Letting of 2/28/2007 LA DOTD Headquarters


READV
go back
Go Back
DBE GOAL FED
Lead Project: 417-01-0015
Parish: VERNON
Routes: LA 28
Description: LA 121 - LA 465
Type Const: grading, drainage structures, class ii base course, superpave asphaltic concrete
pavement,type ii girder span bridges and related work.
Estimated Construction Cost: $22,665,877.93
 
RankLicenseBidderConstruction Bid
1 12487 DIAMOND B CONSTRUCTION CO., L.L.C. $20,789,428.80
2 12312 GILCHRIST CONSTRUCTION CO. LLC $21,390,244.61
3 42076 AUSTIN BRIDGE & ROAD, LP $23,420,401.95
4 05789 D & J CONSTRUCTION CO., INC. $23,536,890.15
 
Item Number Item Description Quantity Unit of Measure - 1 -
DIAMOND B CONSTRUCTION CO., L.L.C.
- 2 -
GILCHRIST CONSTRUCTION CO. LLC
- 3 -
AUSTIN BRIDGE & ROAD, LP
- 4 -
D & J CONSTRUCTION CO., INC.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing and grubbing lump      lump 800,000.00 800,000.00 900,000.00 900,000.00 1,155,000.00 1,155,000.00 786,000.00 786,000.00
202-01 removal of structures & obstructions lump      lump 181,000.00 181,000.00 25,000.00 25,000.00 91,000.00 91,000.00 100,000.00 100,000.00
202-02-C removal of portland cement concrete pavement 3,055      sq m 6.00 18,330.00 8.00 24,440.00 20.00 61,100.00 12.00 36,660.00
202-02-D removal of concrete walks & drives 100      sq m 15.00 1,500.00 14.00 1,400.00 12.00 1,200.00 12.00 1,200.00
202-02-G removal of surfacing & stabilized base 10,221.6    sq m 6.00 61,329.60 4.50 45,997.20 15.00 153,324.00 9.00 91,994.40
202-02-H removal of guard rail 228      ln m 13.00 2,964.00 12.84 2,927.52 15.00 3,420.00 15.00 3,420.00
203-01 general excavation 278,049      cu m 4.00 1,112,196.00 2.93 814,683.57 5.00 1,390,245.00 3.50 973,171.50
203-02 drainage excavation 7,110      cu m 10.00 71,100.00 10.00 71,100.00 12.00 85,320.00 9.00 63,990.00
203-03 muck excavation 1,000      cu m 12.00 12,000.00 20.00 20,000.00 14.00 14,000.00 11.00 11,000.00
203-04 embankment 309,163      cu m 5.50 1,700,396.50 8.40 2,596,969.20 8.00 2,473,304.00 5.50 1,700,396.50
204-02 temporary hay or straw bales 1,000      ea 10.00 10,000.00 30.00 30,000.00 8.00 8,000.00 7.00 7,000.00
204-03 temporary slope drains 1,266      ln m 35.00 44,310.00 25.00 31,650.00 25.00 31,650.00 23.00 29,118.00
204-04 temporary sediment basins 2      ea 550.00 1,100.00 1,000.00 2,000.00 300.00 600.00 300.00 600.00
204-05-A temporary sediment check dams (hay) 451      ea 150.00 67,650.00 200.00 90,200.00 80.00 36,080.00 80.00 36,080.00
204-05-B temporary sediment check dams (stone) 26      ea 500.00 13,000.00 1,000.00 26,000.00 350.00 9,100.00 350.00 9,100.00
204-06 temporary silt fencing 5,610      ln m 7.00 39,270.00 10.00 56,100.00 6.00 33,660.00 6.00 33,660.00
204-07 temporary stone construction entrance 6      ea 1,500.00 9,000.00 3,000.00 18,000.00 3,000.00 18,000.00 2,400.00 14,400.00
302-01-01 class ii base course (stone or recycled pccp) 24.6    cu m 700.00 17,220.00 700.00 17,220.00 410.00 10,086.00 150.00 3,690.00
