Letting of 8/29/2007 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 742-36-0109
Parish: ORLEANS
Routes:
Description: ROBERT E. LEE BLVD.(WICKFIELD DR. TO ELYSIAN FIELDS AVE.)
Type Const: grading, drainage structures, class ii base course, portland cement concrete pavement,
superpave asphaltic concrete pavement, water distribution system, and related work.
Estimated Construction Cost: $6,597,432.60
Maximum Number of Days Allowed for Construction: 480
Calculated Daily User Cost: $1,000.00
 
RankLicenseBidderConstruction Bid Bidder's Proposed
Contract Time
Total Bid
1 06276 BARRIERE CONSTRUCTION CO., LLC. $7,289,451.90 385 $7,674,451.90
2 02179 BOH BROS. CONSTRUCTION CO., LLC. $7,322,076.80 450 $7,772,076.80
3 24901 HARD ROCK CONSTRUCTION CO. $7,452,294.80 380 $7,832,294.80
4 01033 WALLACE C. DRENNAN, INC. $7,787,950.50 440 $8,227,950.50
5 34567 JAMES CONSTRUCTION GROUP LLC $8,403,589.80 480 $8,883,589.80
6 36961 CYCLE CONSTRUCTION CO. L.L.C. $9,940,053.34 450 $10,390,053.34
 
Item Number Item Description Quantity Unit of Measure - 1 -
BARRIERE CONSTRUCTION CO., LLC.
- 2 -
BOH BROS. CONSTRUCTION CO., LLC.
- 3 -
HARD ROCK CONSTRUCTION CO.
- 4 -
WALLACE C. DRENNAN, INC.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 10,000.00 10,000.00 12,000.00 12,000.00 100,000.00 100,000.00 100,000.00 100,000.00
202-01 removal of structures & obstructions lump      LUMP 100,000.00 100,000.00 172,000.00 172,000.00 100,000.00 100,000.00 66,000.00 66,000.00
202-02-C removal of portland cement concrete pavement 18,297      SQYD 10.00 182,970.00 9.00 164,673.00 11.00 201,267.00 5.00 91,485.00
202-02-D removal of concrete walks & drives 4,037      SQYD 14.00 56,518.00 9.00 36,333.00 13.00 52,481.00 10.00 40,370.00
202-02-F removal of concrete combination curb & gutter 1,027.0    LNFT 5.00 5,135.00 5.00 5,135.00 10.00 10,270.00 1.00 1,027.00
202-02-I removal of asphaltic concrete pavement 3,070      SQYD 9.00 27,630.00 4.00 12,280.00 10.00 30,700.00 1.00 3,070.00
203-05 nonplastic embankment 9,817      CUYD 28.00 274,876.00 26.00 255,242.00 40.00 392,680.00 15.00 147,255.00
203-06 excavation & embankment lump      LUMP 175,000.00 175,000.00 180,000.00 180,000.00 300,000.00 300,000.00 444,000.00 444,000.00
204-06 temporary silt fencing 12,200      LNFT 2.00 24,400.00 2.00 24,400.00 2.00 24,400.00 1.00 12,200.00
302-02-E-01 class ii base course (8" thick)(stone or recycled pccp) 25,640.8    SQYD 18.00 461,534.40 17.00 435,893.60 15.00 384,612.00 20.00 512,816.00
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
477.3    TON 130.00 62,049.00 230.00 109,779.00 100.00 47,730.00 150.00 71,595.00
601-01-I portland cement concrete pavement (9" thick) 22,585.5    SQYD 56.00 1,264,788.00 65.00 1,468,057.50 60.00 1,355,130.00 60.00 1,355,130.00
601-02-G portland cement concrete pavement (8" thick)
(crossovers & turnouts)
282.0    SQYD 55.00 15,510.00 95.00 26,790.00 65.00 18,330.00 120.00 33,840.00
701-03-E storm drain pipe (12" rcp) 363      LNFT 150.00 54,450.00 85.00 30,855.00 185.00 67,155.00 110.00 39,930.00
701-03-F storm drain pipe (15" rcp) 1,086      LNFT 140.00 152,040.00 95.00 103,170.00 115.00 124,890.00 120.00 130,320.00
701-03-G storm drain pipe (18" rcp) 154      LNFT 170.00 26,180.00 110.00 16,940.00 130.00 20,020.00 150.00 23,100.00
701-03-I storm drain pipe (24" rcp) 481      LNFT 180.00 86,580.00 155.00 74,555.00 175.00 84,175.00 160.00 76,960.00
701-03-M storm drain pipe (36" rcp) 913      LNFT 240.00 219,120.00 235.00 214,555.00 240.00 219,120.00 280.00 255,640.00
