.00 4.50 12,019.50        
509-02 contractor retained reclaimed asphaltic pavement - 111      CUYD 1.00 - 111.00 1.00 - 111.00        
601-02-O portland cement concrete pavement (12" thick)
(crossovers & turnouts)
75.0    SQYD 110.00 8,250.00 271.00 20,325.00        
701-10-E reinforced concrete pipe (extension)(12") 86      LNFT 220.00 18,920.00 110.00 9,460.00        
701-10-I reinforced concrete pipe (extension)(24") 52      LNFT 270.00 14,040.00 135.00 7,020.00        
701-10-M reinforced concrete pipe (extension)(36") 32      LNFT 400.00 12,800.00 190.00 6,080.00        
702-03-A catch basins (cb-01) 19      EACH 4,100.00 77,900.00 5,650.00 107,350.00        
702-03-B catch basins (cb-02) 2      EACH 5,800.00 11,600.00 6,000.00 12,000.00        
713-01 temporary signs & barricades lump      LUMP 125,000.00 125,000.00 109,000.00 109,000.00        
717-01 seeding 105      LB 10.00 1,050.00 12.30 1,291.50        
718-01 fertilizer 3,500      LB 0.30 1,050.00 0.80 2,800.00        
726-01 bedding material 1,600.0    CUYD 60.00 96,000.00 103.00 164,800.00        
727-01 mobilization lump      LUMP 300,000.00 300,000.00 165,000.00 165,000.00        
729-19-C dead end road installations(type c) 2      EACH 800.00 1,600.00 625.00 1,250.00        
732-02-A plastic pavement striping (solid line) (4" width) 0.570  MILE 8,000.00 4,560.00 3,366.00 1,918.62        
740-01 construction layout lump      LUMP 45,000.00 45,000.00 35,000.00 35,000.00        
S-001 rumble strips (ground-in) 1.8    MILE 2,500.00 4,500.00 3,120.00 5,616.00        
S-003 reinforced concrete box culvert (10x5) 2,924      LNFT 1,300.00 3,801,200.00 1,260.00 3,684,240.00        
S-004 cleaning existing ditches 300      LNFT 20.00 6,000.00 33.00 9,900.00        
S-005 roadway joint reinforcing mesh (detail repair system) 3,004      LNFT 9.50 28,538.00 71.50 214,786.00        
                       
 CONTRACTOR TOTAL       4,749,631.50   4,876,899.37        