| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BARRIERE CONSTRUCTION CO., LLC. |
- 2 - BOH BROS. CONSTRUCTION CO., LLC. |
- 3 - HARD ROCK CONSTRUCTION CO. |
- 4 - WALLACE C. DRENNAN, INC. |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
10,000.00 |
10,000.00 |
12,000.00 |
12,000.00 |
100,000.00 |
100,000.00 |
100,000.00 |
100,000.00 |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
100,000.00 |
100,000.00 |
172,000.00 |
172,000.00 |
100,000.00 |
100,000.00 |
66,000.00 |
66,000.00 |
| 202-02-C |
removal of portland cement concrete pavement
|
18,297   |
SQYD |
10.00 |
182,970.00 |
9.00 |
164,673.00 |
11.00 |
201,267.00 |
5.00 |
91,485.00 |
| 202-02-D |
removal of concrete walks & drives
|
4,037   |
SQYD |
14.00 |
56,518.00 |
9.00 |
36,333.00 |
13.00 |
52,481.00 |
10.00 |
40,370.00 |
| 202-02-F |
removal of concrete combination curb & gutter
|
1,027.0 |
LNFT |
5.00 |
5,135.00 |
5.00 |
5,135.00 |
10.00 |
10,270.00 |
1.00 |
1,027.00 |
| 202-02-I |
removal of asphaltic concrete pavement
|
3,070   |
SQYD |
9.00 |
27,630.00 |
4.00 |
12,280.00 |
10.00 |
30,700.00 |
1.00 |
3,070.00 |
| 203-05 |
nonplastic embankment
|
9,817   |
CUYD |
28.00 |
274,876.00 |
26.00 |
255,242.00 |
40.00 |
392,680.00 |
15.00 |
147,255.00 |
| 203-06 |
excavation & embankment
|
lump |
LUMP |
175,000.00 |
175,000.00 |
180,000.00 |
180,000.00 |
300,000.00 |
300,000.00 |
444,000.00 |
444,000.00 |
| 204-06 |
temporary silt fencing
|
12,200   |
LNFT |
2.00 |
24,400.00 |
2.00 |
24,400.00 |
2.00 |
24,400.00 |
1.00 |
12,200.00 |
| 302-02-E-01 |
class ii base course (8" thick)(stone or recycled pccp)
|
25,640.8 |
SQYD |
18.00 |
461,534.40 |
17.00 |
435,893.60 |
15.00 |
384,612.00 |
20.00 |
512,816.00 |
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
477.3 |
TON |
130.00 |
62,049.00 |
230.00 |
109,779.00 |
100.00 |
47,730.00 |
150.00 |
71,595.00 |
| 601-01-I |
portland cement concrete pavement (9" thick)
|
22,585.5 |
SQYD |
56.00 |
1,264,788.00 |
65.00 |
1,468,057.50 |
60.00 |
1,355,130.00 |
60.00 |
1,355,130.00 |
| 601-02-G |
portland cement concrete pavement (8" thick)
(crossovers & turnouts) |
282.0 |
SQYD |
55.00 |
15,510.00 |
95.00 |
26,790.00 |
65.00 |
18,330.00 |
120.00 |
33,840.00 |
| 701-03-E |
storm drain pipe (12" rcp)
|
363   |
LNFT |
150.00 |
54,450.00 |
85.00 |
30,855.00 |
185.00 |
67,155.00 |
110.00 |
39,930.00 |
| 701-03-F |
storm drain pipe (15" rcp)
|
1,086   |
LNFT |
140.00 |
152,040.00 |
95.00 |
103,170.00 |
115.00 |
124,890.00 |
120.00 |
130,320.00 |
| 701-03-G |
storm drain pipe (18" rcp)
|
154   |
LNFT |
170.00 |
26,180.00 |
110.00 |
16,940.00 |
130.00 |
20,020.00 |
150.00 |
23,100.00 |
| 701-03-I |
storm drain pipe (24" rcp)
|
481   |
LNFT |
180.00 |
86,580.00 |
155.00 |
74,555.00 |
175.00 |
84,175.00 |
160.00 |
76,960.00 |
| 701-03-M |
storm drain pipe (36" rcp)
|
913   |
LNFT |
240.00 |
219,120.00 |
235.00 |
214,555.00 |
240.00 |
219,120.00 |
280.00 |
255,640.00 |
| 701-03-O |
storm drain pipe (48" rcp)
|
1,506   |
LNFT |
340.00 |
512,040.00 |
315.00 |
474,390.00 |
315.00 |
474,390.00 |
380.00 |
572,280.00 |
| 701-03-P |
storm drain pipe (54" rcp)
|
261   |
LNFT |
400.00 |
104,400.00 |
365.00 |
95,265.00 |
385.00 |
100,485.00 |
400.00 |
104,400.00 |
| 701-03-Q |
storm drain pipe (60" rcp)
|
832   |
LNFT |
450.00 |
374,400.00 |
410.00 |
341,120.00 |
445.00 |
370,240.00 |
500.00 |
416,000.00 |
| 701-04-A |
storm drain pipe arch (15" equiv. rcpa)
|
115   |
LNFT |
100.00 |
11,500.00 |
100.00 |
11,500.00 |
100.00 |
11,500.00 |
180.00 |
20,700.00 |
| 701-04-B |
storm drain pipe arch (18" equiv. rcpa)
|
60   |
LNFT |
170.00 |
10,200.00 |
120.00 |
7,200.00 |
150.00 |
9,000.00 |
190.00 |
11,400.00 |
| 701-04-D |
storm drain pipe arch (24" equiv. rcpa)
|
256   |
LNFT |
200.00 |