701-03-O storm drain pipe (48" rcp) 1,506      LNFT 340.00 512,040.00 315.00 474,390.00 315.00 474,390.00 380.00 572,280.00
701-03-P storm drain pipe (54" rcp) 261      LNFT 400.00 104,400.00 365.00 95,265.00 385.00 100,485.00 400.00 104,400.00
701-03-Q storm drain pipe (60" rcp) 832      LNFT 450.00 374,400.00 410.00 341,120.00 445.00 370,240.00 500.00 416,000.00
701-04-A storm drain pipe arch (15" equiv. rcpa) 115      LNFT 100.00 11,500.00 100.00 11,500.00 100.00 11,500.00 180.00 20,700.00
701-04-B storm drain pipe arch (18" equiv. rcpa) 60      LNFT 170.00 10,200.00 120.00 7,200.00 150.00 9,000.00 190.00 11,400.00
701-04-D storm drain pipe arch (24" equiv. rcpa) 256      LNFT 200.00 51,200.00 140.00 35,840.00 145.00 37,120.00 200.00 51,200.00
701-04-F storm drain pipe arch (36" equiv. rcpa) 25      LNFT 350.00 8,750.00 380.00 9,500.00 385.00 9,625.00 500.00 12,500.00
701-09-A fabricating pipe fittings 15"x15"x12" 1      EACH 300.00 300.00 400.00 400.00 327.00 327.00 200.00 200.00
701-09-B fabricating pipe fittings 15"x15"x15" 1      EACH 300.00 300.00 500.00 500.00 327.00 327.00 200.00 200.00
701-09-C fabricating pipe fittings 18"x18"x12" 1      EACH 400.00 400.00 600.00 600.00 436.00 436.00 400.00 400.00
701-09-D fabricating pipe fittings 24"x24"x12" 2      EACH 600.00 1,200.00 800.00 1,600.00 654.00 1,308.00 600.00 1,200.00
701-09-E fabricating pipe fittings 36"x36"x12" 6      EACH 1,300.00 7,800.00 1,600.00 9,600.00 1,308.00 7,848.00 1,100.00 6,600.00
701-09-F fabricating pipe fittings 36"x36"x15" 1      EACH 1,300.00 1,300.00 1,700.00 1,700.00 1,308.00 1,308.00 1,100.00 1,100.00
701-09-G fabricating pipe fittings 48"x48"x12" 12      EACH 2,100.00 25,200.00 2,700.00 32,400.00 2,180.00 26,160.00 1,200.00 14,400.00
701-09-H fabricating pipe fittings 54"x54"x12" 2      EACH 2,300.00 4,600.00 3,000.00 6,000.00 2,398.00 4,796.00 1,400.00 2,800.00
701-09-I fabricating pipe fittings 60"x60"x12" 7      EACH 3,000.00 21,000.00 3,800.00 26,600.00 3,052.00 21,364.00 1,500.00 10,500.00
701-09-J fabricating pipe fittings 60"x60"x15" 2      EACH 3,000.00 6,000.00 4,000.00 8,000.00 3,052.00 6,104.00 1,500.00 3,000.00
702-04-A adjusting manholes 38      EACH 300.00 11,400.00 550.00 20,900.00 550.00 20,900.00 100.00 3,800.00
706-01-A concrete walk (4" thick) 2,483.0    SQYD 66.00 163,878.00 55.00 136,565.00 80.00 198,640.00 80.00 198,640.00
706-02-C concrete drive (6" thick) 504.1    SQYD 80.00 40,328.00 62.00 31,254.20 90.00 45,369.00 80.00 40,328.00
706-02-E concrete drive (8" thick) 243.4    SQYD 100.00 24,340.00 70.00 17,038.00 92.00 22,392.80 90.00 21,906.00
706-03-C incidental concrete paving (6" thick) 444.3    SQYD 140.00 62,202.00 60.00 26,658.00 100.00 44,430.00 80.00 35,544.00
707-01 concrete curb 12,124.0    LNFT 10.00 121,240.00 8.00 96,992.00 8.00 96,992.00 10.00 121,240.00
713-01 temporary signs & barricades lump      LUMP 120,000.00 120,000.00 150,000.00 150,000.00 100,000.00 100,000.00 88,000.00 88,000.00
714-01 slab sodding 2,272      SQYD 7.00 15,904.00 4.00 9,088.00 7.00 15,904.00 10.00 22,720.00
715-01 topsoil 1,790      CUYD 25.00 44,750.00 30.00 53,700.00 0.00 0.00 11.00 19,690.00
722-01 project site laboratory 1      EACH 40,000.00 40,000.00 10,000.00 10,000.00 25,000.00 25,000.00 10,000.00 10,000.00
724-01-B pavement patching (12" minimum thickness) 15      SQYD 265.00 3,975.00 500.00 7,500.00 200.00 3,000.00 200.00 3,000.00
