| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - T. L. WALLACE CONSTRUCTION, INC. |
- 2 - P.R. PARKER COMPANY INC |
- 3 - DREHER CONTRACTING, INC. |
- 4 - MISSOURI PETROLEUM PRODUCTS CO. LLC |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 507-01-A |
asphaltic surface treatment (1 application)
|
305,310   |
SQYD |
1.39 |
424,380.90 |
1.35 |
412,168.50 |
1.45 |
442,699.50 |
1.92 |
586,195.20 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
19,000.00 |
19,000.00 |
18,000.00 |
18,000.00 |
12,000.00 |
12,000.00 |
20,000.00 |
20,000.00 |
| 713-07-A |
temporary reflectorized raised pavement markers (tabs)
|
6,304   |
EACH |
1.00 |
6,304.00 |
1.00 |
6,304.00 |
1.25 |
7,880.00 |
1.00 |
6,304.00 |
| 724-01-B |
pavement patching (12" minimum thickness)
|
250   |
SQYD |
60.00 |
15,000.00 |
40.00 |
10,000.00 |
60.00 |
15,000.00 |
100.00 |
25,000.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
9,000.00 |
9,000.00 |
43,000.00 |
43,000.00 |
20,000.00 |
20,000.00 |
25,000.00 |
25,000.00 |
| 731-02 |
reflectorized raised pavement markers
|
3,152   |
EACH |
4.50 |
14,184.00 |
4.50 |
14,184.00 |
4.50 |
14,184.00 |
4.00 |
12,608.00 |
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
1   |
EACH |
150.00 |
150.00 |
150.00 |
150.00 |
300.00 |
300.00 |
250.00 |
250.00 |
| 732-04-C |
plastic pavement legends & symbols (only)
|
1   |
EACH |
150.00 |
150.00 |
150.00 |
150.00 |
300.00 |
300.00 |
250.00 |
250.00 |
| 737-01-A |
painted traffic striping (solid line)(4" width)
|
123.440 |
MILE |
550.00 |
67,892.00 |
550.00 |
67,892.00 |
660.00 |
81,470.40 |
600.00 |
74,064.00 |
| 737-02-A |
painted traffic striping (broken line)(4" width)
|
24.970 |
MILE |
300.00 |
7,491.00 |
300.00 |
7,491.00 |
350.00 |
8,739.50 |
300.00 |
7,491.00 |
| 737-03-C |
painted traffic striping (solid line)(8" width)
|
85   |
LNFT |
0.40 |
34.00 |
0.40 |
34.00 |
5.50 |
467.50 |
5.00 |
425.00 |
| 737-03-E |
painted traffic striping (solid line)(24" width)
|
174   |
LNFT |
1.20 |
208.80 |
1.20 |
208.80 |
6.50 |
1,131.00 |
6.00 |
1,044.00 |
| 744-01 |
traffic control management
|
lump |
LUMP |
5,000.00 |
5,000.00 |
1,000.00 |
1,000.00 |
3,500.00 |
3,500.00 |
1,000.00 |
1,000.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
568,794.70 |
|
580,582.30 |
|
607,671.90 |
|
759,631.20 |
|