| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 2 - W. E. MCDONALD & SON, LLC. |
- 3 - GILCHRIST CONSTRUCTION CO. LLC |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
7,000.00 |
7,000.00 |
2,500.00 |
2,500.00 |
14,000.00 |
14,000.00 |
|
|
| 202-02-D |
removal of concrete walks & drives
|
25   |
SQYD |
41.00 |
1,025.00 |
65.00 |
1,625.00 |
50.00 |
1,250.00 |
|
|
| 202-02-E |
removal of concrete curbs
|
590.0 |
LNFT |
3.50 |
2,065.00 |
5.00 |
2,950.00 |
10.00 |
5,900.00 |
|
|
| 202-02-H |
removal of guard rail
|
584   |
LNFT |
6.00 |
3,504.00 |
3.00 |
1,752.00 |
6.00 |
3,504.00 |
|
|
| 203-07 |
borrow (vehicular measurement)
|
646   |
CUYD |
18.00 |
11,628.00 |
12.00 |
7,752.00 |
15.00 |
9,690.00 |
|
|
| 203-07-A |
borrow (vehicular meas.)(selected soils)
|
200   |
CUYD |
16.00 |
3,200.00 |
12.00 |
2,400.00 |
20.00 |
4,000.00 |
|
|
| 304-01 |
lime
|
596.14 |
TON |
150.00 |
89,421.00 |
153.00 |
91,209.42 |
155.00 |
92,401.70 |
|
|
| 304-04-D |
lime treatment (type d) (12" thick)
|
37,850   |
SQYD |
2.00 |
75,700.00 |
3.27 |
123,769.50 |
3.50 |
132,475.00 |
|
|
| 308-01-A |
in-place cement treated base course (12" thick)
|
56,557   |
SQYD |
6.25 |
353,481.25 |
6.50 |
367,620.50 |
6.50 |
367,620.50 |
|
|
| 308-02 |
removal of existing patches
|
350   |
SQYD |
16.00 |
5,600.00 |
15.00 |
5,250.00 |
20.00 |
7,000.00 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
2,002   |
CUYD |
19.00 |
38,038.00 |
20.00 |
40,040.00 |
85.00 |
170,170.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
10,003.3 |
TON |
84.00 |
840,277.20 |
90.00 |
900,297.00 |
89.00 |
890,293.70 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
492.3 |
TON |
140.00 |
68,922.00 |
140.00 |
68,922.00 |
175.00 |
86,152.50 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
53,165   |
SQYD |
1.00 |
53,165.00 |
1.00 |
53,165.00 |
0.45 |
23,924.25 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 3,765   |
CUYD |
0.10 |
- 376.50 |
0.01 |
- 37.65 |
0.01 |
- 37.65 |
|
|
| 701-10-P |
reinforced concrete pipe (extension)(54")
|
16   |
LNFT |
435.00 |
6,960.00 |
350.00 |
5,600.00 |
300.00 |
4,800.00 |
|
|
| 701-15 |
concrete collar
|
1   |
EACH |
2,000.00 |
2,000.00 |
1,500.00 |
1,500.00 |
1,600.00 |
1,600.00 |
|
|
| 704-01-B |
guard rail (single thrie beam)(6'-3" post spacing)
|
560.0 |
LNFT |
33.00 |
18,480.00 |
30.00 |
16,800.00 |
31.00 |
17,360.00 |
|
|
| 704-03 |
blocked out guard rail
|
100.0 |
LNFT |
20.00 |
2,000.00 |
18.00 |
1,800.00 |
20.00 |
2,000.00 |
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
200.0 |
LNFT |
57.00 |
11,400.00 |
52.00 |
10,400.00 |
55.00 |
11,000.00 |
|
|
| 704-11-B |
guard rail end treatment (tangent)
|
8   |
EACH |
2,500.00 |
20,000.00 |
2,300.00 |
18,400.00 |
2,400.00 |
19,200.00 |
|
|
| 707-04 |
asphaltic curb
|
80.0 |
LNFT |
48.00 |
3,840.00 |
100.00 |
8,000.00 |
30.00 |
2,400.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
20,000.00 |
20,000.00 |
100,000.00 |
100,000.00 |
120,000.00 |
120,000.00 |
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
11.259 |
MILE |
135.00 |
1,519.97 |
200.00 |
2,251.80 |
350.00 |
3,940.65 |
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
4.239 |
MILE |
300.00 |
1,271.70 |
0.01 |
0.04 |
50.00 |
211.95 |
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
40.232 |
MILE |
450.00 |
18,104.40 |
0.01 |
0.40 |
100.00 |
4,023.20 |
|
|
| 717-01 |
seeding
|
113   |
LB |
11.00 |
1,243.00 |
10.00 |
1,130.00 |
11.00 |
1,243.00 |
|
|
| 718-01 |
fertilizer
|
3,760   |
LB |
0.50 |
1,880.00 |
0.40 |
1,504.00 |
0.50 |
1,880.00 |
|
|
| 722-01 |
project site laboratory
|
1   |
EACH |
6,000.00 |
6,000.00 |
3,000.00 |
3,000.00 |
20,000.00 |
20,000.00 |
|
|
| 726-01 |
bedding material
|
5.3 |
CUYD |
225.00 |
1,192.50 |
175.00 |
927.50 |
90.00 |
477.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
75,000.00 |
75,000.00 |
105,000.00 |
105,000.00 |
80,000.00 |
80,000.00 |
|
|
| 729-16-B |
object marker assembly (type 2)
|
2   |
EACH |
70.00 |
140.00 |
62.00 |
124.00 |
75.00 |
150.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
8   |
EACH |
75.00 |
600.00 |
72.00 |
576.00 |
75.00 |
600.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
887   |
EACH |
5.50 |
4,878.50 |
4.50 |
3,991.50 |
5.00 |
4,435.00 |
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
587   |
LNFT |
0.80 |
469.60 |
1.00 |
587.00 |
1.00 |
587.00 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
367   |
LNFT |
2.25 |
825.75 |
3.00 |
1,101.00 |
2.25 |
825.75 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
13.399 |
MILE |
2,600.00 |
34,837.40 |
2,150.00 |
28,807.85 |
2,500.00 |
33,497.50 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
1.402 |
MILE |
750.00 |
1,051.50 |
800.00 |
1,121.60 |
725.00 |
1,016.45 |
|
|
| 735-01 |
mailboxes
|
17   |
EACH |
1.00 |
17.00 |
1.00 |
17.00 |
50.00 |
850.00 |
|
|
| 735-02 |
mailbox supports (single)
|
15   |
EACH |
150.00 |
2,250.00 |
150.00 |
2,250.00 |
150.00 |
2,250.00 |
|
|
| 735-03 |
mailbox supports (double)
|
2   |
EACH |
200.00 |
400.00 |
185.00 |
370.00 |
200.00 |
400.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
9,000.00 |
9,000.00 |
6,000.00 |
6,000.00 |
15,000.00 |
15,000.00 |
|
|
| S-001 |
cleaning existing ditches
|
50   |
LNFT |
12.00 |
600.00 |
125.00 |
6,250.00 |
25.00 |
1,250.00 |
|
|
| S-002 |
saw cutting
|
110   |
INFT |
12.00 |
1,320.00 |
5.00 |
550.00 |
7.00 |
770.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,799,931.27 |
|
1,997,274.46 |
|
2,160,111.50 |
|
|
|