726-01 bedding material 3,368.1    CUYD 60.00 202,086.00 70.00 235,767.00 55.00 185,245.50 40.00 134,724.00
727-01 mobilization lump      LUMP 655,000.00 655,000.00 650,000.00 650,000.00 750,000.00 750,000.00 333,000.00 333,000.00
729-01 sign (type a) 201.0    SQFT 22.00 4,422.00 25.00 5,025.00 22.00 4,422.00 225.00 45,225.00
729-21 u-channel post 39      EACH 100.00 3,900.00 100.00 3,900.00 90.00 3,510.00 30.00 1,170.00
731-02 reflectorized raised pavement markers 26      EACH 5.50 143.00 6.00 156.00 5.00 130.00 6.00 156.00
732-02-A plastic pavement striping (solid line) (4" width) 1.893  MILE 3,000.00 5,679.00 3,000.00 5,679.00 2,650.00 5,016.45 1,600.00 3,028.80
732-02-B plastic pavement striping (solid line) (6" width) 0.524  MILE 4,200.00 2,200.80 4,500.00 2,358.00 4,100.00 2,148.40 4,800.00 2,515.20
732-02-C plastic pavement striping (solid line) (8" width) 0.065  MILE 5,500.00 357.50 6,000.00 390.00 5,500.00 357.50 6,600.00 429.00
732-02-D plastic pavement striping (solid line) (12" width) 0.085  MILE 8,000.00 680.00 8,500.00 722.50 8,100.00 688.50 9,900.00 841.50
732-02-E plastic pavement striping (solid line) (24" width) 0.015  MILE 17,000.00 255.00 17,000.00 255.00 16,450.00 246.75 20,000.00 300.00
732-03-A plastic pavement striping (broken line)(4" width) 0.110  MILE 800.00 88.00 800.00 88.00 790.00 86.90 900.00 99.00
732-04-A plastic pavement legends & symbols (arrow) 4      EACH 230.00 920.00 240.00 960.00 225.00 900.00 260.00 1,040.00
732-04-C plastic pavement legends & symbols (only) 2      EACH 300.00 600.00 300.00 600.00 290.00 580.00 333.00 666.00
739-01 hydro-seeding 2.60   ACRE 1,200.00 3,120.00 2,000.00 5,200.00 1,150.00 2,990.00 1,500.00 3,900.00
740-01 construction layout lump      LUMP 100,000.00 100,000.00 100,000.00 100,000.00 150,000.00 150,000.00 133,000.00 133,000.00
744-01 traffic control management lump      LUMP 7,000.00 7,000.00 5,000.00 5,000.00 10,000.00 10,000.00 33,000.00 33,000.00
S-001 geogrid 25,642.0    SQYD 2.60 66,669.20 2.50 64,105.00 2.00 51,284.00 3.00 76,926.00
S-002 remove and replace tree with crepe myrtle 37      EACH 700.00 25,900.00 260.00 9,620.00 700.00 25,900.00 750.00 27,750.00
S-003 tree trimming and/or root pruning 32      EACH 450.00 14,400.00 550.00 17,600.00 400.00 12,800.00 100.00 3,200.00
S-004 remove and replace tree in kind 4      EACH 800.00 3,200.00 800.00 3,200.00 700.00 2,800.00 1,000.00 4,000.00
S-005 project sign 2      EACH 1,000.00 2,000.00 1,250.00 2,500.00 1,500.00 3,000.00 1,000.00 2,000.00
S-006 no. 1 standard drain manhole (s&wb of new orleans dwg.
d-870)
11      EACH 4,000.00 44,000.00 4,200.00 46,200.00 3,300.00 36,300.00 4,400.00 48,400.00
S-007 no. 3 standard drain manhole (s&wb of new orleans dwg.
d-870)
4      EACH 5,500.00 22,000.00 6,300.00 25,200.00 4,000.00 16,000.00 5,500.00 22,000.00
S-008 drain manhole for large pipes (s&wb of new orleans
dwg. d-3340)
11      EACH 8,500.00 93,500.00 9,100.00 100,100.00 5,000.00 55,000.00 20,000.00 220,000.00
S-009 special drain manhole 5      EACH 11,000.00 55,000.00 19,600.00 98,000.00 8,000.00 40,000.00 25,000.00 125,000.00
S-010 no. 1 standard catch basin (s&wb of new orleans dwg.
d-873)
53      EACH 3,500.00 185,500.00 3,500.00 185,500.00 3,000.00 159,000.00 4,300.00 227,900.00
S-011 double no. 1 catch basin (s&wb of new orleans dwg.
d-873-a)
6      EACH 6,500.00 39,000.00 6,800.00 40,800.00 4,000.00 24,000.00 7,000.00 42,000.00
S-012 single mountable catch basin (s&wb of new orleans dwg.
