Letting of 2/28/2007 LA DOTD Headquarters


REBID
go back
Go Back
DBE GOAL FED
Lead Project: 450-91-0150
Parish: CALCASIEU
Routes: LA 108, I-10
Description: LA 108 OVER I-10 BRIDGE REHABILITATION
Type Const: grading, class ii base course, portland cement concrete pavement, bridge rehabilitation,
and related work.
Estimated Construction Cost: $4,892,273.25
Maximum Number of Days Allowed for Construction: 470
Calculated Daily User Cost: $1,000.00
 
RankLicenseBidderConstruction Bid Bidder's Proposed
Contract Time
Total Bid
1 39462 DENTON-JAMES LLC $5,524,752.50 470 $5,994,752.50
2 00060 F. MILLER CONSTRUCTION LLC $5,927,503.37 470 $6,397,503.37
3 12312 GILCHRIST CONSTRUCTION CO. LLC $7,171,967.11 465 $7,636,967.11
 
Item Number Item Description Quantity Unit of Measure - 1 -
DENTON-JAMES LLC
- 2 -
F. MILLER CONSTRUCTION LLC
- 3 -
GILCHRIST CONSTRUCTION CO. LLC

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-02-A removal of bridges 2      EACH 200,000.00 400,000.00 188,000.00 376,000.00 200,000.00 400,000.00    
202-02-C removal of portland cement concrete pavement 586      SQYD 25.00 14,650.00 34.00 19,924.00 15.00 8,790.00    
202-02-E removal of concrete curbs 4,917.8    LNFT 6.00 29,506.80 11.00 54,095.80 5.00 24,589.00    
202-02-G removal of surfacing & stabilized base 3,611.5    SQYD 10.00 36,115.00 21.00 75,841.50 10.00 36,115.00    
202-02-H removal of guard rail 622      LNFT 5.00 3,110.00 6.00 3,732.00 15.00 9,330.00    
202-02-01 removal of abutment (median return, end dam and flares) lump      LUMP 20,000.00 20,000.00 13,000.00 13,000.00 24,000.00 24,000.00    
202-02-02 removal of concrete approach slabs 253.04   SQYD 35.00 8,856.40 52.00 13,158.08 30.00 7,591.20    
202-02-03 removal of catch basins 5      EACH 1,000.00 5,000.00 1,300.00 6,500.00 1,000.00 5,000.00    
202-02-04 removal of fascia mounted sign of bridge 3      EACH 2,500.00 7,500.00 600.00 1,800.00 5,000.00 15,000.00    
202-03-01 relocation of overhead cantilever sign (left of sta.
196+00.72)
1      EACH 2,500.00 2,500.00 14,000.00 14,000.00 45,000.00 45,000.00    
202-03-02 relocation of cb-06 (right of sta. 251+50.46 ramp "e") 1      EACH 3,000.00 3,000.00 1,100.00 1,100.00 12,000.00 12,000.00    
202-03-03 relocation of impact attenuator 1      EACH 3,500.00 3,500.00 4,000.00 4,000.00 4,000.00 4,000.00    
203-01 general excavation 4,469      CUYD 20.00 89,380.00 18.00 80,442.00 15.00 67,035.00    
203-04 embankment 3,161      CUYD 35.00 110,635.00 30.00 94,830.00 30.00 94,830.00    
204-06 temporary silt fencing 1,136      LNFT 2.50 2,840.00 2.60 2,953.60 4.00 4,544.00    
302-02-B class ii base course (8 1/2" thick) 359.3    SQYD 54.00 19,402.20 78.00 28,025.40 45.00 16,168.50    
302-02-D class ii base course (12" thick) 1,958.0    SQYD 60.00 117,480.00 60.00 117,480.00 45.00 88,110.00    
304-01 lime 16.43   TON 160.00 2,628.80 325.00 5,339.75 300.00 4,929.00    
304-04-D lime treatment (type d) (12" thick) 1,159      SQYD 6.00 6,954.00 35.00 40,565.00 6.00 6,954.00    
402-01 traffic maintenance aggregate (vehicular measurement) 500.0    CUYD 65.00 32,500.00 100.00 50,000.00 75.00 37,500.00    
