| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - COASTAL BRIDGE CO., L.L.C. |
- 2 - KIEWIT LOUISIANA CO |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
10,000.00 |
10,000.00 |
250,000.00 |
250,000.00 |
|
|
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
500,000.00 |
500,000.00 |
1,651,922.23 |
1,651,922.23 |
|
|
|
|
| 202-02-C |
removal of portland cement concrete pavement
|
2,213   |
SQYD |
15.00 |
33,195.00 |
25.00 |
55,325.00 |
|
|
|
|
| 202-02-D |
removal of concrete walks & drives
|
282   |
SQYD |
15.00 |
4,230.00 |
20.00 |
5,640.00 |
|
|
|
|
| 203-01 |
general excavation
|
68   |
CUYD |
100.00 |
6,800.00 |
20.00 |
1,360.00 |
|
|
|
|
| 203-02 |
drainage excavation
|
1,750   |
CUYD |
15.00 |
26,250.00 |
35.00 |
61,250.00 |
|
|
|
|
| 203-04 |
embankment
|
2,778   |
CUYD |
60.00 |
166,680.00 |
85.00 |
236,130.00 |
|
|
|
|
| 203-05 |
excavation and embankment
|
lump |
LUMP |
25,000.00 |
25,000.00 |
100,000.00 |
100,000.00 |
|
|
|
|
| 204-01 |
temporary sandbagging
|
45.0 |
CUYD |
200.00 |
9,000.00 |
100.00 |
4,500.00 |
|
|
|
|
| 204-02 |
temporary hay or straw bales
|
34   |
EACH |
15.00 |
510.00 |
10.00 |
340.00 |
|
|
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
20   |
EACH |
300.00 |
6,000.00 |
100.00 |
2,000.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
1,660   |
LNFT |
5.00 |
8,300.00 |
4.00 |
6,640.00 |
|
|
|
|
| 302-01-A |
class ii base course(stone or recycled pcc)
|
537.0 |
CUYD |
100.00 |
53,700.00 |
130.00 |
69,810.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
1,025.4 |
TON |
200.00 |
205,080.00 |
187.00 |
191,749.80 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
32.1 |
TON |
200.00 |
6,420.00 |
187.00 |
6,002.70 |
|
|
|
|
| 704-01-C |
guard rail (double thrie beam)(3'-1 1/2" post spacing)
|
530.8 |
LNFT |
75.00 |
39,810.00 |
66.00 |
35,032.80 |
|
|
|
|
| 704-03 |
blocked out guard rail
|
100.0 |
LNFT |
30.00 |
3,000.00 |
22.00 |
2,200.00 |
|
|
|
|
| 704-11-A |
guard rail end treatment (flared)
|
8   |
EACH |
3,500.00 |
28,000.00 |
2,750.00 |
22,000.00 |
|
|
|
|
| 706-02-C |
concrete drive (6" thick)
|
68.9 |
SQYD |
100.00 |
6,890.00 |
300.00 |
20,670.00 |
|
|
|
|
| 711-01-D |
riprap (55 lb,18" thick)
|
566   |
SQYD |
100.00 |
56,600.00 |
100.00 |
56,600.00 |
|
|
|
|
| 711-04 |
geotextile fabric
|
566   |
SQYD |
2.00 |
1,132.00 |
3.00 |
1,698.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
75,000.00 |
75,000.00 |
150,000.00 |
150,000.00 |
|
|
|
|
| 716-01-A |
mulch (vegetative)
|
1.7 |
TON |
1,000.00 |
1,700.00 |
600.00 |
1,020.00 |
|
|
|
|
| 717-01 |
seeding
|
38   |
LB |
30.00 |
1,140.00 |
7.50 |
285.00 |
|
|
|
|
| 718-01 |
fertilizer
|
838   |
LB |
2.00 |
1,676.00 |
0.50 |
419.00 |
|
|
|
|
| 722-01 |
project site laboratory
|
1   |
EACH |
30,000.00 |
30,000.00 |
15,000.00 |
15,000.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
1,060,000.00 |
1,060,000.00 |
1,650,000.00 |
1,650,000.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
12   |
EACH |
100.00 |
1,200.00 |
83.00 |
996.00 |
|
|
|
|
| 730-09 |
electrical system
|
lump |
LUMP |
1,200,000.00 |
1,200,000.00 |
1,500,000.00 |
1,500,000.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
27   |
EACH |
70.00 |
1,890.00 |
55.00 |
1,485.00 |
|
|
|
|
| 732-01-A |
plastic pavement striping (4" width)
|
4,200   |
LNFT |
6.50 |
27,300.00 |
6.00 |
25,200.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
100,000.00 |
100,000.00 |
350,000.00 |
350,000.00 |
|
|
|
|
| 804-01-D-01 |
precast concrete piles (18")(hpc)
|
1,864   |
LNFT |
120.00 |
223,680.00 |
325.00 |
605,800.00 |
|
|
|
|
| 804-01-F-01 |
precast concrete piles (24")(hpc)
|
1,400   |