51,200.00 |
140.00 |
35,840.00 |
145.00 |
37,120.00 |
200.00 |
51,200.00 |
| 701-04-F |
storm drain pipe arch (36" equiv. rcpa)
|
25   |
LNFT |
350.00 |
8,750.00 |
380.00 |
9,500.00 |
385.00 |
9,625.00 |
500.00 |
12,500.00 |
| 701-09-A |
fabricating pipe fittings 15"x15"x12"
|
1   |
EACH |
300.00 |
300.00 |
400.00 |
400.00 |
327.00 |
327.00 |
200.00 |
200.00 |
| 701-09-B |
fabricating pipe fittings 15"x15"x15"
|
1   |
EACH |
300.00 |
300.00 |
500.00 |
500.00 |
327.00 |
327.00 |
200.00 |
200.00 |
| 701-09-C |
fabricating pipe fittings 18"x18"x12"
|
1   |
EACH |
400.00 |
400.00 |
600.00 |
600.00 |
436.00 |
436.00 |
400.00 |
400.00 |
| 701-09-D |
fabricating pipe fittings 24"x24"x12"
|
2   |
EACH |
600.00 |
1,200.00 |
800.00 |
1,600.00 |
654.00 |
1,308.00 |
600.00 |
1,200.00 |
| 701-09-E |
fabricating pipe fittings 36"x36"x12"
|
6   |
EACH |
1,300.00 |
7,800.00 |
1,600.00 |
9,600.00 |
1,308.00 |
7,848.00 |
1,100.00 |
6,600.00 |
| 701-09-F |
fabricating pipe fittings 36"x36"x15"
|
1   |
EACH |
1,300.00 |
1,300.00 |
1,700.00 |
1,700.00 |
1,308.00 |
1,308.00 |
1,100.00 |
1,100.00 |
| 701-09-G |
fabricating pipe fittings 48"x48"x12"
|
12   |
EACH |
2,100.00 |
25,200.00 |
2,700.00 |
32,400.00 |
2,180.00 |
26,160.00 |
1,200.00 |
14,400.00 |
| 701-09-H |
fabricating pipe fittings 54"x54"x12"
|
2   |
EACH |
2,300.00 |
4,600.00 |
3,000.00 |
6,000.00 |
2,398.00 |
4,796.00 |
1,400.00 |
2,800.00 |
| 701-09-I |
fabricating pipe fittings 60"x60"x12"
|
7   |
EACH |
3,000.00 |
21,000.00 |
3,800.00 |
26,600.00 |
3,052.00 |
21,364.00 |
1,500.00 |
10,500.00 |
| 701-09-J |
fabricating pipe fittings 60"x60"x15"
|
2   |
EACH |
3,000.00 |
6,000.00 |
4,000.00 |
8,000.00 |
3,052.00 |
6,104.00 |
1,500.00 |
3,000.00 |
| 702-04-A |
adjusting manholes
|
38   |
EACH |
300.00 |
11,400.00 |
550.00 |
20,900.00 |
550.00 |
20,900.00 |
100.00 |
3,800.00 |
| 706-01-A |
concrete walk (4" thick)
|
2,483.0 |
SQYD |
66.00 |
163,878.00 |
55.00 |
136,565.00 |
80.00 |
198,640.00 |
80.00 |
198,640.00 |
| 706-02-C |
concrete drive (6" thick)
|
504.1 |
SQYD |
80.00 |
40,328.00 |
62.00 |
31,254.20 |
90.00 |
45,369.00 |
80.00 |
40,328.00 |
| 706-02-E |
concrete drive (8" thick)
|
243.4 |
SQYD |
100.00 |
24,340.00 |
70.00 |
17,038.00 |
92.00 |
22,392.80 |
90.00 |
21,906.00 |
| 706-03-C |
incidental concrete paving (6" thick)
|
444.3 |
SQYD |
140.00 |
62,202.00 |
60.00 |
26,658.00 |
100.00 |
44,430.00 |
80.00 |
35,544.00 |
| 707-01 |
concrete curb
|
12,124.0 |
LNFT |
10.00 |
121,240.00 |
8.00 |
96,992.00 |
8.00 |
96,992.00 |
10.00 |
121,240.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
120,000.00 |
120,000.00 |
150,000.00 |
150,000.00 |
100,000.00 |
100,000.00 |
88,000.00 |
88,000.00 |
| 714-01 |
slab sodding
|
2,272   |
SQYD |
7.00 |
15,904.00 |
4.00 |
9,088.00 |
7.00 |
15,904.00 |
10.00 |
22,720.00 |
| 715-01 |
topsoil
|
1,790   |
CUYD |
25.00 |
44,750.00 |
30.00 |
53,700.00 |
0.00 |
0.00 |
11.00 |
19,690.00 |
| 722-01 |
project site laboratory
|
1   |
EACH |
40,000.00 |
40,000.00 |
10,000.00 |
10,000.00 |
25,000.00 |
25,000.00 |
10,000.00 |
10,000.00 |
| 724-01-B |
pavement patching (12" minimum thickness)
|
15   |
SQYD |
265.00 |
3,975.00 |
500.00 |
7,500.00 |
200.00 |
3,000.00 |
200.00 |
3,000.00 |
| 726-01 |
bedding material
|
3,368.1 |
CUYD |
60.00 |
202,086.00 |
70.00 |
235,767.00 |
55.00 |
185,245.50 |
40.00 |
134,724.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
655,000.00 |
655,000.00 |
650,000.00 |
650,000.00 |
750,000.00 |
750,000.00 |
333,000.00 |
333,000.00 |
| 729-01 |
sign (type a)
|
201.0 |
SQFT |
22.00 |
4,422.00 |
25.00 |
5,025.00 |
22.00 |
4,422.00 |
225.00 |
45,225.00 |
| 729-21 |
u-channel post
|
39   |
EACH |
100.00 |
3,900.00 |
100.00 |
3,900.00 |
90.00 |
3,510.00 |
30.00 |
1,170.00 |
| 731-02 |
