| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BARRIERE CONSTRUCTION CO., LLC |
- 2 - HUEY STOCKSTILL, INC. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-H |
removal of guard rail
|
464   |
LNFT |
4.00 |
1,856.00 |
8.00 |
3,712.00 |
|
|
|
|
| 203-07 |
borrow (vehicular measurement)
|
605   |
CUYD |
5.00 |
3,025.00 |
16.00 |
9,680.00 |
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
1,028   |
CUYD |
80.00 |
82,240.00 |
83.00 |
85,324.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
14,913.1 |
TON |
65.00 |
969,351.50 |
72.00 |
1,073,743.20 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
805.9 |
TON |
65.00 |
52,383.50 |
150.00 |
120,885.00 |
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
79,060   |
SQYD |
1.00 |
79,060.00 |
2.35 |
185,791.00 |
|
|
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 3,294   |
CUYD |
1.00 |
- 3,294.00 |
10.00 |
- 32,940.00 |
|
|
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
500   |
SQYD |
70.00 |
35,000.00 |
110.00 |
55,000.00 |
|
|
|
|
| 510-02 |
pavement widening
|
532.2 |
SQYD |
40.00 |
21,288.00 |
60.00 |
31,932.00 |
|
|
|
|
| 704-01-A |
guard rail (single thrie beam)(3'-1 1/2" post spacing)
|
37.5 |
LNFT |
60.00 |
2,250.00 |
60.00 |
2,250.00 |
|
|
|
|
| 704-01-B |
guard rail (single thrie beam)(6'-3" post spacing)
|
256.0 |
LNFT |
50.00 |
12,800.00 |
50.00 |
12,800.00 |
|
|
|
|
| 704-03 |
blocked out guard rail
|
37.5 |
LNFT |
22.00 |
825.00 |
22.00 |
825.00 |
|
|
|
|
| 704-05 |
guard rail anchor sections (bct)
|
12.5 |
LNFT |
85.00 |
1,062.50 |
85.00 |
1,062.50 |
|
|
|
|
| 704-11-A |
guard rail end treatment (flared)
|
3   |
EACH |
2,500.00 |
7,500.00 |
2,400.00 |
7,200.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
80,000.00 |
80,000.00 |
10,000.00 |
10,000.00 |
|
|
|
|
| 713-02-A |
temporary pavement markings (4" width)
|
1,050   |
LNFT |
0.10 |
105.00 |
0.15 |
157.50 |
|
|
|
|
| 713-02-C |
temporary pavement markings (8" width)
|
150   |
LNFT |
0.10 |
15.00 |
0.30 |
45.00 |
|
|
|
|
| 713-02-E |
temporary pavement markings (24" width)
|
215   |
LNFT |
1.00 |
215.00 |
1.00 |
215.00 |
|
|
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
5.280 |
MILE |
150.00 |
792.00 |
600.00 |
3,168.00 |
|
|
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
4.210 |
MILE |
100.00 |
421.00 |
600.00 |
2,526.00 |
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
4.030 |
MILE |
600.00 |
2,418.00 |
1,800.00 |
7,254.00 |
|
|
|
|
| 713-05-A |
temporary pavement legends and symbols (arrow)
|
1   |
EACH |
20.00 |
20.00 |
50.00 |
50.00 |
|
|
|
|
| 713-05-C |
temporary pavement legends and symbols (only)
|
1   |
EACH |
20.00 |
20.00 |
50.00 |
50.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
150,000.00 |
150,000.00 |
106,000.00 |
106,000.00 |
|
|
|
|
| 729-16-B |
object marker assembly (type 2)
|
72   |
EACH |
20.00 |
1,440.00 |
55.00 |
3,960.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
4   |
EACH |
80.00 |
320.00 |
90.00 |
360.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
727   |
EACH |
6.00 |
4,362.00 |
5.50 |
3,998.50 |
|
|
|
|
| 732-01-A |
plastic pavement striping (4" width)
|
1,050   |
LNFT |
0.50 |
525.00 |
0.50 |
525.00 |
|
|
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
150   |
LNFT |
1.00 |
150.00 |
1.00 |
150.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
215   |
LNFT |
4.00 |
860.00 |
4.50 |
967.50 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
4.030 |
MILE |
6,000.00 |
24,180.00 |
5,000.00 |
20,150.00 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
4.210 |
MILE |
1,000.00 |
4,210.00 |
800.00 |
3,368.00 |
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
1   |
EACH |
200.00 |
200.00 |
180.00 |
180.00 |
|
|
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
1   |
EACH |
250.00 |
250.00 |
200.00 |
200.00 |
|
|
|
|
| 735-01 |
mailboxes
|
112   |
EACH |
1.00 |
112.00 |
5.00 |
560.00 |
|
|
|
|
| 735-02 |
mailbox supports (single)
|
105   |
EACH |
100.00 |
10,500.00 |
150.00 |
15,750.00 |
|
|
|
|
| 735-03 |
mailbox supports (double)
|
5   |
EACH |
175.00 |
875.00 |
180.00 |
900.00 |
|
|
|
|
| 735-04 |
mailbox supports (multiple)
|
2   |
EACH |
300.00 |
600.00 |
340.00 |
680.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
15,000.00 |
15,000.00 |
4,000.00 |
4,000.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,562,937.50 |
|
1,742,479.20 |
|
|
|
|
|