LNFT |
165.00 |
231,000.00 |
375.00 |
525,000.00 |
|
|
|
|
| 804-02-B |
treated timber piles (coastal treatment)
|
10,285   |
LNFT |
24.00 |
246,840.00 |
45.00 |
462,825.00 |
|
|
|
|
| 804-05 |
precast concrete test piles
|
1   |
EACH |
40,000.00 |
40,000.00 |
40,000.00 |
40,000.00 |
|
|
|
|
| 804-09 |
loading test piles
|
3   |
EACH |
10,000.00 |
30,000.00 |
60,000.00 |
180,000.00 |
|
|
|
|
| 804-10 |
reloading test piles
|
1   |
EACH |
100.00 |
100.00 |
15,000.00 |
15,000.00 |
|
|
|
|
| 804-11 |
redriving test piles
|
1   |
EACH |
100.00 |
100.00 |
10,000.00 |
10,000.00 |
|
|
|
|
| 804-12 |
loading permanent piles
|
1   |
EACH |
100.00 |
100.00 |
15,000.00 |
15,000.00 |
|
|
|
|
| 804-17 |
dynamic monitoring
|
15   |
EACH |
2,000.00 |
30,000.00 |
1,500.00 |
22,500.00 |
|
|
|
|
| 805-01-E-01 |
class a concrete (piers)(hpc)
|
417.57 |
CUYD |
870.00 |
363,285.90 |
1,000.00 |
417,570.00 |
|
|
|
|
| 805-01-F-01 |
class a concrete (bents)(hpc)
|
42.23 |
CUYD |
2,000.00 |
84,460.00 |
1,000.00 |
42,230.00 |
|
|
|
|
| 805-01-H-01 |
class a concrete (counterweights)(hpc)
|
53.12 |
CUYD |
1,600.00 |
84,992.00 |
1,000.00 |
53,120.00 |
|
|
|
|
| 805-01-I-01 |
class a concrete (pedestals and bases)(hpc)
|
23.12 |
CUYD |
1,750.00 |
40,460.00 |
1,000.00 |
23,120.00 |
|
|
|
|
| 805-03-01 |
class aa concrete(hpc)
|
266.43 |
CUYD |
1,200.00 |
319,716.00 |
1,200.00 |
319,716.00 |
|
|
|
|
| 806-01 |
deformed reinforcing steel
|
149,559   |
LB |
1.00 |
149,559.00 |
1.75 |
261,728.25 |
|
|
|
|
| 807-08 |
structural metalwork
|
lump |
LUMP |
1,700,000.00 |
1,700,000.00 |
1,850,000.00 |
1,850,000.00 |
|
|
|
|
| 808-01 |
steel grid flooring
|
2,574.8 |
SQFT |
77.00 |
198,259.60 |
80.00 |
205,984.00 |
|
|
|
|
| 809-01 |
movable bridge machinery
|
lump |
LUMP |
1,500,000.00 |
1,500,000.00 |
2,211,438.00 |
2,211,438.00 |
|
|
|
|
| 809-03 |
operating house
|
lump |
LUMP |
470,000.00 |
470,000.00 |
950,000.00 |
950,000.00 |
|
|
|
|
| 810-01-01 |
concrete railing (transition barrier)(hpc)
|
80.00 |
LNFT |
150.00 |
12,000.00 |
250.00 |
20,000.00 |
|
|
|
|
| 810-02 |
steel railing
|
304.00 |
LNFT |
165.00 |
50,160.00 |
100.00 |
30,400.00 |
|
|
|
|
| 810-04-01 |
steel & concrete railing (hpc)
|
159.34 |
LNFT |
325.00 |
51,785.50 |
500.00 |
79,670.00 |
|
|
|
|
| 812-01-B |
treated timber (coastal treatment)
|
42.25 |
MFBM |
7,400.00 |
312,650.00 |
5,000.00 |
211,250.00 |
|
|
|
|
| 813-01-01 |
concrete approach slabs (hpc)
|
207.04 |
SQYD |
300.00 |
62,112.00 |
1,000.00 |
207,040.00 |
|
|
|
|
| S-101 |
dynamic analysis
|
15   |
EACH |
2,000.00 |
30,000.00 |
3,000.00 |
45,000.00 |
|
|
|
|
| S-102 |
vibration monitoring
|
lump |
lump |
75,000.00 |
75,000.00 |
12,000.00 |
12,000.00 |
|
|
|
|
| | SUBTOTAL GENERAL |
|
|
|
10,002,763.00 |
|
15,291,666.78 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| ALTERNATE A |
bridge piling
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| ALTERNATE A1 |
precast concrete piles
|
|
|
|
|
|
|
|
|
|
|
| 804-01-F-01-A |
precast concrete piles (24")(hpc)
|
4,856   |
LNFT |
175.00 |
849,800.00 |
375.00 |
1,821,000.00 |
|
|
|
|
| 804-05-01 |
precast concrete test piles
|
2   |
EACH |
40,000.00 |
80,000.00 |
40,000.00 |
80,000.00 |
|
|
|
|
| | SUBTOTAL ALT A1 |
|
|
|
929,800.00 |
|
1,901,000.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| ALTERNATE A2 |
steel piles
|
|
|
|
|
|
|
|
|
|
|
| 804-03 |
steel piles (30" diameter, 5/8" minimum wall thickness)
|
4,930   |
LNFT |
0.00 |
0.00 |
0.00 |
0.00 |
|
|
|
|
| 804-07 |
steel test piles
|
2   |
EACH |
0.00 |
0.00 |
0.00 |
0.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
10,932,563.00 |
|
17,192,666.78 |
|
|
|
|
|