302-02-C-01 class ii base course (250 mm thick)(soil cement) 185,719.4    sq m 12.50 2,321,492.50 12.50 2,321,492.50 9.00 1,671,474.60 14.00 2,600,071.60
302-02-E-02 class ii base course (100 mm thick)(stone or recycled
pccp)
185,719.4    sq m 11.00 2,042,913.40 12.00 2,228,632.80 10.00 1,857,194.00 12.25 2,275,062.65
304-01 lime 1,152.75   Mg 172.00 198,273.00 1.00 1,152.75 195.00 224,786.25 125.00 144,093.75
304-04-D lime treatment (type d) (300 mm thick) 76,154      sq m 1.00 76,154.00 0.01 761.54 2.50 190,385.00 2.00 152,308.00
401-02 aggregate surface course (adjusted vehicular
measurement)
385.0    cu m 42.00 16,170.00 110.00 42,350.00 175.00 67,375.00 75.00 28,875.00
402-01 traffic maintenance aggregate (vehicular measurement) 2,000.0    cu m 80.00 160,000.00 30.00 60,000.00 60.00 120,000.00 60.00 120,000.00
502-01 superpave asphaltic concrete 45,133.3    Mg 70.00 3,159,331.00 75.00 3,384,997.50 100.00 4,513,330.00 90.00 4,061,997.00
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
10,296.4    Mg 90.00 926,676.00 100.00 1,029,640.00 105.00 1,081,122.00 110.00 1,132,604.00
701-01-G cross drain pipe (450 mm rcp/pcp) 539.5    ln m 250.00 134,875.00 200.00 107,900.00 150.00 80,925.00 160.00 86,320.00
701-01-I cross drain pipe (600 mm rcp/pcp) 294.0    ln m 295.00 86,730.00 250.00 73,500.00 200.00 58,800.00 220.00 64,680.00
701-01-K cross drain pipe (750 mm rcp/pcp) 58.0    ln m 405.00 23,490.00 300.00 17,400.00 250.00 14,500.00 275.00 15,950.00
701-01-M cross drain pipe (900 mm rcp/pcp) 301.0    ln m 450.00 135,450.00 400.00 120,400.00 300.00 90,300.00 325.00 97,825.00
701-01-O cross drain pipe (1200 mm rcp/pcp) 224.0    ln m 900.00 201,600.00 500.00 112,000.00 500.00 112,000.00 550.00 123,200.00
701-01-S cross drain pipe (1800 mm rcp/pcp) 583.0    ln m 1,300.00 757,900.00 960.00 559,680.00 1,300.00 757,900.00 1,275.00 743,325.00
701-02-J cross drain pipe arch (1500 mm equiv. rcpa) 132.0    ln m 950.00 125,400.00 850.00 112,200.00 850.00 112,200.00 900.00 118,800.00
701-05-G side drain pipe (450 mm) 213.0    ln m 250.00 53,250.00 200.00 42,600.00 150.00 31,950.00 160.00 34,080.00
701-05-G-01 side drain pipe (450 mm)(bridge drain) 31.5    ln m 250.00 7,875.00 340.00 10,710.00 150.00 4,725.00 160.00 5,040.00
701-05-I side drain pipe (600 mm) 142.0    ln m 295.00 41,890.00 290.00 41,180.00 200.00 28,400.00 220.00 31,240.00
701-10-I reinforced concrete pipe (extension)(600 mm) 300.1    ln m 400.00 120,040.00 310.00 93,031.00 420.00 126,042.00 450.00 135,045.00
701-10-K reinforced concrete pipe (extension)(750 mm) 32.9    ln m 500.00 16,450.00 315.00 10,363.50 600.00 19,740.00 600.00 19,740.00
701-10-M reinforced concrete pipe (extension)(900 mm) 64.5    ln m 565.00 36,442.50 390.00 25,155.00 655.00 42,247.50 700.00 45,150.00
701-10-N reinforced concrete pipe (extension)(1050 mm) 102.0    ln m 765.00 78,030.00 520.00 53,040.00 740.00 75,480.00 800.00 81,600.00
701-10-O reinforced concrete pipe (extension)(1200 mm) 204.3    ln m 945.00 193,063.50 600.00 122,580.00 820.00 167,526.00 850.00 173,655.00
701-11-I reinforced concrete pipe arch (extension)(600 mm
equiv.)
