Letting of 12/12/2007 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 026-02-0060
Parish: CONCORDIA
Routes: US 65
Description: VIDALIA - FERRIDAY (TURN LANES)
Type Const: grading, drainage structures, superpave asphaltic concrete overlay and related work.
Estimated Construction Cost: $1,100,253.04
 
RankLicenseBidderConstruction Bid
1 02214 W. E. BLAIN & SONS, INC. $1,139,335.98
2 12312 GILCHRIST CONSTRUCTION CO. LLC $1,400,296.27
3 05789 D & J CONSTRUCTION CO., INC. $1,415,359.90
 
Item Number Item Description Quantity Unit of Measure - 1 -
W. E. BLAIN & SONS, INC.
- 2 -
GILCHRIST CONSTRUCTION CO. LLC
- 3 -
D & J CONSTRUCTION CO., INC.

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-02-E removal of concrete curbs 2,190.4    LNFT 5.00 10,952.00 1.80 3,942.72 7.00 15,332.80    
202-02-I removal of shoulder 3,717      LNFT 5.00 18,585.00 25.00 92,925.00 12.00 44,604.00    
203-01 general excavation 2,952      CUYD 30.00 88,560.00 15.00 44,280.00 25.00 73,800.00    
502-01 superpave asphaltic concrete 6,001.7    TON 100.00 600,170.00 108.00 648,183.60 125.00 750,212.50    
701-03-E storm drain pipe (12" plastic) 80      LNFT 45.00 3,600.00 300.00 24,000.00 50.00 4,000.00    
701-03-G storm drain pipe (18" rcp/pcp) 384      LNFT 85.00 32,640.00 280.00 107,520.00 75.00 28,800.00    
701-15 concrete collar 4      EACH 750.00 3,000.00 1,000.00 4,000.00 750.00 3,000.00    
702-03-A catch basins (cb-01) 4      EACH 3,500.00 14,000.00 4,000.00 16,000.00 2,200.00 8,800.00    
702-04-B adjusting catch basins 7      EACH 2,000.00 14,000.00 7,500.00 52,500.00 2,200.00 15,400.00    
707-01 concrete curb 75.4    LNFT 35.00 2,639.00 50.00 3,770.00 33.00 2,488.20    
713-01 temporary signs & barricades lump      LUMP 100,000.00 100,000.00 140,000.00 140,000.00 185,000.00 185,000.00    
726-01 bedding material 118.8    CUYD 25.00 2,970.00 98.00 11,642.40 100.00 11,880.00    
727-01 mobilization lump      LUMP 112,000.00 112,000.00 140,000.00 140,000.00 141,000.00 141,000.00    
731-02 reflectorized raised pavement markers 1,701      EACH 5.25 8,930.25 5.50 9,355.50 7.00 11,907.00    
732-01-C plastic pavement striping (8" width) 422      LNFT 0.90 379.80 1.00 422.00 3.00 1,266.00    
732-01-E plastic pavement striping (24" width) 2,123      LNFT 3.75 7,961.25 3.80 8,067.40 9.00 19,107.00    
732-02-A plastic pavement striping (solid line) (4" width) 2.117  MILE 2,650.00 5,610.05 2,700.00 5,715.90 6,200.00 13,125.40    
732-03-A plastic pavement striping (broken line)(4" width) 0.497  MILE 690.00 342.93 750.00 372.75 3,000.00 1,491.00    
732-04-A plastic pavement legends & symbols (arrow) 12      EACH 175.00 2,100.00 230.00 2,760.00 650.00 7,800.00    
732-05 removal of existing markings 2.165  MILE 5,900.00 12,773.50 6,500.00 14,072.50 5,000.00 10,825.00    
740-01 construction layout lump      LUMP 50,000.00 50,000.00 35,000.00 35,000.00 20,000.00 20,000.00    
S-001 sawcuts for concrete curb and shoulder removal 6,503.00   LNFT 7.40 48,122.20 5.50 35,766.50 7.00 45,521.00    
                       
 CONTRACTOR TOTAL       1,139,335.98   1,400,296.27   1,415,359.90    