Lead Project: 020-02-0033
Parish: TENSAS
Routes: US 65
Description: LA 568 NORTH - LA 128 NORTH
Type Const: grading, superpave asphaltic concrete pavement, cold planing asphaltic concrete,
pavement patching, and related work.
Estimated Construction Cost: $4,258,741.44
 
RankLicenseBidderConstruction Bid
1 05789 D & J CONSTRUCTION CO., INC. $3,848,118.70
2 12487 DIAMOND B CONSTRUCTION CO., L.L.C. $4,048,049.55
3 12312 GILCHRIST CONSTRUCTION CO. LLC $4,080,381.65
 
Item Number Item Description Quantity Unit of Measure - 1 -
D & J CONSTRUCTION CO., INC.
- 2 -
DIAMOND B CONSTRUCTION CO., L.L.C.
- 3 -
GILCHRIST CONSTRUCTION CO. LLC

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-01 removal of structures & obstructions lump      LUMP 3,000.00 3,000.00 37,000.00 37,000.00 170,000.00 170,000.00    
202-02-D removal of concrete walks & drives 86      SQYD 22.00 1,892.00 22.00 1,892.00 16.00 1,376.00    
202-02-G removal of surfacing & stabilized base 4,727.8    SQYD 7.00 33,094.60 8.00 37,822.40 12.00 56,733.60    
203-07 borrow (vehicular measurement) 1,145      CUYD 30.00 34,350.00 25.00 28,625.00 20.00 22,900.00    
401-02 aggregate surface course (adjusted vehicular
measurement)
58      CUYD 35.00 2,030.00 110.00 6,380.00 70.00 4,060.00    
502-01 superpave asphaltic concrete 19,486.5    TON 93.00 1,812,244.50 94.00 1,831,731.00 91.00 1,773,271.50    
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
24.8    TON 193.00 4,786.40 175.00 4,340.00 220.00 5,456.00    
507-01-A asphaltic material (crs-2p emulsion) 32,001      GAL 3.00 96,003.00 2.50 80,002.50 3.00 96,003.00    
507-02-B aggregate (s2) 78,050      SQYD 1.00 78,050.00 1.50 117,075.00 1.10 85,855.00    
509-01 cold planing asphaltic pavement 103,117      SQYD 2.50 257,792.50 3.15 324,818.55 2.00 206,234.00    
509-02 contractor retained reclaimed asphaltic pavement - 1,740      CUYD 0.01 - 17.40 0.10 - 174.00 0.01 - 17.40    
510-01-B pavement patching (12" minimum thickness) 787      SQYD 150.00 118,050.00 120.00 94,440.00 145.00 114,115.00    
602-02-A cleaning and resealing existing longitudinal pavement
joints
59,286      LNFT 1.80 106,714.80 1.75 103,750.50 1.60 94,857.60    
602-02-B cleaning and resealing existing transverse pavement
joints
21,780      LNFT 2.40 52,272.00 2.00 43,560.00 2.00 43,560.00    
602-03 cleaning and sealing cracks 1,500      LNFT 4.00 6,000.00 3.00 4,500.00 3.00 4,500.00    
602-05-G full depth patching of jointed concrete pavement (8"
thick)
1,518.0    SQYD 185.00 280,830.00 175.00 265,650.00 190.00 288,420.00    
701-10-I reinforced concrete pipe (extension)(24") 16      LNFT 250.00 4,000.00 185.00 2,960.00 250.00 4,000.00    
701-15 concrete collar 2      EACH 1,500.00 3,000.00 1,000.00 2,000.00 900.00 1,800.00    
706-02-C concrete drive (6" thick) 35.6    SQYD 75.00 2,670.00 75.00 2,670.00 60.00 2,136.00    
713-01 temporary signs & barricades lump      LUMP 200,000.00 200,000.00 200,000.00 200,000.00 250,000.00 250,000.00    
713-03-A temporary pavement markings (broken line)(4" width)(4'
length)
12.406  MILE 225.00 2,791.35 150.00 1,860.90 400.00 4,962.40    
713-03-B temporary pavement markings (broken line)(4" width)
(10' length)
11.786  MILE 200.00 2,357.20 325.00 3,830.45 600.00 7,071.60    
713-04-A temporary pavement markings (solid line)(4" width) 29.164  MILE 250.00 7,291.00 550.00 16,040.20 900.00 26,247.60    
713-05-A temporary pavement legends and symbols (arrow) 4      EACH 175.00 700.00 52.00 208.00 65.00 260.00    
716-01-A mulch (vegetative) 3.7    TON 500.00 1,850.00 375.00 1,387.50 450.00 1,665.00    
717-01 seeding 83      LB 10.00 830.00 8.00 664.00 9.00 747.00    
718-01 fertilizer 1,840      LB 0.50 920.00 0.45 828.00 0.50 920.00    
726-01 bedding material 7.2    CUYD 100.00 720.00 95.00 684.00 100.00 720.00    
727-01 mobilization lump      LUMP 275,000.00 275,000.00 400,000.00 400,000.00 400,000.00 400,000.00    
729-16-C object marker assembly (type 3) 2      EACH 95.00 190.00 100.00 200.00 85.00 170.00    
731-02 reflectorized raised pavement markers 1,319      EACH 7.00 9,233.00 5.00 6,595.00 5.50 7,254.50    
732-02-A plastic pavement striping (solid line) (4" width) 21.864  MILE 3,500.00 76,524.00 2,500.00 54,660.00 2,800.00 61,219.20    
732-03-A plastic pavement striping (broken line)(4" width) 9.603  MILE 2,000.00 19,206.00 750.00 7,202.25 850.00 8,162.55    
732-04-A plastic pavement legends & symbols (arrow) 2      EACH 600.00 1,200.00 150.00 300.00 200.00 400.00    
S-001 milling concrete pavement 1,586      SQYD 20.00 31,720.00 18.00 28,548.00 5.50 8,723.00    
S-002 breaking and seating pavement 22,643      SQYD 1.75 39,625.25 1.35 30,568.05 1.80 40,757.40    
S-003 rumble strips (ground-in) 10.8    MILE 1,100.00 11,880.00 900.00 9,720.00 800.00 8,640.00    
S-004 stone shoulder drains 78      EACH 500.00 39,000.00 920.00 71,760.00 500.00 39,000.00    
S-005 sawcuts for pavement patching 1,660      LNFT 6.00 9,960.00 4.50 7,470.00 8.50 14,110.00    
S-006 saw cutting driveways (6" deep) 36      LNFT 9.00 324.00 11.00 396.00 17.50 630.00    
S-922 sawing and sealing longitudinal joints in asphaltic
concrete overlay
68,532      LNFT 1.25 85,665.00 1.25 85,665.00 1.30 89,091.60    
S-923 sawing and sealing transverse joints in asphaltic
concrete overlay
26,335      LNFT 1.50 39,502.50 1.35 35,552.25 1.50 39,502.50    
S-927 sawcuts in asphaltic concrete lifts 94,867      LNFT 1.00 94,867.00 1.00 94,867.00 1.00 94,867.00    
                       
 CONTRACTOR TOTAL       3,848,118.70   4,048,049.55   4,080,381.65    