30.0    ln m 400.00 12,000.00 340.00 10,200.00 400.00 12,000.00 450.00 13,500.00
702-02-E manholes (r-cb-32) 1      ea 9,500.00 9,500.00 5,800.00 5,800.00 6,000.00 6,000.00 5,500.00 5,500.00
702-02-F manholes (mh-01) 1      ea 5,000.00 5,000.00 9,200.00 9,200.00 6,000.00 6,000.00 5,500.00 5,500.00
702-03-A catch basins (cb-01) 19      ea 4,000.00 76,000.00 2,500.00 47,500.00 2,600.00 49,400.00 3,000.00 57,000.00
702-03-B catch basins (cb-02) 11      ea 6,400.00 70,400.00 9,200.00 101,200.00 3,700.00 40,700.00 4,000.00 44,000.00
702-05-A cross drain end treatment (1 barrell, 450mm rcp) 2      ea 2,400.00 4,800.00 1,600.00 3,200.00 1,600.00 3,200.00 1,700.00 3,400.00
702-05-B cross drain end treatment (1 barrell, 600mm rcp) 9      ea 3,300.00 29,700.00 1,650.00 14,850.00 2,000.00 18,000.00 2,100.00 18,900.00
702-05-C cross drain end treatment (1 barrell, 750mm rcp) 2      ea 3,600.00 7,200.00 1,800.00 3,600.00 2,500.00 5,000.00 2,600.00 5,200.00
702-05-D cross drain end treatment (1 barrell, 900mm rcp) 8      ea 3,800.00 30,400.00 3,000.00 24,000.00 3,000.00 24,000.00 3,100.00 24,800.00
702-05-E cross drain end treatment (1 barrell, 1050mm rcp) 2      ea 4,200.00 8,400.00 3,300.00 6,600.00 3,500.00 7,000.00 3,600.00 7,200.00
702-05-F cross drain end treatment (1 barrell, 1200mm rcp) 8      ea 4,800.00 38,400.00 3,500.00 28,000.00 4,000.00 32,000.00 4,100.00 32,800.00
702-05-G cross drain end treatment (1 barrell, 1800mm rcp) 2      ea 5,600.00 11,200.00 7,000.00 14,000.00 6,500.00 13,000.00 7,000.00 14,000.00
702-05-H cross drain end treatment (2 barrell, 600mm rcp) 2      ea 6,700.00 13,400.00 3,000.00 6,000.00 3,800.00 7,600.00 4,000.00 8,000.00
702-05-I cross drain end treatment (2 barrell, 900mm rcp) 2      ea 4,500.00 9,000.00 5,300.00 10,600.00 4,500.00 9,000.00 5,000.00 10,000.00
702-05-J cross drain end treatment (2 barrell, 1200mm rcp) 1      ea 5,800.00 5,800.00 6,400.00 6,400.00 6,000.00 6,000.00 6,500.00 6,500.00
702-05-K cross drain end treatment (2 barrell, 1500mm equiv.
rcpa)
2      ea 6,700.00 13,400.00 7,200.00 14,400.00 7,000.00 14,000.00 7,500.00 15,000.00
702-05-L cross drain end treatment (3 barrell, 1800mm rcp) 2      ea 8,700.00 17,400.00 11,300.00 22,600.00 15,000.00 30,000.00 15,500.00 31,000.00
702-05-M cross drain end treatment (4 barrell, 1800mm rcp) 2      ea 13,500.00 27,000.00 12,300.00 24,600.00 19,000.00 38,000.00 20,000.00 40,000.00
702-08-A side drain safety end (type 1) 20      ea 1,600.00 32,000.00 2,400.00 48,000.00 1,000.00 20,000.00 1,100.00 22,000.00
704-03 blocked out guard rail 461.02   ln m 62.00 28,583.24 60.00 27,661.20 58.00 26,739.16 61.00 28,122.22
704-08-B guard rail transitions (double thrie beam) 76.20   ln m 190.00 14,478.00 190.00 14,478.00 180.00 13,716.00 161.00 12,268.20
704-11-A guard rail end treatment (flared) 10      ea 2,200.00 22,000.00 2,200.00 22,000.00 2,000.00 20,000.00 2,250.00 22,500.00
705-01 barbed wire fence 500      ln m 18.00 9,000.00 17.00 8,500.00 17.00 8,500.00 17.00 8,500.00
705-02 combination mesh & barbed wire fence 798      ln m 22.00 17,556.00 20.00 15,960.00 20.00 15,960.00 21.00 16,758.00
705-04 single swinging driveway gates 5      ea 250.00 1,250.00 570.00 2,850.00 800.00 4,000.00 300.00 1,500.00
705-05 double swinging driveway gates 5      dbgt 550.00 2,750.00 800.00 4,000.00 1,300.00 6,500.00 550.00 2,750.00
708-01 right-of-way monument 6      ea 105.00 630.00 325.00 1,950.00 150.00 900.00 500.00 3,000.00
708-02 right-of-way monument witness post 6      ea 105.00 630.00 325.00 1,950.00 40.00 240.00 300.00 1,800.00
709-01 steel cattle guard 2      ea 4,500.00 9,000.00 15,000.00 30,000.00 4,000.00 8,000.00 4,500.00 9,000.00
711-01-D riprap (25 kg, 450 mm) 3,252      sq m 65.00 211,380.00 75.00 243,900.00 75.00 243,900.00 90.00 292,680.00
