| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - MADDEN CONTRACTING CO., INC. |
|
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 203-07 |
borrow (vehicular measurement)
|
7,000   |
CUYD |
10.30 |
72,100.00 |
|
|
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
250   |
CUYD |
40.00 |
10,000.00 |
|
|
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
23,255.2 |
TON |
72.75 |
1,691,815.80 |
|
|
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
400.0 |
TON |
40.00 |
16,000.00 |
|
|
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
85,372   |
SQYD |
1.40 |
119,520.80 |
|
|
|
|
|
|
| 510-01-C |
pavement patching (10" minimum thickness)
|
1,100   |
SQYD |
56.25 |
61,875.00 |
|
|
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
72,000.00 |
72,000.00 |
|
|
|
|
|
|
| 713-02-E |
temporary pavement markings (24" width)
|
24   |
LNFT |
0.10 |
2.40 |
|
|
|
|
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
13.127 |
MILE |
325.00 |
4,266.28 |
|
|
|
|
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
7.870 |
MILE |
1.00 |
7.87 |
|
|
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
42.904 |
MILE |
1.00 |
42.90 |
|
|
|
|
|
|
| 713-05-D |
temporary pavement legends and symbols (rr crossing)
|
2   |
EACH |
1.00 |
2.00 |
|
|
|
|
|
|
| 716-01-A |
mulch (vegetative)
|
28.0 |
TON |
600.00 |
16,800.00 |
|
|
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
72,000.00 |
72,000.00 |
|
|
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
870   |
EACH |
4.50 |
3,915.00 |
|
|
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
24   |
LNFT |
3.00 |
72.00 |
|
|
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
21.452 |
MILE |
2,300.00 |
49,339.60 |
|
|
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
3.935 |
MILE |
700.00 |
2,754.50 |
|
|
|
|
|
|
| 732-04-D |
plastic pavement legends & symbols (rr crossing)
|
2   |
EACH |
400.00 |
800.00 |
|
|
|
|
|
|
| 735-01 |
mailboxes
|
9   |
EACH |
1.00 |
9.00 |
|
|
|
|
|
|
| 735-02 |
mailbox supports (single)
|
7   |
EACH |
150.00 |
1,050.00 |
|
|
|
|
|
|
| 735-03 |
mailbox supports (double)
|
1   |
EACH |
200.00 |
200.00 |
|
|
|
|
|
|
| 739-01 |
hydro-seeding
|
16.00 |
ACRE |
1,200.00 |
19,200.00 |
|
|
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
22,750.00 |
22,750.00 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
2,236,523.15 |
|
|
|
|
|
|
|