601-01-G portland cement concrete pavement (8" thick) 284.6    SQYD 80.00 22,768.00 60.00 17,076.00 85.00 24,191.00    
601-01-K portland cement concrete pavement (10" thick) 1,561.4    SQYD 75.00 117,105.00 78.00 121,789.20 90.00 140,526.00    
601-03-C portland cement concrete shoulder (6" thick) 359.3    SQYD 56.00 20,120.80 52.00 18,683.60 65.00 23,354.50    
701-10-F reinforced concrete pipe (extension) (15" diameter) 8      LF 120.00 960.00 25.00 200.00 250.00 2,000.00    
701-15 concrete collar 1      EACH 700.00 700.00 120.00 120.00 1,500.00 1,500.00    
702-04-B adjusting catch basins 9      EACH 1,800.00 16,200.00 750.00 6,750.00 6,000.00 54,000.00    
704-03 blocked out guard rail 250.0    LNFT 20.00 5,000.00 64.00 16,000.00 22.00 5,500.00    
704-08-B guard rail transitions (double thrie beam) 150.0    LNFT 55.00 8,250.00 76.00 11,400.00 56.00 8,400.00    
704-11-A guard rail end treatment (flared) 2      EACH 2,200.00 4,400.00 2,200.00 4,400.00 2,300.00 4,600.00    
704-11-C guard rail end treatment (bi-directional) 2      EACH 4,200.00 8,400.00 4,200.00 8,400.00 4,400.00 8,800.00    
706-03-C incidental concrete paving (6" thick) 842.0    SQYD 60.00 50,520.00 28.00 23,576.00 90.00 75,780.00    
707-01 concrete curb 1,495.0    LNFT 10.00 14,950.00 13.00 19,435.00 10.00 14,950.00    
707-03 combination curb and gutter 675.5    LNFT 30.00 20,265.00 15.00 10,132.50 30.00 20,265.00    
707-04 asphaltic curb 173.0    LNFT 98.00 16,954.00 115.00 19,895.00 25.00 4,325.00    
711-01-B riprap (10 lb, 10" thick) 53      SQYD 120.00 6,360.00 38.00 2,014.00 100.00 5,300.00    
712-01-A concrete cast-in-place revetment (4" thick) 525      SQYD 56.00 29,400.00 38.00 19,950.00 80.00 42,000.00    
713-01 temporary signs & barricades lump      LUMP 200,000.00 200,000.00 200,000.00 200,000.00 100,000.00 100,000.00    
713-03-C temporary pavement markings (8" width) 311      LNFT 0.50 155.50 0.50 155.50 0.45 139.95    
713-03-E temporary pavement markings (24" width) 360      LNFT 1.40 504.00 1.60 576.00 1.50 540.00    
713-04-A-01 temporary pvmt. markings (broken line)(4" w)(4' l)
(type i removable)
1.061  MILE 4,000.00 4,244.00 3,540.00 3,755.94 355.00 376.66    
713-05-A-01 temporary pavement markings (solid line)(4" width)
(type i removable)
3.023  MILE 12,000.00 36,276.00 13,900.00 42,019.70 12,000.00 36,276.00    
713-06-A temporary pavement legends and symbols (arrow) 4      EACH 60.00 240.00 60.00 240.00 60.00 240.00    
713-06-C temporary pavement legends and symbols (only) 4      EACH 60.00 240.00 60.00 240.00 60.00 240.00    
713-07 temporary reflectorized raised pavement markers 400      EACH 5.00 2,000.00 6.00 2,400.00 6.00 2,400.00    
716-01-A mulch (vegetative) 3.60   ACRE 1,000.00 3,600.00 1,000.00 3,600.00 725.00 2,610.00    
720-01-B erosion control system, slope protection (type b) 162      SQYD 2.50 405.00 2.50 405.00 3.00 486.00    
722-01 project site laboratory 1      EACH 20,000.00 20,000.00 10,000.00 10,000.00 50,000.00 50,000.00    
724-02 pavement widening 5,516.8    SQYD 58.00 319,974.40 56.00 308,940.80 95.00 524,096.00    