d-3431-a)
3      EACH 3,000.00 9,000.00 3,600.00 10,800.00 3,000.00 9,000.00 3,666.00 10,998.00
S-013 double mountable catch basin (s&wb of new orleans dwg.
d-3431-b)
1      EACH 5,000.00 5,000.00 6,600.00 6,600.00 3,000.00 3,000.00 4,888.00 4,888.00
S-014 24" x 30" clear opening standard drop inlet (s&wb of
new orleans dwg. d-3264)
8      EACH 3,500.00 28,000.00 3,300.00 26,400.00 2,000.00 16,000.00 3,300.00 26,400.00
S-015 new 6" water valve with valve box (r.d. wood double
disc gate valve per s&wb)
5      EACH 5,000.00 25,000.00 5,000.00 25,000.00 4,000.00 20,000.00 4,600.00 23,000.00
S-016 new 8" water valve and manhole(r.d. wood double disc
gate valve per s&wb)
7      EACH 8,000.00 56,000.00 8,900.00 62,300.00 7,000.00 49,000.00 8,800.00 61,600.00
S-017 new 12" water valve and manhole (r.d. wood double disc
gate valve per s&wb)
2      EACH 11,000.00 22,000.00 12,000.00 24,000.00 10,000.00 20,000.00 11,188.00 22,376.00
S-018 new manhole around existing water valve 1      EACH 2,100.00 2,100.00 4,000.00 4,000.00 3,000.00 3,000.00 10,000.00 10,000.00
S-019 fire hydrant (includes fire hydrant, lead, tee, lugs,
blocking, etc.)
5      EACH 2,200.00 11,000.00 3,800.00 19,000.00 3,000.00 15,000.00 4,600.00 23,000.00
S-020 relocate existing fire hydrant 1      EACH 4,500.00 4,500.00 3,000.00 3,000.00 3,000.00 3,000.00 2,600.00 2,600.00
S-021 replace 3/4" water house connection (from main to
meter)
3      EACH 1,500.00 4,500.00 600.00 1,800.00 600.00 1,800.00 2,500.00 7,500.00
S-022 replace 1" water house connection (from main to meter) 10      EACH 3,000.00 30,000.00 700.00 7,000.00 700.00 7,000.00 2,600.00 26,000.00
S-023 water service line (2" pvc from main to valve) 50      LNFT 35.00 1,750.00 50.00 2,500.00 40.00 2,000.00 33.00 1,650.00
S-024 6" water line offset 5      EACH 3,500.00 17,500.00 5,000.00 25,000.00 5,000.00 25,000.00 10,000.00 50,000.00
S-025 adj. water valve and/or meter box(complete to grade)
including removal of mu d/debris inside the water
meter or valve box
37      EACH 300.00 11,100.00 500.00 18,500.00 200.00 7,400.00 50.00 1,850.00
S-026 replace sewer house connection to back of curb 17      EACH 600.00 10,200.00 1,500.00 25,500.00 2,000.00 34,000.00 100.00 1,700.00
S-027 replace existing sewer house connection beyond back of
curb
85      LNFT 70.00 5,950.00 70.00 5,950.00 60.00 5,100.00 10.00 850.00
S-028 8" pvc drain house connection collector line 750      LNFT 20.00 15,000.00 40.00 30,000.00 15.00 11,250.00 10.00 7,500.00
S-029 replace drain house connection beyond back of curb 330      LNFT 30.00 9,900.00 30.00 9,900.00 25.00 8,250.00 10.00 3,300.00
S-030 exploratory excavation 7      EACH 1,600.00 11,200.00 1,200.00 8,400.00 900.00 6,300.00 1,000.00 7,000.00
S-031 saw cut existing concrete pavement (full depth)
including curb
340      LNFT 13.00 4,420.00 14.00 4,760.00 10.00 3,400.00 25.00 8,500.00
S-032 saw cut, wheel cut, or spade cut existing asphaltic
concrete pavement (full depth)
523      LNFT 11.00 5,753.00 14.00 7,322.00 10.00 5,230.00 15.00 7,845.00
S-033 relocate existing signal pedestal poles, including new
foundations, demo of existing foundations,
conduit & rewiring
3      EACH 4,000.00 12,000.00 3,200.00 9,600.00 3,000.00 9,000.00 3,500.00 10,500.00
