| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - C.E.C., INC. |
- 2 - F. MILLER CONSTRUCTION LLC |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-I |
removal of piles
|
750   |
LNFT |
9.60 |
7,200.00 |
25.00 |
18,750.00 |
|
|
|
|
| 203-07 |
borrow (vehicular measurement)
|
220   |
CUYD |
26.50 |
5,830.00 |
36.00 |
7,920.00 |
|
|
|
|
| 701-05-K-01 |
side drain pipe (30")(rcp)
|
344   |
LNFT |
120.00 |
41,280.00 |
100.00 |
34,400.00 |
|
|
|
|
| 701-08 |
relaying pipe
|
32   |
LNFT |
175.00 |
5,600.00 |
75.00 |
2,400.00 |
|
|
|
|
| 704-01-A |
guard rail (single thrie beam)(3'-1 1/2" post spacing)
|
100.0 |
LNFT |
60.50 |
6,050.00 |
45.00 |
4,500.00 |
|
|
|
|
| 704-01-B |
guard rail (single thrie beam)(6'-3" post spacing)
|
78.0 |
LNFT |
55.00 |
4,290.00 |
97.00 |
7,566.00 |
|
|
|
|
| 704-09 |
guard rail anchor sections (turndown)
|
100.0 |
LNFT |
48.00 |
4,800.00 |
39.00 |
3,900.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
9,600.00 |
9,600.00 |
14,000.00 |
14,000.00 |
|
|
|
|
| 725-04 |
low profile runaround
|
1   |
EACH |
77,500.00 |
77,500.00 |
150,000.00 |
150,000.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
16,250.00 |
16,250.00 |
45,000.00 |
45,000.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
8   |
EACH |
80.00 |
640.00 |
100.00 |
800.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
2,000.00 |
2,000.00 |
2,200.00 |
2,200.00 |
|
|
|
|
| 804-01-B-01 |
precast concrete piles (9 - 14" x 50')
|
450   |
LNFT |
81.00 |
36,450.00 |
87.70 |
39,465.00 |
|
|
|
|
| 804-02-A-01 |
treated timber piles (noncoastal treatment)(16 @ 30')
|
480   |
LNFT |
37.00 |
17,760.00 |
53.00 |
25,440.00 |
|
|
|
|
| 804-12 |
loading permanent piles
|
1   |
EACH |
20,375.00 |
20,375.00 |
100.00 |
100.00 |
|
|
|
|
| 812-01-A |
treated timber (land and fresh water)
|
2.52 |
MFBM |
5,700.00 |
14,364.00 |
8,000.00 |
20,160.00 |
|
|
|
|
| S-101 |
concrete approach slabs (w/out asphalt)
|
2   |
EACH |
16,220.00 |
32,440.00 |
16,000.00 |
32,000.00 |
|
|
|
|
| S-102 |
remove & reinstall span
|
2   |
EACH |
47,600.00 |
95,200.00 |
15,800.00 |
31,600.00 |
|
|
|
|
| S-103 |
concrete bents (pss-90-24-20sl)(w/out wingwalls)
|
3   |
each |
11,700.00 |
35,100.00 |
7,500.00 |
22,500.00 |
|
|
|
|
| S-104 |
tie rods
|
4   |
each |
600.00 |
2,400.00 |
550.00 |
2,200.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
435,129.00 |
|
464,901.00 |
|
|
|
|
|