725-02 temporary detour roads 1,302.2    SQYD 120.00 156,264.00 310.00 403,682.00 130.00 169,286.00    
727-01 mobilization lump      LUMP 550,000.00 550,000.00 402,000.00 402,000.00 700,000.00 700,000.00    
729-01-01 sign (type a)(r10-12) 5.0    SQFT 35.00 175.00 52.00 260.00 80.00 400.00    
729-01-02 sign (type a)(r3-1)(24" x 24") 4.0    SQFT 35.00 140.00 65.00 260.00 80.00 320.00    
729-01-03 sign (type a)(r3-5)(30" x 36") 15.0    SQFT 35.00 525.00 50.00 750.00 80.00 1,200.00    
729-13 mounting (bridge fascia mounted) 3      EACH 5,800.00 17,400.00 7,700.00 23,100.00 6,500.00 19,500.00    
729-16-C object marker assembly (type 3) 8      EACH 70.00 560.00 70.00 560.00 80.00 640.00    
731-02 reflectorized raised pavement markers 205      EACH 5.20 1,066.00 5.20 1,066.00 5.50 1,127.50    
732-01-C plastic pavement striping (8" width) 974      LNFT 0.90 876.60 1.00 974.00 1.00 974.00    
732-01-E plastic pavement striping (24" width) 441      LNFT 2.70 1,190.70 2.70 1,190.70 3.00 1,323.00    
732-02-A plastic pavement striping (solid line) (4" width) 1.924  MILE 2,650.00 5,098.60 2,600.00 5,002.40 2,700.00 5,194.80    
732-03-A plastic pavement striping (broken line)(4" width) 0.354  MILE 1,000.00 354.00 1,000.00 354.00 1,000.00 354.00    
732-05 removal of existing markings 0.874  MILE 5,700.00 4,981.80 5,000.00 4,370.00 6,000.00 5,244.00    
736-01 trenching and backfilling 445      LNFT 4.00 1,780.00 3.50 1,557.50 4.00 1,780.00    
736-03 jacked or bored conduit (3" p.e.c.) 155      LNFT 23.00 3,565.00 29.00 4,495.00 28.00 4,340.00    
736-04-01 signal support (30' steel strain pole) 2      EACH 6,000.00 12,000.00 9,000.00 18,000.00 10,000.00 20,000.00    
736-04-02 signal support (15' timber pole) 2      EACH 1,100.00 2,200.00 1,525.00 3,050.00 1,800.00 3,600.00    
736-05-01 signal head (3 section, r, y, g) 4      EACH 850.00 3,400.00 1,000.00 4,000.00 1,200.00 4,800.00    
736-05-02 signal head (3 section, r,lt y,lt g) 3      EACH 870.00 2,610.00 900.00 2,700.00 900.00 2,700.00    
736-05-03 signal head (5 section, r,y,g,lt y,lt g) 1      EACH 1,200.00 1,200.00 1,500.00 1,500.00 1,600.00 1,600.00    
736-06 signal service 1      EACH 1,800.00 1,800.00 1,800.00 1,800.00 1,900.00 1,900.00    
736-08 signal controller 1      EACH 20,000.00 20,000.00 19,760.00 19,760.00 20,000.00 20,000.00    
736-10-01 underground junction box 2      EACH 400.00 800.00 560.00 1,120.00 600.00 1,200.00    
736-10-02 underground junction box 7      EACH 700.00 4,900.00 670.00 4,690.00 700.00 4,900.00    
736-10-03 underground junction box 2      EACH 830.00 1,660.00 1,150.00 2,300.00 1,200.00 2,400.00    
736-11-01 conduit (2" p.e.c.) 390      LNFT 4.20 1,638.00 5.15 2,008.50 6.00 2,340.00    
736-11-02 conduit (3" p.e.c.) 250      LNFT 6.30 1,575.00 6.60 1,650.00 7.00 1,750.00    
736-12-01 conductor (6c, signal #14 awg) 510      LNFT 2.00 1,020.00 2.00 1,020.00 2.50 1,275.00    
736-12-02 conductor (10c, signal,#14 awg) 800      LNFT 2.60 2,080.00 2.50 2,000.00 3.00 2,400.00    
736-12-03 conductor (3c, signal,#6 awg, thhn/thwn) 615      LNFT 5.00 3,075.00 5.00 3,075.00 5.00 3,075.00    