reflectorized raised pavement markers
|
26   |
EACH |
5.50 |
143.00 |
6.00 |
156.00 |
5.00 |
130.00 |
6.00 |
156.00 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
1.893 |
MILE |
3,000.00 |
5,679.00 |
3,000.00 |
5,679.00 |
2,650.00 |
5,016.45 |
1,600.00 |
3,028.80 |
| 732-02-B |
plastic pavement striping (solid line) (6" width)
|
0.524 |
MILE |
4,200.00 |
2,200.80 |
4,500.00 |
2,358.00 |
4,100.00 |
2,148.40 |
4,800.00 |
2,515.20 |
| 732-02-C |
plastic pavement striping (solid line) (8" width)
|
0.065 |
MILE |
5,500.00 |
357.50 |
6,000.00 |
390.00 |
5,500.00 |
357.50 |
6,600.00 |
429.00 |
| 732-02-D |
plastic pavement striping (solid line) (12" width)
|
0.085 |
MILE |
8,000.00 |
680.00 |
8,500.00 |
722.50 |
8,100.00 |
688.50 |
9,900.00 |
841.50 |
| 732-02-E |
plastic pavement striping (solid line) (24" width)
|
0.015 |
MILE |
17,000.00 |
255.00 |
17,000.00 |
255.00 |
16,450.00 |
246.75 |
20,000.00 |
300.00 |
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
0.110 |
MILE |
800.00 |
88.00 |
800.00 |
88.00 |
790.00 |
86.90 |
900.00 |
99.00 |
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
4   |
EACH |
230.00 |
920.00 |
240.00 |
960.00 |
225.00 |
900.00 |
260.00 |
1,040.00 |
| 732-04-C |
plastic pavement legends & symbols (only)
|
2   |
EACH |
300.00 |
600.00 |
300.00 |
600.00 |
290.00 |
580.00 |
333.00 |
666.00 |
| 739-01 |
hydro-seeding
|
2.60 |
ACRE |
1,200.00 |
3,120.00 |
2,000.00 |
5,200.00 |
1,150.00 |
2,990.00 |
1,500.00 |
3,900.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
100,000.00 |
100,000.00 |
100,000.00 |
100,000.00 |
150,000.00 |
150,000.00 |
133,000.00 |
133,000.00 |
| 744-01 |
traffic control management
|
lump |
LUMP |
7,000.00 |
7,000.00 |
5,000.00 |
5,000.00 |
10,000.00 |
10,000.00 |
33,000.00 |
33,000.00 |
| S-001 |
geogrid
|
25,642.0 |
SQYD |
2.60 |
66,669.20 |
2.50 |
64,105.00 |
2.00 |
51,284.00 |
3.00 |
76,926.00 |
| S-002 |
remove and replace tree with crepe myrtle
|
37   |
EACH |
700.00 |
25,900.00 |
260.00 |
9,620.00 |
700.00 |
25,900.00 |
750.00 |
27,750.00 |
| S-003 |
tree trimming and/or root pruning
|
32   |
EACH |
450.00 |
14,400.00 |
550.00 |
17,600.00 |
400.00 |
12,800.00 |
100.00 |
3,200.00 |
| S-004 |
remove and replace tree in kind
|
4   |
EACH |
800.00 |
3,200.00 |
800.00 |
3,200.00 |
700.00 |
2,800.00 |
1,000.00 |
4,000.00 |
| S-005 |
project sign
|
2   |
EACH |
1,000.00 |
2,000.00 |
1,250.00 |
2,500.00 |
1,500.00 |
3,000.00 |
1,000.00 |
2,000.00 |
| S-006 |
no. 1 standard drain manhole (s&wb of new orleans dwg.
d-870) |
11   |
EACH |
4,000.00 |
44,000.00 |
4,200.00 |
46,200.00 |
3,300.00 |
36,300.00 |
4,400.00 |
48,400.00 |
| S-007 |
no. 3 standard drain manhole (s&wb of new orleans dwg.
d-870) |
4   |
EACH |
5,500.00 |
22,000.00 |
6,300.00 |
25,200.00 |
4,000.00 |
16,000.00 |
5,500.00 |
22,000.00 |
| S-008 |
drain manhole for large pipes (s&wb of new orleans
dwg. d-3340) |
11   |
EACH |
8,500.00 |
93,500.00 |
9,100.00 |
100,100.00 |
5,000.00 |
55,000.00 |
20,000.00 |
220,000.00 |
| S-009 |
special drain manhole
|
5   |
EACH |
11,000.00 |
55,000.00 |
19,600.00 |
98,000.00 |
8,000.00 |
40,000.00 |
25,000.00 |
125,000.00 |
| S-010 |
no. 1 standard catch basin (s&wb of new orleans dwg.
d-873) |
53   |
EACH |
3,500.00 |
185,500.00 |
3,500.00 |
185,500.00 |
3,000.00 |
159,000.00 |
4,300.00 |
227,900.00 |
| S-011 |
double no. 1 catch basin (s&wb of new orleans dwg.
d-873-a) |
6   |
EACH |
6,500.00 |
39,000.00 |
6,800.00 |
40,800.00 |
4,000.00 |
24,000.00 |
7,000.00 |
42,000.00 |
| S-012 |
single mountable catch basin (s&wb of new orleans dwg.
d-3431-a) |
3   |
EACH |
3,000.00 |
9,000.00 |
3,600.00 |
10,800.00 |
3,000.00 |
9,000.00 |
3,666.00 |
10,998.00 |
| S-013 |
double mountable catch basin (s&wb of new orleans dwg.
