| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BENTON & BROWN, LLC. |
- 2 - BEST-YET BUILDERS, LLC |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-D |
removal of concrete walks & drives
|
20   |
SQYD |
40.00 |
800.00 |
10.00 |
200.00 |
|
|
|
|
| 202-02-E |
removal of concrete curbs
|
24.0 |
LNFT |
30.00 |
720.00 |
20.00 |
480.00 |
|
|
|
|
| 202-02-I |
removal of culvert pipe
|
503   |
LNFT |
1.00 |
503.00 |
25.00 |
12,575.00 |
|
|
|
|
| 203-06 |
excavation & embankment
|
lump |
LUMP |
6,000.00 |
6,000.00 |
25,000.00 |
25,000.00 |
|
|
|
|
| 203-08 |
borrow (vehicular measurement)
|
600   |
CUYD |
15.00 |
9,000.00 |
20.00 |
12,000.00 |
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
100   |
CUYD |
55.00 |
5,500.00 |
50.00 |
5,000.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
5,378.9 |
TON |
70.00 |
376,523.00 |
78.00 |
419,554.20 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
1,071.8 |
TON |
75.00 |
80,385.00 |
83.00 |
88,959.40 |
|
|
|
|
| 701-01-Q/S |
cross drain pipe (60" rcp/pcp or 72" cmp)
|
303   |
LNFT |
300.00 |
90,900.00 |
610.00 |
184,830.00 |
|
|
|
|
| 701-01-S/U |
cross drain pipe (72" rcp/pcp or 84" cmp)
|
200   |
LNFT |
400.00 |
80,000.00 |
730.00 |
146,000.00 |
|
|
|
|
| 701-08 |
relaying pipe
|
24   |
LNFT |
85.00 |
2,040.00 |
350.00 |
8,400.00 |
|
|
|
|
| 701-10-I |
reinforced concrete pipe (extension)(24")
|
8   |
LNFT |
110.00 |
880.00 |
125.00 |
1,000.00 |
|
|
|
|
| 701-15 |
concrete collar
|
3   |
EACH |
700.00 |
2,100.00 |
1,000.00 |
3,000.00 |
|
|
|
|
| 707-03 |
combination concrete curb & gutter
|
13.0 |
LNFT |
200.00 |
2,600.00 |
40.00 |
520.00 |
|
|
|
|
| 712-04 |
flexible revetment
|
295   |
SQYD |
72.00 |
21,240.00 |
75.00 |
22,125.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
29,000.00 |
29,000.00 |
10,000.00 |
10,000.00 |
|
|
|
|
| 713-03-C |
temporary pavement markings (8" width)
|
350   |
LNFT |
0.40 |
140.00 |
0.10 |
35.00 |
|
|
|
|
| 713-03-E |
temporary pavement markings (24" width)
|
68   |
LNFT |
1.00 |
68.00 |
0.10 |
6.80 |
|
|
|
|
| 713-03-F |
temporary pavement markings (8" width)(dash)
|
62   |
LNFT |
0.40 |
24.80 |
0.10 |
6.20 |
|
|
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
4.330 |
MILE |
330.00 |
1,428.90 |
850.00 |
3,680.50 |
|
|
|
|
| 713-04-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
3.530 |
MILE |
355.00 |
1,253.15 |
675.00 |
2,382.75 |
|
|
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
5.380 |
MILE |
655.00 |
3,523.90 |
0.10 |
0.54 |
|
|
|
|
| 713-06-A |
temporary pavement legends and symbols (arrow)
|
1   |
EACH |
55.00 |
55.00 |
55.00 |
55.00 |
|
|
|
|
| 713-06-B |
temporary pavement legends and symbols (double arrow)
|
1   |
EACH |
80.00 |
80.00 |
85.00 |
85.00 |
|
|
|
|
| 713-06-C |
temporary pavement legends and symbols (only)
|
1   |
EACH |
60.00 |
60.00 |
65.00 |
65.00 |
|
|
|
|
| 716-01-A |
mulch (vegetative)
|
5.26 |
ACRE |
1,450.00 |
7,627.00 |
850.00 |
4,471.00 |
|
|
|
|
| 724-01-A |
pavement patching (6" minimum thickness)
|
1,000   |
SQYD |
35.00 |
35,000.00 |
45.00 |
45,000.00 |
|
|
|
|
| 726-01 |
bedding material
|
200.0 |
CUYD |
1.00 |
200.00 |
60.00 |
12,000.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
30,000.00 |
30,000.00 |
100,000.00 |
100,000.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
14   |
EACH |
110.00 |
1,540.00 |
110.00 |
1,540.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
584   |
EACH |
5.75 |
3,358.00 |
6.50 |
3,796.00 |
|
|
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
350   |
LNFT |
1.00 |
350.00 |
1.00 |
350.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
92   |
LNFT |
4.50 |
414.00 |
4.35 |
400.20 |
|
|
|
|
| 732-01-F |
plastic pavement striping (8" width) (dash)
|
62   |
LNFT |
1.00 |
62.00 |
1.00 |
62.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
5.380 |
MILE |
2,770.00 |
14,902.60 |
2,655.00 |
14,283.90 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
1.181 |
MILE |
825.00 |
974.33 |
825.00 |
974.33 |
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
1   |
EACH |
200.00 |
200.00 |
195.00 |
195.00 |
|
|
|
|
| 732-04-B |
plastic pavement legends & symbols (double arrow)
|
1   |
EACH |
255.00 |
255.00 |
250.00 |
250.00 |
|
|
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
1   |
EACH |
225.00 |
225.00 |
225.00 |
225.00 |
|
|
|
|
| 735-01 |
mailboxes
|
35   |
EACH |
1.10 |
38.50 |
15.00 |
525.00 |
|
|
|
|
| 735-02 |
mailbox supports (single)
|
33   |
EACH |
160.00 |
5,280.00 |
150.00 |
4,950.00 |
|
|
|
|
| 735-03 |
mailbox supports (double)
|
1   |
EACH |
200.00 |
200.00 |
225.00 |
225.00 |
|
|
|
|
| 739-01 |
hydro-seeding
|
5.26 |
ACRE |
1,650.00 |
8,679.00 |
1,800.00 |
9,468.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
5,000.00 |
5,000.00 |
10,000.00 |
10,000.00 |
|
|
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
3,000.00 |
3,000.00 |
10,000.00 |
10,000.00 |
|
|
|
|
| S-001 |
cleaning existing ditches
|
120   |
LNFT |
7.00 |
840.00 |
20.00 |
2,400.00 |
|
|
|
|
| S-002 |
surface preparation
|
lump |
LUMP |
15,000.00 |
15,000.00 |
40,000.00 |
40,000.00 |
|
|
|
|
| S-003 |
saw cutting existing concrete drives (4" depth)
|
55   |
LNFT |
14.00 |
770.00 |
12.00 |
660.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
848,740.18 |
|
1,207,735.82 |
|
|
|
|
|