739-01 hydro-seeding 3.60   ACRE 950.00 3,420.00 950.00 3,420.00 1,100.00 3,960.00    
740-01 construction layout lump      LUMP 250,000.00 250,000.00 100,000.00 100,000.00 200,000.00 200,000.00    
744-01 traffic control management lump      LUMP 82,000.00 82,000.00 100,000.00 100,000.00 200,000.00 200,000.00    
804-01-B precast concrete piles (14" diameter) 410      LNFT 170.00 69,700.00 170.00 69,700.00 100.00 41,000.00    
805-01-F class a concrete (bents) 75.11   CUYD 1,500.00 112,665.00 2,400.00 180,264.00 3,000.00 225,330.00    
805-03 class aa concrete 666.04   CUYD 750.00 499,530.00 1,100.00 732,644.00 1,500.00 999,060.00    
805-11 strip seal joints 546.00   LNFT 150.00 81,900.00 130.00 70,980.00 125.00 68,250.00    
806-01 deformed reinforcing steel 254,165      LB 1.00 254,165.00 0.90 228,748.50 1.00 254,165.00    
807-06 structural metalwork lump      LUMP 800,000.00 800,000.00 800,000.00 800,000.00 1,200,000.00 1,200,000.00    
810-01 concrete railing (type f-shaped pl2) 1,440.00   LNFT 56.00 80,640.00 75.00 108,000.00 90.00 129,600.00    
813-01 concrete approach slabs 362.92   SQYD 180.00 65,325.60 220.00 79,842.40 300.00 108,876.00    
814-01-D drilled shaft (36" diameter) 150.0    LNFT 400.00 60,000.00 130.00 19,500.00 1,000.00 150,000.00    
S-001 sawcutting 57,821      INFT 1.30 75,167.30 1.00 57,821.00 1.00 57,821.00    
S-002 dynamic message sign unit 4      EACH 20,000.00 80,000.00 24,000.00 96,000.00 26,000.00 104,000.00    
S-003 removal, storage and replacement of existing roadway
signs
lump      LUMP 10,000.00 10,000.00 8,000.00 8,000.00 40,000.00 40,000.00    
S-004 adjusting guard rail 425.0    LF 15.00 6,375.00 23.00 9,775.00 20.00 8,500.00    
S-005 pile protection 2      EACH 40,000.00 80,000.00 30,000.00 60,000.00 40,000.00 80,000.00    
S-006 relocation of electrical transformer and conduits (lt.
of sta. 201+80.69)
lump      LUMP 6,300.00 6,300.00 10,000.00 10,000.00 10,000.00 10,000.00    
S-101 removal and handling of existing girders,diaphragms &
guardrail.
lump      LUMP 170,000.00 170,000.00 240,000.00 240,000.00 80,000.00 80,000.00    
S-102 new anchor bolts (for deck joints) set in pre-drilled
holes on existing endwalls
48      EACH 90.00 4,320.00 105.00 5,040.00 200.00 9,600.00    
S-103 extension of existing anchor bolts (for girders) 192      EACH 70.00 13,440.00 61.00 11,712.00 100.00 19,200.00    
S-104 new anchor bolts (for girders) set in pre-drilled
holes on existing portions of bent caps
48      EACH 90.00 4,320.00 70.00 3,360.00 200.00 9,600.00    
S-105 risers built with non-shrink grout 36      EACH 300.00 10,800.00 360.00 12,960.00 350.00 12,600.00    
S-106 top flange treatment for re-used girders 92      EACH 100.00 9,200.00 650.00 59,800.00 600.00 55,200.00    
S-107 bottom flange treatment for re-used girders 92      EACH 500.00 46,000.00 725.00 66,700.00 600.00 55,200.00    
                       
 ITEM TOTAL (CONSTRUCTION BID)       5,524,752.50   5,927,503.37   7,171,967.11    
 NUMBER OF DAYS BID AT $1,000 PER DAY.       470,000.00   470,000.00   465,000.00    
 TOTAL BID       5,994,752.50   6,397,503.37   7,636,967.11    