d-3431-b) |
1   |
EACH |
5,000.00 |
5,000.00 |
6,600.00 |
6,600.00 |
3,000.00 |
3,000.00 |
4,888.00 |
4,888.00 |
| S-014 |
24" x 30" clear opening standard drop inlet (s&wb of
new orleans dwg. d-3264) |
8   |
EACH |
3,500.00 |
28,000.00 |
3,300.00 |
26,400.00 |
2,000.00 |
16,000.00 |
3,300.00 |
26,400.00 |
| S-015 |
new 6" water valve with valve box (r.d. wood double
disc gate valve per s&wb) |
5   |
EACH |
5,000.00 |
25,000.00 |
5,000.00 |
25,000.00 |
4,000.00 |
20,000.00 |
4,600.00 |
23,000.00 |
| S-016 |
new 8" water valve and manhole(r.d. wood double disc
gate valve per s&wb) |
7   |
EACH |
8,000.00 |
56,000.00 |
8,900.00 |
62,300.00 |
7,000.00 |
49,000.00 |
8,800.00 |
61,600.00 |
| S-017 |
new 12" water valve and manhole (r.d. wood double disc
gate valve per s&wb) |
2   |
EACH |
11,000.00 |
22,000.00 |
12,000.00 |
24,000.00 |
10,000.00 |
20,000.00 |
11,188.00 |
22,376.00 |
| S-018 |
new manhole around existing water valve
|
1   |
EACH |
2,100.00 |
2,100.00 |
4,000.00 |
4,000.00 |
3,000.00 |
3,000.00 |
10,000.00 |
10,000.00 |
| S-019 |
fire hydrant (includes fire hydrant, lead, tee, lugs,
blocking, etc.) |
5   |
EACH |
2,200.00 |
11,000.00 |
3,800.00 |
19,000.00 |
3,000.00 |
15,000.00 |
4,600.00 |
23,000.00 |
| S-020 |
relocate existing fire hydrant
|
1   |
EACH |
4,500.00 |
4,500.00 |
3,000.00 |
3,000.00 |
3,000.00 |
3,000.00 |
2,600.00 |
2,600.00 |
| S-021 |
replace 3/4" water house connection (from main to
meter) |
3   |
EACH |
1,500.00 |
4,500.00 |
600.00 |
1,800.00 |
600.00 |
1,800.00 |
2,500.00 |
7,500.00 |
| S-022 |
replace 1" water house connection (from main to meter)
|
10   |
EACH |
3,000.00 |
30,000.00 |
700.00 |
7,000.00 |
700.00 |
7,000.00 |
2,600.00 |
26,000.00 |
| S-023 |
water service line (2" pvc from main to valve)
|
50   |
LNFT |
35.00 |
1,750.00 |
50.00 |
2,500.00 |
40.00 |
2,000.00 |
33.00 |
1,650.00 |
| S-024 |
6" water line offset
|
5   |
EACH |
3,500.00 |
17,500.00 |
5,000.00 |
25,000.00 |
5,000.00 |
25,000.00 |
10,000.00 |
50,000.00 |
| S-025 |
adj. water valve and/or meter box(complete to grade)
including removal of mu d/debris inside the water meter or valve box |
37   |
EACH |
300.00 |
11,100.00 |
500.00 |
18,500.00 |
200.00 |
7,400.00 |
50.00 |
1,850.00 |
| S-026 |
replace sewer house connection to back of curb
|
17   |
EACH |
600.00 |
10,200.00 |
1,500.00 |
25,500.00 |
2,000.00 |
34,000.00 |
100.00 |
1,700.00 |
| S-027 |
replace existing sewer house connection beyond back of
curb |
85   |
LNFT |
70.00 |
5,950.00 |
70.00 |
5,950.00 |
60.00 |
5,100.00 |
10.00 |
850.00 |
| S-028 |
8" pvc drain house connection collector line
|
750   |
LNFT |
20.00 |
15,000.00 |
40.00 |
30,000.00 |
15.00 |
11,250.00 |
10.00 |
7,500.00 |
| S-029 |
replace drain house connection beyond back of curb
|
330   |
LNFT |
30.00 |
9,900.00 |
30.00 |
9,900.00 |
25.00 |
8,250.00 |
10.00 |
3,300.00 |
| S-030 |
exploratory excavation
|
7   |
EACH |
1,600.00 |
11,200.00 |
1,200.00 |
8,400.00 |
900.00 |
6,300.00 |
1,000.00 |
7,000.00 |
| S-031 |
saw cut existing concrete pavement (full depth)
including curb |
340   |
LNFT |
13.00 |
4,420.00 |
14.00 |
4,760.00 |
10.00 |
3,400.00 |
25.00 |
8,500.00 |
| S-032 |
saw cut, wheel cut, or spade cut existing asphaltic
concrete pavement (full depth) |
523   |
LNFT |
11.00 |
5,753.00 |
14.00 |
7,322.00 |
10.00 |
5,230.00 |
15.00 |
7,845.00 |
| S-033 |
relocate existing signal pedestal poles, including new
foundations, demo of existing foundations, conduit & rewiring |
3   |
EACH |
4,000.00 |
12,000.00 |
3,200.00 |
9,600.00 |
3,000.00 |
9,000.00 |
3,500.00 |
10,500.00 |
| S-034 |
relocate existing signal double mast arms, including
new foundations, demo of existing foundations, conduit & rewiring |
2   |
EACH |
9,000.00 |
18,000.00 |
8,000.00 |
16,000.00 |
7,500.00 |
15,000.00 |
8,800.00 |
17,600.00 |
| S-035 |
relocate existing traffic manhole, including new
foundation, conduit and rewiring |
1   |
EACH |
6,000.00 |
6,000.00 |
6,000.00 |
6,000.00 |
5,500.00 |
5,500.00 |
6,400.00 |
6,400.00 |
| S-036 |
relocate existing signal service meter, including
conduit and rewiring |
1   |
EACH |
3,000.00 |
3,000.00 |
2,700.00 |
2,700.00 |
2,500.00 |
2,500.00 |
2,900.00 |
2,900.00 |
| S-037 |
street name signs on new post or mast arm
|
22   |
EACH |
250.00 |
5,500.00 |
270.00 |
5,940.00 |
250.00 |
5,500.00 |
