| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - R. E. HEIDT CONSTRUCTION CO., INC. |
- 2 - PRAIRIE CONTRACTORS INC. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
514   |
CUYD |
93.00 |
47,802.00 |
120.00 |
61,680.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
12,824.0 |
TON |
77.00 |
987,448.00 |
79.00 |
1,013,096.00 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
2,173.1 |
TON |
88.00 |
191,232.80 |
110.00 |
239,041.00 |
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
58,398   |
SQYD |
0.75 |
43,798.50 |
2.10 |
122,635.80 |
|
|
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
2,920   |
SQYD |
55.00 |
160,600.00 |
82.50 |
240,900.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
9,240.00 |
9,240.00 |
35,000.00 |
35,000.00 |
|
|
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
7.989 |
MILE |
561.53 |
4,486.06 |
400.00 |
3,195.60 |
|
|
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
7.989 |
MILE |
315.00 |
2,516.54 |
0.01 |
0.08 |
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
10.043 |
MILE |
630.00 |
6,327.09 |
0.01 |
0.10 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
32,175.00 |
32,175.00 |
35,000.00 |
35,000.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
555   |
EACH |
4.73 |
2,625.15 |
6.00 |
3,330.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
10.043 |
MILE |
2,415.00 |
24,253.85 |
2,500.00 |
25,107.50 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
3.994 |
MILE |
735.00 |
2,935.59 |
1,000.00 |
3,994.00 |
|
|
|
|
| 735-01 |
mailboxes
|
105   |
EACH |
1.05 |
110.25 |
1.00 |
105.00 |
|
|
|
|
| 735-02 |
mailbox supports (single)
|
105   |
EACH |
122.85 |
12,899.25 |
150.00 |
15,750.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
12,700.00 |
12,700.00 |
10,000.00 |
10,000.00 |
|
|
|
|
| S-001 |
hot mix asphalted treated aggregate surface course
(hot rap) |
3,245.0 |
TON |
62.00 |
201,190.00 |
73.00 |
236,885.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,742,340.08 |
|
2,045,720.08 |
|
|
|
|
|