S-034 relocate existing signal double mast arms, including
new foundations, demo of existing foundations,
conduit & rewiring
2      EACH 9,000.00 18,000.00 8,000.00 16,000.00 7,500.00 15,000.00 8,800.00 17,600.00
S-035 relocate existing traffic manhole, including new
foundation, conduit and rewiring
1      EACH 6,000.00 6,000.00 6,000.00 6,000.00 5,500.00 5,500.00 6,400.00 6,400.00
S-036 relocate existing signal service meter, including
conduit and rewiring
1      EACH 3,000.00 3,000.00 2,700.00 2,700.00 2,500.00 2,500.00 2,900.00 2,900.00
S-037 street name signs on new post or mast arm 22      EACH 250.00 5,500.00 270.00 5,940.00 250.00 5,500.00 200.00 4,400.00
S-038 hand formed and poured in place concrete curb within
the limits of the tree dripline
70      LNFT 25.00 1,750.00 50.00 3,500.00 20.00 1,400.00 50.00 3,500.00
S-039 gravel bed and filter cloth over tree roots 66      SQYD 25.00 1,650.00 30.00 1,980.00 7.00 462.00 1.00 66.00
S-040 install stainless steel trough through the top slab of
the st. anthony ave. box canal
lump      LUMP 30,000.00 30,000.00 28,000.00 28,000.00 10,000.00 10,000.00 66,000.00 66,000.00
S-041 type a catch basin adjustment 5      EACH 1,000.00 5,000.00 500.00 2,500.00 800.00 4,000.00 100.00 500.00
S-042 60" rcp drain line tie-in to existing concrete box
canal
2      EACH 20,000.00 40,000.00 14,500.00 29,000.00 30,000.00 60,000.00 88,000.00 176,000.00
S-043 48" rcp drain line tie-in to existing concrete box
canal
1      EACH 13,000.00 13,000.00 12,000.00 12,000.00 25,000.00 25,000.00 66,000.00 66,000.00
S-044 36" equiv. (43" x 26") sdpa drain line tie-in to
existing concrete box canal
1      EACH 16,000.00 16,000.00 8,500.00 8,500.00 25,000.00 25,000.00 44,000.00 44,000.00
S-045 water main -6" pvc with main line fittings 40.0    LNFT 95.00 3,800.00 75.00 3,000.00 70.00 2,800.00 130.00 5,200.00
S-046 water main -8" pvc with main line fittings 660.0    LNFT 95.00 62,700.00 78.00 51,480.00 60.00 39,600.00 160.00 105,600.00
S-047 water main -12" pvc with main line fittings 1,380.0    LNFT 75.00 103,500.00 88.00 121,440.00 60.00 82,800.00 100.00 138,000.00
S-048 water main 6" d.i. with main line fittings 50.0    LNFT 130.00 6,500.00 108.00 5,400.00 185.00 9,250.00 200.00 10,000.00
S-049 water main 8" d.i. with main line fittings 70.0    LNFT 130.00 9,100.00 118.00 8,260.00 115.00 8,050.00 210.00 14,700.00
S-050 water main 12" d.i. with main line fittings 20.0    LNFT 200.00 4,000.00 139.00 2,780.00 265.00 5,300.00 220.00 4,400.00
S-051 untreated timber foundations for bedding material 113.0    MFBM 700.00 79,100.00 400.00 45,200.00 900.00 101,700.00 500.00 56,500.00
S-052 geotextile fabric 53,171.0    SQYD 1.00 53,171.00 1.00 53,171.00 1.00 53,171.00 1.00 53,171.00
S-053 brick sidewalk or footlap 8.0    SQYD 100.00 800.00 550.00 4,400.00 150.00 1,200.00 400.00 3,200.00
                       
 ITEM TOTAL (CONSTRUCTION BID)       7,289,451.90   7,322,076.80   7,452,294.80   7,787,950.50
 NUMBER OF DAYS BID AT $1,000 PER DAY.       385,000.00   450,000.00   380,000.00   440,000.00
 TOTAL BID       7,674,451.90   7,772,076.80   7,832,294.80   8,227,950.50
 
Item Number Item Description Quantity Unit of Measure - 5 -
JAMES CONSTRUCTION GROUP LLC
- 6 -
CYCLE CONSTRUCTION CO. L.L.C.