200.00 |
4,400.00 |
| S-038 |
hand formed and poured in place concrete curb within
the limits of the tree dripline |
70   |
LNFT |
25.00 |
1,750.00 |
50.00 |
3,500.00 |
20.00 |
1,400.00 |
50.00 |
3,500.00 |
| S-039 |
gravel bed and filter cloth over tree roots
|
66   |
SQYD |
25.00 |
1,650.00 |
30.00 |
1,980.00 |
7.00 |
462.00 |
1.00 |
66.00 |
| S-040 |
install stainless steel trough through the top slab of
the st. anthony ave. box canal |
lump |
LUMP |
30,000.00 |
30,000.00 |
28,000.00 |
28,000.00 |
10,000.00 |
10,000.00 |
66,000.00 |
66,000.00 |
| S-041 |
type a catch basin adjustment
|
5   |
EACH |
1,000.00 |
5,000.00 |
500.00 |
2,500.00 |
800.00 |
4,000.00 |
100.00 |
500.00 |
| S-042 |
60" rcp drain line tie-in to existing concrete box
canal |
2   |
EACH |
20,000.00 |
40,000.00 |
14,500.00 |
29,000.00 |
30,000.00 |
60,000.00 |
88,000.00 |
176,000.00 |
| S-043 |
48" rcp drain line tie-in to existing concrete box
canal |
1   |
EACH |
13,000.00 |
13,000.00 |
12,000.00 |
12,000.00 |
25,000.00 |
25,000.00 |
66,000.00 |
66,000.00 |
| S-044 |
36" equiv. (43" x 26") sdpa drain line tie-in to
existing concrete box canal |
1   |
EACH |
16,000.00 |
16,000.00 |
8,500.00 |
8,500.00 |
25,000.00 |
25,000.00 |
44,000.00 |
44,000.00 |
| S-045 |
water main -6" pvc with main line fittings
|
40.0 |
LNFT |
95.00 |
3,800.00 |
75.00 |
3,000.00 |
70.00 |
2,800.00 |
130.00 |
5,200.00 |
| S-046 |
water main -8" pvc with main line fittings
|
660.0 |
LNFT |
95.00 |
62,700.00 |
78.00 |
51,480.00 |
60.00 |
39,600.00 |
160.00 |
105,600.00 |
| S-047 |
water main -12" pvc with main line fittings
|
1,380.0 |
LNFT |
75.00 |
103,500.00 |
88.00 |
121,440.00 |
60.00 |
82,800.00 |
100.00 |
138,000.00 |
| S-048 |
water main 6" d.i. with main line fittings
|
50.0 |
LNFT |
130.00 |
6,500.00 |
108.00 |
5,400.00 |
185.00 |
9,250.00 |
200.00 |
10,000.00 |
| S-049 |
water main 8" d.i. with main line fittings
|
70.0 |
LNFT |
130.00 |
9,100.00 |
118.00 |
8,260.00 |
115.00 |
8,050.00 |
210.00 |
14,700.00 |
| S-050 |
water main 12" d.i. with main line fittings
|
20.0 |
LNFT |
200.00 |
4,000.00 |
139.00 |
2,780.00 |
265.00 |
5,300.00 |
220.00 |
4,400.00 |
| S-051 |
untreated timber foundations for bedding material
|
113.0 |
MFBM |
700.00 |
79,100.00 |
400.00 |
45,200.00 |
900.00 |
101,700.00 |
500.00 |
56,500.00 |
| S-052 |
geotextile fabric
|
53,171.0 |
SQYD |
1.00 |
53,171.00 |
1.00 |
53,171.00 |
1.00 |
53,171.00 |
1.00 |
53,171.00 |
| S-053 |
brick sidewalk or footlap
|
8.0 |
SQYD |
100.00 |
800.00 |
550.00 |
4,400.00 |
150.00 |
1,200.00 |
400.00 |
3,200.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | ITEM TOTAL (CONSTRUCTION BID) |
|
|
|
7,289,451.90 |
|
7,322,076.80 |
|
7,452,294.80 |
|
7,787,950.50 |
| | NUMBER OF DAYS BID AT $1,000 PER DAY. |
|
|
|
385,000.00 |
|
450,000.00 |
|
380,000.00 |
|
440,000.00 |
| | TOTAL BID |
|
|
|
7,674,451.90 |
|
7,772,076.80 |
|
7,832,294.80 |
|
8,227,950.50 |
|
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 5 - JAMES CONSTRUCTION GROUP LLC |
- 6 - CYCLE CONSTRUCTION CO. L.L.C. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
45,000.00 |
45,000.00 |
50,000.00 |
50,000.00 |
|
|
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
400,000.00 |
400,000.00 |
190,000.00 |
190,000.00 |
|
|
|
|
| 202-02-C |
removal of portland cement concrete pavement
|
18,297   |
SQYD |
18.00 |
329,346.00 |
11.00 |
201,267.00 |
|
|
|
|
| 202-02-D |
removal of concrete walks & drives
|
4,037   |
SQYD |
7.00 |
28,259.00 |
11.00 |
44,407.00 |
|
|
|
|
| 202-02-F |
removal of concrete combination curb & gutter
|
1,027.0 |
LNFT |
6.00 |
6,162.00 |
5.00 |
5,135.00 |
|
|
|
|
| 202-02-I |
removal of asphaltic concrete pavement
|
3,070   |
SQYD |
8.00 |
24,560.00 |
9.00 |
27,630.00 |
|
|
|
|
| 203-05 |
nonplastic embankment
|
9,817   |
CUYD |
35.00 |
343,595.00 |
27.00 |
265,059.00 |
|
|
|
|
| 203-06 |
excavation & embankment
|
lump |
LUMP |
105,000.00 |
105,000.00 |
250,000.00 |
250,000.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
12,200   |
LNFT |
3.50 |
42,700.00 |
2.50 |
30,500.00 |
|
|
|
|
| 302-02-E-01 |
class ii base course (8" thick)(stone or recycled pccp)
|
25,640.8 |
SQYD |
24.00 |
615,379.20 |
24.00 |
615,379.20 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
477.3 |
TON |
130.00 |
62,049.00 |
150.00 |
71,595.00 |
|
|
|
|
