| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - D & J CONSTRUCTION CO., INC. |
- 2 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 3 - GILCHRIST CONSTRUCTION CO. LLC |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 203-07 |
borrow (vehicular measurement)
|
1,116   |
CUYD |
15.00 |
16,740.00 |
16.00 |
17,856.00 |
30.00 |
33,480.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
7,281.1 |
TON |
90.00 |
655,299.00 |
85.00 |
618,893.50 |
100.00 |
728,110.00 |
|
|
| 507-01-A |
asphaltic material (crs-2p cold applied emulsion)
|
49,100   |
GAL |
2.20 |
108,020.00 |
2.25 |
110,475.00 |
2.00 |
98,200.00 |
|
|
| 507-02-B |
aggregate (s2)
|
84,836   |
SQYD |
1.20 |
101,803.20 |
1.35 |
114,528.60 |
1.40 |
118,770.40 |
|
|
| 507-02-C |
aggregate (s3)
|
53,023   |
SQYD |
0.75 |
39,767.25 |
0.90 |
47,720.70 |
1.00 |
53,023.00 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
53,023   |
SQYD |
2.25 |
119,301.75 |
1.50 |
79,534.50 |
1.80 |
95,441.40 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 1,474   |
CUYD |
0.01 |
- 14.74 |
0.10 |
- 147.40 |
0.01 |
- 14.74 |
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
70   |
SQYD |
150.00 |
10,500.00 |
130.00 |
9,100.00 |
220.00 |
15,400.00 |
|
|
| 510-01-C |
pavement patching (18" minimum thickness)
|
550   |
SQYD |
150.00 |
82,500.00 |
150.00 |
82,500.00 |
200.00 |
110,000.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
42,500.00 |
42,500.00 |
45,000.00 |
45,000.00 |
20,000.00 |
20,000.00 |
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
10.845 |
MILE |
225.00 |
2,440.13 |
150.00 |
1,626.75 |
350.00 |
3,795.75 |
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
10.845 |
MILE |
360.00 |
3,904.20 |
330.00 |
3,578.85 |
325.00 |
3,524.63 |
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
21.691 |
MILE |
400.00 |
8,676.40 |
200.00 |
4,338.20 |
750.00 |
16,268.25 |
|
|
| 713-06-A |
temporary reflectorized raised pavement markers (tabs)
|
478   |
EACH |
1.50 |
717.00 |
1.50 |
717.00 |
1.00 |
478.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
60,000.00 |
60,000.00 |
128,500.00 |
128,500.00 |
77,000.00 |
77,000.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
478   |
EACH |
6.80 |
3,250.40 |
5.00 |
2,390.00 |
6.50 |
3,107.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
7.230 |
MILE |
2,500.00 |
18,075.00 |
2,500.00 |
18,075.00 |
3,300.00 |
23,859.00 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
3.615 |
MILE |
1,200.00 |
4,338.00 |
800.00 |
2,892.00 |
1,000.00 |
3,615.00 |
|
|
| 735-01 |
mailboxes
|
7   |
EACH |
20.00 |
140.00 |
12.00 |
84.00 |
15.00 |
105.00 |
|
|
| 735-02 |
mailbox supports (single)
|
5   |
EACH |
175.00 |
875.00 |
200.00 |
1,000.00 |
150.00 |
750.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
11,000.00 |
11,000.00 |
11,000.00 |
11,000.00 |
12,000.00 |
12,000.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,289,832.59 |
|
1,299,662.70 |
|
1,416,912.69 |
|
|
|