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 45,000.00 45,000.00 50,000.00 50,000.00        
202-01 removal of structures & obstructions lump      LUMP 400,000.00 400,000.00 190,000.00 190,000.00        
202-02-C removal of portland cement concrete pavement 18,297      SQYD 18.00 329,346.00 11.00 201,267.00        
202-02-D removal of concrete walks & drives 4,037      SQYD 7.00 28,259.00 11.00 44,407.00        
202-02-F removal of concrete combination curb & gutter 1,027.0    LNFT 6.00 6,162.00 5.00 5,135.00        
202-02-I removal of asphaltic concrete pavement 3,070      SQYD 8.00 24,560.00 9.00 27,630.00        
203-05 nonplastic embankment 9,817      CUYD 35.00 343,595.00 27.00 265,059.00        
203-06 excavation & embankment lump      LUMP 105,000.00 105,000.00 250,000.00 250,000.00        
204-06 temporary silt fencing 12,200      LNFT 3.50 42,700.00 2.50 30,500.00        
302-02-E-01 class ii base course (8" thick)(stone or recycled pccp) 25,640.8    SQYD 24.00 615,379.20 24.00 615,379.20        
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
477.3    TON 130.00 62,049.00 150.00 71,595.00        
601-01-I portland cement concrete pavement (9" thick) 22,585.5    SQYD 75.00 1,693,912.50 70.00 1,580,985.00        
601-02-G portland cement concrete pavement (8" thick)
(crossovers & turnouts)
282.0    SQYD 115.00 32,430.00 95.00 26,790.00        
701-03-E storm drain pipe (12" rcp) 363      LNFT 69.00 25,047.00 160.00 58,080.00        
701-03-F storm drain pipe (15" rcp) 1,086      LNFT 72.00 78,192.00 170.00 184,620.00        
701-03-G storm drain pipe (18" rcp) 154      LNFT 78.00 12,012.00 220.00 33,880.00        
701-03-I storm drain pipe (24" rcp) 481      LNFT 105.00 50,505.00 230.00 110,630.00        
701-03-M storm drain pipe (36" rcp) 913      LNFT 175.00 159,775.00 290.00 264,770.00        
701-03-O storm drain pipe (48" rcp) 1,506      LNFT 240.00 361,440.00 360.00 542,160.00        
701-03-P storm drain pipe (54" rcp) 261      LNFT 300.00 78,300.00 400.00 104,400.00        
701-03-Q storm drain pipe (60" rcp) 832      LNFT 360.00 299,520.00 475.00 395,200.00        
701-04-A storm drain pipe arch (15" equiv. rcpa) 115      LNFT 90.00 10,350.00 220.00 25,300.00        
701-04-B storm drain pipe arch (18" equiv. rcpa) 60      LNFT 105.00 6,300.00 240.00 14,400.00        
701-04-D storm drain pipe arch (24" equiv. rcpa) 256      LNFT 135.00 34,560.00 250.00 64,000.00        
701-04-F storm drain pipe arch (36" equiv. rcpa) 25      LNFT 188.00 4,700.00 360.00 9,000.00        
701-09-A fabricating pipe fittings 15"x15"x12" 1      EACH 800.00 800.00 2,300.00 2,300.00        
701-09-B fabricating pipe fittings 15"x15"x15" 1      EACH 815.00 815.00 2,900.00 2,900.00        
701-09-C fabricating pipe fittings 18"x18"x12" 1      EACH 825.00 825.00 3,000.00 3,000.00        
701-09-D fabricating pipe fittings 24"x24"x12" 2      EACH 1,200.00 2,400.00 3,800.00 7,600.00        
701-09-E fabricating pipe fittings 36"x36"x12" 6      EACH 2,000.00 12,000.00 4,600.00 27,600.00        
701-09-F fabricating pipe fittings 36"x36"x15" 1      EACH 2,300.00 2,300.00 4,600.00 4,600.00        
701-09-G fabricating pipe fittings 48"x48"x12" 12      EACH 3,100.00 37,200.00 5,600.00 67,200.00        
701-09-H fabricating pipe fittings 54"x54"x12" 2      EACH 3,400.00 6,800.00 8,600.00 17,200.00        
701-09-I fabricating pipe fittings 60"x60"x12" 7      EACH 4,200.00 29,400.00 9,500.00 66,500.00        
701-09-J fabricating pipe fittings 60"x60"x15" 2      EACH 4,300.00 8,600.00 9,500.00 19,000.00        
702-04-A adjusting manholes 38      EACH 1,250.00 47,500.00 1,000.00 38,000.00        
706-01-A concrete walk (4" thick) 2,483.0    SQYD 60.00 148,980.00 67.00 166,361.00        
706-02-C concrete drive (6" thick) 504.1    SQYD 75.00 37,807.50 70.00 35,287.00        
706-02-E concrete drive (8" thick) 243.4    SQYD 85.00 20,689.00 75.00 18,255.00        
706-03-C incidental concrete paving (6" thick) 444.3    SQYD 100.00 44,430.00 50.00 22,215.00        
707-01 concrete curb 12,124.0    LNFT 10.00 121,240.00 12.00 145,488.00        