| 601-01-I |
portland cement concrete pavement (9" thick)
|
22,585.5 |
SQYD |
75.00 |
1,693,912.50 |
70.00 |
1,580,985.00 |
|
|
|
|
| 601-02-G |
portland cement concrete pavement (8" thick)
(crossovers & turnouts) |
282.0 |
SQYD |
115.00 |
32,430.00 |
95.00 |
26,790.00 |
|
|
|
|
| 701-03-E |
storm drain pipe (12" rcp)
|
363   |
LNFT |
69.00 |
25,047.00 |
160.00 |
58,080.00 |
|
|
|
|
| 701-03-F |
storm drain pipe (15" rcp)
|
1,086   |
LNFT |
72.00 |
78,192.00 |
170.00 |
184,620.00 |
|
|
|
|
| 701-03-G |
storm drain pipe (18" rcp)
|
154   |
LNFT |
78.00 |
12,012.00 |
220.00 |
33,880.00 |
|
|
|
|
| 701-03-I |
storm drain pipe (24" rcp)
|
481   |
LNFT |
105.00 |
50,505.00 |
230.00 |
110,630.00 |
|
|
|
|
| 701-03-M |
storm drain pipe (36" rcp)
|
913   |
LNFT |
175.00 |
159,775.00 |
290.00 |
264,770.00 |
|
|
|
|
| 701-03-O |
storm drain pipe (48" rcp)
|
1,506   |
LNFT |
240.00 |
361,440.00 |
360.00 |
542,160.00 |
|
|
|
|
| 701-03-P |
storm drain pipe (54" rcp)
|
261   |
LNFT |
300.00 |
78,300.00 |
400.00 |
104,400.00 |
|
|
|
|
| 701-03-Q |
storm drain pipe (60" rcp)
|
832   |
LNFT |
360.00 |
299,520.00 |
475.00 |
395,200.00 |
|
|
|
|
| 701-04-A |
storm drain pipe arch (15" equiv. rcpa)
|
115   |
LNFT |
90.00 |
10,350.00 |
220.00 |
25,300.00 |
|
|
|
|
| 701-04-B |
storm drain pipe arch (18" equiv. rcpa)
|
60   |
LNFT |
105.00 |
6,300.00 |
240.00 |
14,400.00 |
|
|
|
|
| 701-04-D |
storm drain pipe arch (24" equiv. rcpa)
|
256   |
LNFT |
135.00 |
34,560.00 |
250.00 |
64,000.00 |
|
|
|
|
| 701-04-F |
storm drain pipe arch (36" equiv. rcpa)
|
25   |
LNFT |
188.00 |
4,700.00 |
360.00 |
9,000.00 |
|
|
|
|
| 701-09-A |
fabricating pipe fittings 15"x15"x12"
|
1   |
EACH |
800.00 |
800.00 |
2,300.00 |
2,300.00 |
|
|
|
|
| 701-09-B |
fabricating pipe fittings 15"x15"x15"
|
1   |
EACH |
815.00 |
815.00 |
2,900.00 |
2,900.00 |
|
|
|
|
| 701-09-C |
fabricating pipe fittings 18"x18"x12"
|
1   |
EACH |
825.00 |
825.00 |
3,000.00 |
3,000.00 |
|
|
|
|
| 701-09-D |
fabricating pipe fittings 24"x24"x12"
|
2   |
EACH |
1,200.00 |
2,400.00 |
3,800.00 |
7,600.00 |
|
|
|
|
| 701-09-E |
fabricating pipe fittings 36"x36"x12"
|
6   |
EACH |
2,000.00 |
12,000.00 |
4,600.00 |
27,600.00 |
|
|
|
|
| 701-09-F |
fabricating pipe fittings 36"x36"x15"
|
1   |
EACH |
2,300.00 |
2,300.00 |
4,600.00 |
4,600.00 |
|
|
|
|
| 701-09-G |
fabricating pipe fittings 48"x48"x12"
|
12   |
EACH |
3,100.00 |
37,200.00 |
5,600.00 |
67,200.00 |
|
|
|
|
| 701-09-H |
fabricating pipe fittings 54"x54"x12"
|
2   |
EACH |
3,400.00 |
6,800.00 |
8,600.00 |
17,200.00 |
|
|
|
|
| 701-09-I |
fabricating pipe fittings 60"x60"x12"
|
7   |
EACH |
4,200.00 |
29,400.00 |
9,500.00 |
66,500.00 |
|
|
|
|
| 701-09-J |
fabricating pipe fittings 60"x60"x15"
|
2   |
EACH |
4,300.00 |
8,600.00 |
9,500.00 |
19,000.00 |
|
|
|
|
| 702-04-A |
adjusting manholes
|
38   |
EACH |
1,250.00 |
47,500.00 |
1,000.00 |
38,000.00 |
|
|
|
|
| 706-01-A |
concrete walk (4" thick)
|
2,483.0 |
SQYD |
60.00 |
148,980.00 |
67.00 |
166,361.00 |
|
|
|
|
| 706-02-C |
concrete drive (6" thick)
|
504.1 |
SQYD |
75.00 |
37,807.50 |
70.00 |
35,287.00 |
|
|
|
|
| 706-02-E |
concrete drive (8" thick)
|
243.4 |
SQYD |
85.00 |
20,689.00 |
75.00 |
18,255.00 |
|
|
|
|
| 706-03-C |
incidental concrete paving (6" thick)
|
444.3 |
SQYD |
100.00 |
44,430.00 |
50.00 |
22,215.00 |
|
|
|
|
| 707-01 |
concrete curb
|
12,124.0 |
LNFT |
10.00 |
121,240.00 |
12.00 |
145,488.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
90,000.00 |
90,000.00 |
200,000.00 |
200,000.00 |
|
|
|
|
| 714-01 |
slab sodding
|
2,272   |
SQYD |
7.50 |
17,040.00 |
5.00 |
11,360.00 |
|
|
|
|
| 715-01 |
topsoil
|
1,790   |
CUYD |
50.00 |
89,500.00 |
30.00 |
53,700.00 |
|
|
|
|
| 722-01 |
project site laboratory
|
1   |
EACH |
15,000.00 |
15,000.00 |
25,000.00 |
25,000.00 |
|
|
|
|
| 724-01-B |
pavement patching (12" minimum thickness)
|
15   |
SQYD |
1,000.00 |
15,000.00 |
300.00 |
4,500.00 |
|
|
|
|
| 726-01 |
bedding material
|
3,368.1 |
CUYD |
90.00 |
303,129.00 |
65.00 |
218,926.50 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
820,000.00 |
820,000.00 |
500,000.00 |
500,000.00 |
|
|
|
|
| 729-01 |
sign (type a)
|
201.0 |
SQFT |
22.00 |
4,422.00 |
26.00 |
5,226.00 |
|
|
|
|
| 729-21 |
u-channel post
|
39   |
EACH |
90.00 |
3,510.00 |
100.00 |
