| Lead Project: 704-90-0039 |
| Parish: ST TAMMANY |
| Routes: |
| Description: DISTRICT 62 DEBRIS REMOVAL, REDUCTION, AND DISPOSAL |
| Type Const:
debris removal, reduction, and disposal
|
| Estimated Construction Cost: $151,250.00 |
|
| |
| Rank | License | Bidder | Construction Bid |
| 1 | 38508 |
DRC, INC. OF ALABAMA | $44,285.00 |
| 2 | 47154 |
NATCO, INC. OF TN | $60,723.00 |
| 3 | 16724 |
STRANCO, INC. | $112,503.00 |
| 4 | 15288 |
GULF SOUTH PILING & CONST., INC. | $132,850.00 |
| 5 | 45210 |
CERES ENVIRONMENTAL SERVICES,INC. | $133,500.00 |
| 6 | 43244 |
FMA INC | $144,125.00 |
| 7 | 16378 |
MCDONALD CONST. INC. OF SLIDELL | $174,750.00 |
| 8 | 38325 |
GREAT SOUTHERN DREDGING INC | $187,000.00 |
| 9 | 11625 |
PHILLIPS & JORDAN, INC | $62,426,250.00 |
|
| |
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - DRC, INC. OF ALABAMA |
- 2 - NATCO, INC. OF TN |
- 3 - STRANCO, INC. |
- 4 - GULF SOUTH PILING & CONST., INC. |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
FREE |
FREE |
2,500.00 |
2,500.00 |
1.50 |
1.50 |
29,400.00 |
29,400.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
FREE |
FREE |
5,293.00 |
5,293.00 |
1.50 |
1.50 |
13,200.00 |
13,200.00 |
| S-001 |
removal, reduction, and disposal of vegetative debris
|
1,000.0 |
CUYD |
11.34 |
11,340.00 |
12.49 |
12,490.00 |
19.50 |
19,500.00 |
16.00 |
16,000.00 |
| S-002 |
removal, reduction, and disposal of construction and
demolition debris |
1,000.0 |
CUYD |
12.89 |
12,890.00 |
13.49 |
13,490.00 |
26.00 |
26,000.00 |
16.00 |
16,000.00 |
| S-003 |
removal and disposal of household appliances and
hazardous waste |
750.0 |
CUYD |
1.82 |
1,365.00 |
15.00 |
11,250.00 |
55.00 |
41,250.00 |
65.00 |
48,750.00 |
| S-004 |
removal and disposal of stumps - 30" to 48" in
diameter |
25   |
EACH |
284.00 |
7,100.00 |
240.00 |
6,000.00 |
385.00 |
9,625.00 |
110.00 |
2,750.00 |
| S-005 |
removal and disposal of stumps - greater than 48" in
diameter |
25   |
EACH |
345.00 |
8,625.00 |
288.00 |
7,200.00 |
450.00 |
11,250.00 |
110.00 |
2,750.00 |
| S-006 |
removal and disposal of earthen, stone, and rock
debris |
250.0 |
CUYD |
11.86 |
2,965.00 |
10.00 |
2,500.00 |
19.50 |
4,875.00 |
16.00 |
4,000.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
44,285.00 |
|
60,723.00 |
|
112,503.00 |
|
132,850.00 |
|
| |
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 5 - CERES ENVIRONMENTAL SERVICES,INC. |
- 6 - FMA INC |
- 7 - MCDONALD CONST. INC. OF SLIDELL |
- 8 - GREAT SOUTHERN DREDGING INC |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
1,000.00 |
1,000.00 |
5,000.00 |
5,000.00 |
10,500.00 |
10,500.00 |
10,000.00 |
10,000.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
10,000.00 |
10,000.00 |
15,000.00 |
15,000.00 |
7,000.00 |
7,000.00 |
50,000.00 |
50,000.00 |
| S-001 |
removal, reduction, and disposal of vegetative debris
|
1,000.0 |
CUYD |
25.00 |
25,000.00 |
18.50 |
18,500.00 |
29.00 |
29,000.00 |
14.00 |
14,000.00 |
| S-002 |
removal, reduction, and disposal of construction and
demolition debris |
1,000.0 |
CUYD |
28.00 |
28,000.00 |
21.00 |
21,000.00 |
32.00 |
32,000.00 |
15.00 |
15,000.00 |
| S-003 |
removal and disposal of household appliances and
hazardous waste |
750.0 |
CUYD |
66.00 |
49,500.00 |
32.00 |
24,000.00 |
65.00 |
48,750.00 |
100.00 |
75,000.00 |
| S-004 |
removal and disposal of stumps - 30" to 48" in
diameter |
25   |
EACH |
200.00 |
5,000.00 |
1,120.00 |
28,000.00 |
500.00 |
12,500.00 |
400.00 |
10,000.00 |
| S-005 |
removal and disposal of stumps - greater than 48" in
diameter |
25   |
EACH |
300.00 |
7,500.00 |
1,120.00 |
28,000.00 |
1,200.00 |
30,000.00 |
400.00 |
10,000.00 |
| S-006 |
removal and disposal of earthen, stone, and rock
debris |
250.0 |
CUYD |
30.00 |
7,500.00 |
18.50 |
4,625.00 |
20.00 |
5,000.00 |
12.00 |
3,000.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
133,500.00 |
|
144,125.00 |
|
174,750.00 |
|
187,000.00 |
|
| |
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 9 - PHILLIPS & JORDAN, INC |
|
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
10,000.00 |
10,000.00 |
|
|
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
10,000.00 |
10,000.00 |
|
|
|
|
|
|
| S-001 |
removal, reduction, and disposal of vegetative debris
|
1,000.0 |
CUYD |
17,500.00 |
17,500,000.00 |
|
|
|
|
|
|
| S-002 |
removal, reduction, and disposal of construction and
demolition debris |
1,000.0 |
CUYD |
22,500.00 |
22,500,000.00 |
|
|
|
|
|
|
| S-003 |
removal and disposal of household appliances and
hazardous waste |
750.0 |
CUYD |
26,250.00 |
19,687,500.00 |
|
|
|
|
|
|
| S-004 |
removal and disposal of stumps - 30" to 48" in
diameter |
25   |
EACH |
12,500.00 |
312,500.00 |
|
|
|
|
|
|
| S-005 |
removal and disposal of stumps - greater than 48" in
diameter |
25   |
EACH |
21,250.00 |
531,250.00 |
|
|
|
|
|
|
| S-006 |
removal and disposal of earthen, stone, and rock
debris |
250.0 |
CUYD |
7,500.00 |
1,875,000.00 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
62,426,250.00 |
|
|
|
|
|
|
|