713-01 temporary signs & barricades lump      LUMP 90,000.00 90,000.00 200,000.00 200,000.00        
714-01 slab sodding 2,272      SQYD 7.50 17,040.00 5.00 11,360.00        
715-01 topsoil 1,790      CUYD 50.00 89,500.00 30.00 53,700.00        
722-01 project site laboratory 1      EACH 15,000.00 15,000.00 25,000.00 25,000.00        
724-01-B pavement patching (12" minimum thickness) 15      SQYD 1,000.00 15,000.00 300.00 4,500.00        
726-01 bedding material 3,368.1    CUYD 90.00 303,129.00 65.00 218,926.50        
727-01 mobilization lump      LUMP 820,000.00 820,000.00 500,000.00 500,000.00        
729-01 sign (type a) 201.0    SQFT 22.00 4,422.00 26.00 5,226.00        
729-21 u-channel post 39      EACH 90.00 3,510.00 100.00 3,900.00        
731-02 reflectorized raised pavement markers 26      EACH 5.20 135.20 6.00 156.00        
732-02-A plastic pavement striping (solid line) (4" width) 1.893  MILE 1,400.00 2,650.20 3,200.00 6,057.60        
732-02-B plastic pavement striping (solid line) (6" width) 0.524  MILE 4,200.00 2,200.80 5,000.00 2,620.00        
732-02-C plastic pavement striping (solid line) (8" width) 0.065  MILE 6,000.00 390.00 7,000.00 455.00        
732-02-D plastic pavement striping (solid line) (12" width) 0.085  MILE 8,600.00 731.00 10,000.00 850.00        
732-02-E plastic pavement striping (solid line) (24" width) 0.015  MILE 25,000.00 375.00 13,000.00 195.00        
732-03-A plastic pavement striping (broken line)(4" width) 0.110  MILE 790.00 86.90 900.00 99.00        
732-04-A plastic pavement legends & symbols (arrow) 4      EACH 225.00 900.00 300.00 1,200.00        
732-04-C plastic pavement legends & symbols (only) 2      EACH 290.00 580.00 300.00 600.00        
739-01 hydro-seeding 2.60   ACRE 1,150.00 2,990.00 1,700.00 4,420.00        
740-01 construction layout lump      LUMP 225,000.00 225,000.00 150,000.00 150,000.00        
744-01 traffic control management lump      LUMP 25,000.00 25,000.00 100,000.00 100,000.00        
S-001 geogrid 25,642.0    SQYD 4.00 102,568.00 3.00 76,926.00        
S-002 remove and replace tree with crepe myrtle 37      EACH 40.00 1,480.00 900.00 33,300.00        
S-003 tree trimming and/or root pruning 32      EACH 35.00 1,120.00 600.00 19,200.00        
S-004 remove and replace tree in kind 4      EACH 10.00 40.00 900.00 3,600.00        
S-005 project sign 2      EACH 1,500.00 3,000.00 1,000.00 2,000.00        
S-006 no. 1 standard drain manhole (s&wb of new orleans dwg.
d-870)
11      EACH 3,200.00 35,200.00 9,000.00 99,000.00        
S-007 no. 3 standard drain manhole (s&wb of new orleans dwg.
d-870)
4      EACH 4,800.00 19,200.00 11,000.00 44,000.00        
S-008 drain manhole for large pipes (s&wb of new orleans
dwg. d-3340)
11      EACH 6,500.00 71,500.00 30,000.00 330,000.00        
S-009 special drain manhole 5      EACH 6,000.00 30,000.00 40,000.00 200,000.00        
S-010 no. 1 standard catch basin (s&wb of new orleans dwg.
d-873)
53      EACH 2,850.00 151,050.00 9,500.00 503,500.00        
S-011 double no. 1 catch basin (s&wb of new orleans dwg.
d-873-a)
6      EACH 4,000.00 24,000.00 11,000.00 66,000.00        
S-012 single mountable catch basin (s&wb of new orleans dwg.
d-3431-a)
3      EACH 2,500.00 7,500.00 8,500.00 25,500.00        
S-013 double mountable catch basin (s&wb of new orleans dwg.
d-3431-b)
1      EACH 5,800.00 5,800.00 10,000.00 10,000.00        
S-014 24" x 30" clear opening standard drop inlet (s&wb of
new orleans dwg. d-3264)
8      EACH 3,000.00 24,000.00 8,500.00 68,000.00        
S-015 new 6" water valve with valve box (r.d. wood double
disc gate valve per s&wb)
5      EACH 4,500.00 22,500.00 6,000.00 30,000.00        
S-016 new 8" water valve and manhole(r.d. wood double disc
gate valve per s&wb)
7      EACH 5,200.00 36,400.00 16,500.00 115,500.00        
S-017 new 12" water valve and manhole (r.d. wood double disc
gate valve per s&wb)
2      EACH 9,000.00 18,000.00 19,500.00 39,000.00        
S-018 new manhole around existing water valve 1      EACH 61,000.00 61,000.00 12,500.00 12,500.00        
S-019 fire hydrant (includes fire hydrant, lead, tee, lugs,
blocking, etc.)