3,900.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
26   |
EACH |
5.20 |
135.20 |
6.00 |
156.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
1.893 |
MILE |
1,400.00 |
2,650.20 |
3,200.00 |
6,057.60 |
|
|
|
|
| 732-02-B |
plastic pavement striping (solid line) (6" width)
|
0.524 |
MILE |
4,200.00 |
2,200.80 |
5,000.00 |
2,620.00 |
|
|
|
|
| 732-02-C |
plastic pavement striping (solid line) (8" width)
|
0.065 |
MILE |
6,000.00 |
390.00 |
7,000.00 |
455.00 |
|
|
|
|
| 732-02-D |
plastic pavement striping (solid line) (12" width)
|
0.085 |
MILE |
8,600.00 |
731.00 |
10,000.00 |
850.00 |
|
|
|
|
| 732-02-E |
plastic pavement striping (solid line) (24" width)
|
0.015 |
MILE |
25,000.00 |
375.00 |
13,000.00 |
195.00 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
0.110 |
MILE |
790.00 |
86.90 |
900.00 |
99.00 |
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
4   |
EACH |
225.00 |
900.00 |
300.00 |
1,200.00 |
|
|
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
2   |
EACH |
290.00 |
580.00 |
300.00 |
600.00 |
|
|
|
|
| 739-01 |
hydro-seeding
|
2.60 |
ACRE |
1,150.00 |
2,990.00 |
1,700.00 |
4,420.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
225,000.00 |
225,000.00 |
150,000.00 |
150,000.00 |
|
|
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
25,000.00 |
25,000.00 |
100,000.00 |
100,000.00 |
|
|
|
|
| S-001 |
geogrid
|
25,642.0 |
SQYD |
4.00 |
102,568.00 |
3.00 |
76,926.00 |
|
|
|
|
| S-002 |
remove and replace tree with crepe myrtle
|
37   |
EACH |
40.00 |
1,480.00 |
900.00 |
33,300.00 |
|
|
|
|
| S-003 |
tree trimming and/or root pruning
|
32   |
EACH |
35.00 |
1,120.00 |
600.00 |
19,200.00 |
|
|
|
|
| S-004 |
remove and replace tree in kind
|
4   |
EACH |
10.00 |
40.00 |
900.00 |
3,600.00 |
|
|
|
|
| S-005 |
project sign
|
2   |
EACH |
1,500.00 |
3,000.00 |
1,000.00 |
2,000.00 |
|
|
|
|
| S-006 |
no. 1 standard drain manhole (s&wb of new orleans dwg.
d-870) |
11   |
EACH |
3,200.00 |
35,200.00 |
9,000.00 |
99,000.00 |
|
|
|
|
| S-007 |
no. 3 standard drain manhole (s&wb of new orleans dwg.
d-870) |
4   |
EACH |
4,800.00 |
19,200.00 |
11,000.00 |
44,000.00 |
|
|
|
|
| S-008 |
drain manhole for large pipes (s&wb of new orleans
dwg. d-3340) |
11   |
EACH |
6,500.00 |
71,500.00 |
30,000.00 |
330,000.00 |
|
|
|
|
| S-009 |
special drain manhole
|
5   |
EACH |
6,000.00 |
30,000.00 |
40,000.00 |
200,000.00 |
|
|
|
|
| S-010 |
no. 1 standard catch basin (s&wb of new orleans dwg.
d-873) |
53   |
EACH |
2,850.00 |
151,050.00 |
9,500.00 |
503,500.00 |
|
|
|
|
| S-011 |
double no. 1 catch basin (s&wb of new orleans dwg.
d-873-a) |
6   |
EACH |
4,000.00 |
24,000.00 |
11,000.00 |
66,000.00 |
|
|
|
|
| S-012 |
single mountable catch basin (s&wb of new orleans dwg.
d-3431-a) |
3   |
EACH |
2,500.00 |
7,500.00 |
8,500.00 |
25,500.00 |
|
|
|
|
| S-013 |
double mountable catch basin (s&wb of new orleans dwg.
d-3431-b) |
1   |
EACH |
5,800.00 |
5,800.00 |
10,000.00 |
10,000.00 |
|
|
|
|
| S-014 |
24" x 30" clear opening standard drop inlet (s&wb of
new orleans dwg. d-3264) |
8   |
EACH |
3,000.00 |
24,000.00 |
8,500.00 |
68,000.00 |
|
|
|
|
| S-015 |
new 6" water valve with valve box (r.d. wood double
disc gate valve per s&wb) |
5   |
EACH |
4,500.00 |
22,500.00 |
6,000.00 |
30,000.00 |
|
|
|
|
| S-016 |
new 8" water valve and manhole(r.d. wood double disc
gate valve per s&wb) |
7   |
EACH |
5,200.00 |
36,400.00 |
16,500.00 |
115,500.00 |
|
|
|
|
| S-017 |
new 12" water valve and manhole (r.d. wood double disc
gate valve per s&wb) |
2   |
EACH |
9,000.00 |
18,000.00 |
19,500.00 |
39,000.00 |
|
|
|
|
| S-018 |
new manhole around existing water valve
|
1   |
EACH |
61,000.00 |
61,000.00 |
12,500.00 |
12,500.00 |
|
|
|
|
| S-019 |
fire hydrant (includes fire hydrant, lead, tee, lugs,
blocking, etc.) |
5   |
EACH |
4,900.00 |
24,500.00 |
5,400.00 |
27,000.00 |
|
|
|
|
| S-020 |
relocate existing fire hydrant
|
1   |
EACH |
2,200.00 |
2,200.00 |
4,600.00 |
4,600.00 |
|
|
|
|
| S-021 |
replace 3/4" water house connection (from main to
meter) |
3   |
EACH |
600.00 |
1,800.00 |
2,200.00 |
6,600.00 |
|
|
|
|
| S-022 |
replace 1" water house connection (from main to meter)
|
10   |
EACH |
650.00 |
6,500.00 |
2,200.00 |
22,000.00 |
|
|
|
|
| S-023 |
water service line (2" pvc from main to valve)
|
50   |
LNFT |
12.00 |
600.00 |
75.00 |
3,750.00 |
