| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - SHILOH CONTRACTORS, INC. |
- 2 - CONSTRUCTING SOLUTIONS LLC |
- 3 - BEN ALLEN, INC. |
- 4 - C W & W CONTRACTORS, INC. |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
11,000.00 |
11,000.00 |
15,000.00 |
15,000.00 |
10,000.00 |
10,000.00 |
10,000.00 |
10,000.00 |
| 202-02-I |
removal of debris
|
lump |
LUMP |
8,500.00 |
8,500.00 |
10,000.00 |
10,000.00 |
5,000.00 |
5,000.00 |
10,000.00 |
10,000.00 |
| 711-01-D |
riprap (55 lb, 18" thick)
|
205   |
SQYD |
80.00 |
16,400.00 |
80.00 |
16,400.00 |
125.00 |
25,625.00 |
100.00 |
20,500.00 |
| 711-04 |
geotextile fabric
|
205   |
SQYD |
3.00 |
615.00 |
6.00 |
1,230.00 |
3.00 |
615.00 |
3.00 |
615.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
3,000.00 |
3,000.00 |
10,000.00 |
10,000.00 |
5,000.00 |
5,000.00 |
10,000.00 |
10,000.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
40,800.00 |
40,800.00 |
35,000.00 |
35,000.00 |
25,000.00 |
25,000.00 |
20,000.00 |
20,000.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
1,500.00 |
1,500.00 |
5,000.00 |
5,000.00 |
3,500.00 |
3,500.00 |
5,000.00 |
5,000.00 |
| 804-01-B-01 |
precast concrete piles (14")(2 @ 75')
|
150   |
LNFT |
55.00 |
8,250.00 |
100.00 |
15,000.00 |
125.00 |
18,750.00 |
325.00 |
48,750.00 |
| S-101 |
remove and reinstall spans
|
2   |
EACH |
10,000.00 |
20,000.00 |
5,000.00 |
10,000.00 |
20,000.00 |
40,000.00 |
20,000.00 |
40,000.00 |
| S-102 |
reinforced concrete cap
|
1   |
EACH |
6,000.00 |
6,000.00 |
15,000.00 |
15,000.00 |
8,000.00 |
8,000.00 |
8,000.00 |
8,000.00 |
| S-103 |
tie rods
|
8   |
EACH |
50.00 |
400.00 |
200.00 |
1,600.00 |
500.00 |
4,000.00 |
1,000.00 |
8,000.00 |
| S-104 |
relaying existing riprap
|
lump |
LUMP |
5,350.00 |
5,350.00 |
10,000.00 |
10,000.00 |
20,000.00 |
20,000.00 |
4,000.00 |
4,000.00 |
| S-105 |
cleaning and resealing longitudinal and transverse
joints |
lump |
LUMP |
2,500.00 |
2,500.00 |
5,000.00 |
5,000.00 |
5,000.00 |
5,000.00 |
10,000.00 |
10,000.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
124,315.00 |
|
149,230.00 |
|
170,490.00 |
|
194,865.00 |
|
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 5 - GUINN BROTHERS, LLC. |
|
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
10,000.00 |
10,000.00 |
|
|
|
|
|
|
| 202-02-I |
removal of debris
|
lump |
LUMP |
10,000.00 |
10,000.00 |
|
|
|
|
|
|
| 711-01-D |
riprap (55 lb, 18" thick)
|
205   |
SQYD |
105.00 |
21,525.00 |
|
|
|
|
|
|
| 711-04 |
geotextile fabric
|
205   |
SQYD |
10.00 |
2,050.00 |
|
|
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
13,000.00 |
13,000.00 |
|
|
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
38,000.00 |
38,000.00 |
|
|
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
4,500.00 |
4,500.00 |
|
|
|
|
|
|
| 804-01-B-01 |
precast concrete piles (14")(2 @ 75')
|
150   |
LNFT |
168.00 |
25,200.00 |
|
|
|
|
|
|
| S-101 |
remove and reinstall spans
|
2   |
EACH |
25,000.00 |
50,000.00 |
|
|
|
|
|
|
| S-102 |
reinforced concrete cap
|
1   |
EACH |
12,500.00 |
12,500.00 |
|
|
|
|
|
|
| S-103 |
tie rods
|
8   |
EACH |
850.00 |
6,800.00 |
|
|
|
|
|
|
| S-104 |
relaying existing riprap
|
lump |
LUMP |
15,000.00 |
15,000.00 |
|
|
|
|
|
|
| S-105 |
cleaning and resealing longitudinal and transverse
joints |
lump |
LUMP |
12,000.00 |
12,000.00 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
220,575.00 |
|
|
|
|
|
|
|