5      EACH 4,900.00 24,500.00 5,400.00 27,000.00        
S-020 relocate existing fire hydrant 1      EACH 2,200.00 2,200.00 4,600.00 4,600.00        
S-021 replace 3/4" water house connection (from main to
meter)
3      EACH 600.00 1,800.00 2,200.00 6,600.00        
S-022 replace 1" water house connection (from main to meter) 10      EACH 650.00 6,500.00 2,200.00 22,000.00        
S-023 water service line (2" pvc from main to valve) 50      LNFT 12.00 600.00 75.00 3,750.00        
S-024 6" water line offset 5      EACH 2,200.00 11,000.00 11,000.00 55,000.00        
S-025 adj. water valve and/or meter box(complete to grade)
including removal of mu d/debris inside the water
meter or valve box
37      EACH 600.00 22,200.00 500.00 18,500.00        
S-026 replace sewer house connection to back of curb 17      EACH 550.00 9,350.00 2,000.00 34,000.00        
S-027 replace existing sewer house connection beyond back of
curb
85      LNFT 30.00 2,550.00 200.00 17,000.00        
S-028 8" pvc drain house connection collector line 750      LNFT 30.00 22,500.00 150.00 112,500.00        
S-029 replace drain house connection beyond back of curb 330      LNFT 30.00 9,900.00 150.00 49,500.00        
S-030 exploratory excavation 7      EACH 1,500.00 10,500.00 2,000.00 14,000.00        
S-031 saw cut existing concrete pavement (full depth)
including curb
340      LNFT 6.00 2,040.00 14.00 4,760.00        
S-032 saw cut, wheel cut, or spade cut existing asphaltic
concrete pavement (full depth)
523      LNFT 8.00 4,184.00 7.00 3,661.00        
S-033 relocate existing signal pedestal poles, including new
foundations, demo of existing foundations,
conduit & rewiring
3      EACH 3,000.00 9,000.00 3,500.00 10,500.00        
S-034 relocate existing signal double mast arms, including
new foundations, demo of existing foundations,
conduit & rewiring
2      EACH 7,500.00 15,000.00 9,000.00 18,000.00        
S-035 relocate existing traffic manhole, including new
foundation, conduit and rewiring
1      EACH 5,500.00 5,500.00 6,500.00 6,500.00        
S-036 relocate existing signal service meter, including
conduit and rewiring
1      EACH 2,500.00 2,500.00 3,000.00 3,000.00        
S-037 street name signs on new post or mast arm 22      EACH 150.00 3,300.00 300.00 6,600.00        
S-038 hand formed and poured in place concrete curb within
the limits of the tree dripline
70      LNFT 500.00 35,000.00 15.00 1,050.00        
S-039 gravel bed and filter cloth over tree roots 66      SQYD 10.00 660.00 80.00 5,280.00        
S-040 install stainless steel trough through the top slab of
the st. anthony ave. box canal
lump      LUMP 20,000.00 20,000.00 32,000.00 32,000.00        
S-041 type a catch basin adjustment 5      EACH 4,500.00 22,500.00 5,000.00 25,000.00        
S-042 60" rcp drain line tie-in to existing concrete box
canal
2      EACH 4,250.00 8,500.00 22,000.00 44,000.00        
S-043 48" rcp drain line tie-in to existing concrete box
canal
1      EACH 3,200.00 3,200.00 12,000.00 12,000.00        
S-044 36" equiv. (43" x 26") sdpa drain line tie-in to
existing concrete box canal
1      EACH 1,800.00 1,800.00 12,000.00 12,000.00        
S-045 water main -6" pvc with main line fittings 40.0    LNFT 60.00 2,400.00 425.00 17,000.00        
S-046 water main -8" pvc with main line fittings 660.0    LNFT 65.00 42,900.00 160.00 105,600.00        
S-047 water main -12" pvc with main line fittings 1,380.0    LNFT 70.00 96,600.00 170.00 234,600.00        
S-048 water main 6" d.i. with main line fittings 50.0    LNFT 70.00 3,500.00 250.00 12,500.00        
S-049 water main 8" d.i. with main line fittings 70.0    LNFT 80.00 5,600.00 255.00 17,850.00        
S-050 water main 12" d.i. with main line fittings 20.0    LNFT 120.00 2,400.00 330.00 6,600.00        
S-051 untreated timber foundations for bedding material 113.0    MFBM 2,200.00 248,600.00 1,206.54 136,339.02        
S-052 geotextile fabric 53,171.0    SQYD 2.50 132,927.50 1.54 81,883.34        
S-053 brick sidewalk or footlap 8.0    SQYD 1,000.00 8,000.00 361.96 2,895.68        
                       
 ITEM TOTAL (CONSTRUCTION BID)       8,403,589.80   9,940,053.34        
 NUMBER OF DAYS BID AT $1,000 PER DAY.       480,000.00   450,000.00        
 TOTAL BID       8,883,589.80   10,390,053.34        