|
|
|
|
| S-024 |
6" water line offset
|
5   |
EACH |
2,200.00 |
11,000.00 |
11,000.00 |
55,000.00 |
|
|
|
|
| S-025 |
adj. water valve and/or meter box(complete to grade)
including removal of mu d/debris inside the water meter or valve box |
37   |
EACH |
600.00 |
22,200.00 |
500.00 |
18,500.00 |
|
|
|
|
| S-026 |
replace sewer house connection to back of curb
|
17   |
EACH |
550.00 |
9,350.00 |
2,000.00 |
34,000.00 |
|
|
|
|
| S-027 |
replace existing sewer house connection beyond back of
curb |
85   |
LNFT |
30.00 |
2,550.00 |
200.00 |
17,000.00 |
|
|
|
|
| S-028 |
8" pvc drain house connection collector line
|
750   |
LNFT |
30.00 |
22,500.00 |
150.00 |
112,500.00 |
|
|
|
|
| S-029 |
replace drain house connection beyond back of curb
|
330   |
LNFT |
30.00 |
9,900.00 |
150.00 |
49,500.00 |
|
|
|
|
| S-030 |
exploratory excavation
|
7   |
EACH |
1,500.00 |
10,500.00 |
2,000.00 |
14,000.00 |
|
|
|
|
| S-031 |
saw cut existing concrete pavement (full depth)
including curb |
340   |
LNFT |
6.00 |
2,040.00 |
14.00 |
4,760.00 |
|
|
|
|
| S-032 |
saw cut, wheel cut, or spade cut existing asphaltic
concrete pavement (full depth) |
523   |
LNFT |
8.00 |
4,184.00 |
7.00 |
3,661.00 |
|
|
|
|
| S-033 |
relocate existing signal pedestal poles, including new
foundations, demo of existing foundations, conduit & rewiring |
3   |
EACH |
3,000.00 |
9,000.00 |
3,500.00 |
10,500.00 |
|
|
|
|
| S-034 |
relocate existing signal double mast arms, including
new foundations, demo of existing foundations, conduit & rewiring |
2   |
EACH |
7,500.00 |
15,000.00 |
9,000.00 |
18,000.00 |
|
|
|
|
| S-035 |
relocate existing traffic manhole, including new
foundation, conduit and rewiring |
1   |
EACH |
5,500.00 |
5,500.00 |
6,500.00 |
6,500.00 |
|
|
|
|
| S-036 |
relocate existing signal service meter, including
conduit and rewiring |
1   |
EACH |
2,500.00 |
2,500.00 |
3,000.00 |
3,000.00 |
|
|
|
|
| S-037 |
street name signs on new post or mast arm
|
22   |
EACH |
150.00 |
3,300.00 |
300.00 |
6,600.00 |
|
|
|
|
| S-038 |
hand formed and poured in place concrete curb within
the limits of the tree dripline |
70   |
LNFT |
500.00 |
35,000.00 |
15.00 |
1,050.00 |
|
|
|
|
| S-039 |
gravel bed and filter cloth over tree roots
|
66   |
SQYD |
10.00 |
660.00 |
80.00 |
5,280.00 |
|
|
|
|
| S-040 |
install stainless steel trough through the top slab of
the st. anthony ave. box canal |
lump |
LUMP |
20,000.00 |
20,000.00 |
32,000.00 |
32,000.00 |
|
|
|
|
| S-041 |
type a catch basin adjustment
|
5   |
EACH |
4,500.00 |
22,500.00 |
5,000.00 |
25,000.00 |
|
|
|
|
| S-042 |
60" rcp drain line tie-in to existing concrete box
canal |
2   |
EACH |
4,250.00 |
8,500.00 |
22,000.00 |
44,000.00 |
|
|
|
|
| S-043 |
48" rcp drain line tie-in to existing concrete box
canal |
1   |
EACH |
3,200.00 |
3,200.00 |
12,000.00 |
12,000.00 |
|
|
|
|
| S-044 |
36" equiv. (43" x 26") sdpa drain line tie-in to
existing concrete box canal |
1   |
EACH |
1,800.00 |
1,800.00 |
12,000.00 |
12,000.00 |
|
|
|
|
| S-045 |
water main -6" pvc with main line fittings
|
40.0 |
LNFT |
60.00 |
2,400.00 |
425.00 |
17,000.00 |
|
|
|
|
| S-046 |
water main -8" pvc with main line fittings
|
660.0 |
LNFT |
65.00 |
42,900.00 |
160.00 |
105,600.00 |
|
|
|
|
| S-047 |
water main -12" pvc with main line fittings
|
1,380.0 |
LNFT |
70.00 |
96,600.00 |
170.00 |
234,600.00 |
|
|
|
|
| S-048 |
water main 6" d.i. with main line fittings
|
50.0 |
LNFT |
70.00 |
3,500.00 |
250.00 |
12,500.00 |
|
|
|
|
| S-049 |
water main 8" d.i. with main line fittings
|
70.0 |
LNFT |
80.00 |
5,600.00 |
255.00 |
17,850.00 |
|
|
|
|
| S-050 |
water main 12" d.i. with main line fittings
|
20.0 |
LNFT |
120.00 |
2,400.00 |
330.00 |
6,600.00 |
|
|
|
|
| S-051 |
untreated timber foundations for bedding material
|
113.0 |
MFBM |
2,200.00 |
248,600.00 |
1,206.54 |
136,339.02 |
|
|
|
|
| S-052 |
geotextile fabric
|
53,171.0 |
SQYD |
2.50 |
132,927.50 |
1.54 |
81,883.34 |
|
|
|
|
| S-053 |
brick sidewalk or footlap
|
8.0 |
SQYD |
1,000.00 |
8,000.00 |
361.96 |
2,895.68 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | ITEM TOTAL (CONSTRUCTION BID) |
|
|
|
8,403,589.80 |
|
9,940,053.34 |
|
|
|
|
| | NUMBER OF DAYS BID AT $1,000 PER DAY. |
|
|
|
480,000.00 |
|
450,000.00 |
|
|
|
|
| | TOTAL BID |
|
|
|
8,883,589.80 |
|
10,390,053.34 |
|
|
|
|
|