711-04 geotextile fabric 1,462      sq m 4.00 5,848.00 3.00 4,386.00 5.00 7,310.00 4.00 5,848.00
712-01-C concrete cast-in-place revetment (150 mm thick) 128.0    sq m 100.00 12,800.00 80.00 10,240.00 135.00 17,280.00 80.00 10,240.00
713-01 temporary signs & barricades lump      lump 90,000.00 90,000.00 180,000.00 180,000.00 125,000.00 125,000.00 750,000.00 750,000.00
713-04-B temporary pavement markings (broken line)(100 mm width)
(3.0 m length)
13.007  km 675.00 8,779.73 680.00 8,844.76 600.00 7,804.20 175.00 2,276.23
713-04-B-01 temporary pvmt. markings (broken line)(100 mm w)(3.0 m
l)(type i removable)
0.750  km 2,750.00 2,062.50 2,700.00 2,025.00 2,500.00 1,875.00 7,500.00 5,625.00
713-05-A temporary pavement markings (solid line)(100 mm width) 13.007  km 400.00 5,202.80 420.00 5,462.94 370.00 4,812.59 400.00 5,202.80
713-05-A-01 temporary pavement markings (solid line)(100 mm width)
(type i removable)
0.750  km 10,000.00 7,500.00 10,000.00 7,500.00 9,500.00 7,125.00 9,000.00 6,750.00
716-01-A mulch (vegetative) 83.0    hctr 1,400.00 116,200.00 2,200.00 182,600.00 1,900.00 157,700.00 2,000.00 166,000.00
717-01 seeding 2,800      kg 19.00 53,200.00 20.00 56,000.00 12.00 33,600.00 12.50 35,000.00
718-01 fertilizer 93,334      kg 0.60 56,000.40 0.70 65,333.80 0.50 46,667.00 0.60 56,000.40
720-01-A erosion control system, slope protection (type a) 62,993      sq m 1.50 94,489.50 1.40 88,190.20 1.60 100,788.80 1.50 94,489.50
720-01-C erosion control system, flexible channel liner (type c) 6,385      sq m 1.50 9,577.50 2.20 14,047.00 2.20 14,047.00 2.00 12,770.00
720-01-D erosion control system, flexible channel liner (type d) 9,063      sq m 3.25 29,454.75 2.39 21,660.57 2.20 19,938.60 2.00 18,126.00
720-01-E erosion control system, flexible channel liner (type e) 100      sq m 3.25 325.00 4.00 400.00 3.30 330.00 3.00 300.00
720-01-F erosion control system, flexible channel liner (type f) 100      sq m 5.50 550.00 5.00 500.00 3.30 330.00 3.00 300.00
722-02 project site laboratory (equipped) 1      ea 35,000.00 35,000.00 60,000.00 60,000.00 20,000.00 20,000.00 35,000.00 35,000.00
724-01-B pavement patching (300 mm minimum thickness) 2,527      sq m 105.00 265,335.00 125.00 315,875.00 150.00 379,050.00 125.00 315,875.00
725-01 temporary detour roads 79.2    ln m 500.00 39,600.00 650.00 51,480.00 850.00 67,320.00 600.00 47,520.00
726-01 bedding material 1,847.9    cu m 110.00 203,269.00 105.00 194,029.50 150.00 277,185.00 100.00 184,790.00
727-01 mobilization lump      lump 1,900,000.00 1,900,000.00 2,100,000.00 2,100,000.00 2,300,000.00 2,300,000.00 2,300,000.00 2,300,000.00
729-16-C object marker assembly (type 3) 10      ea 77.00 770.00 80.00 800.00 70.00 700.00 75.00 750.00
729-19-B dead end road installation (type b) 2      ea 1,400.00 2,800.00 1,400.00 2,800.00 1,500.00 3,000.00 1,500.00 3,000.00
731-02 reflectorized raised pavement markers 2,576      ea 5.00 12,880.00 5.00 12,880.00 4.50 11,592.00 5.50 14,168.00
732-01-C plastic pavement striping (200 mm width) 440      ln m 1.10 484.00 1.14 501.60 1.00 440.00 17.00 7,480.00
732-01-E plastic pavement striping (600 mm width) 412      ln m 3.30 1,359.60 3.40 1,400.80 3.00 1,236.00 21.00 8,652.00
732-02-A plastic pavement striping (solid line)(100 mm width) 53.994  km 1,500.00 80,991.00 1,500.00 80,991.00 1,350.00 72,891.90 1,550.00 83,690.70
732-03-A plastic pavement striping (broken line)(100 mm width) 26.725  km 475.00 12,694.38 500.00 13,362.50 450.00 12,026.25 600.00 16,035.00
732-04-A plastic pavement legends & symbols (arrow) 22      ea 150.00 3,300.00 160.00 3,520.00 150.00 3,300.00 350.00 7,700.00
732-04-C plastic pavement legends & symbols (only) 22      ea 150.00 3,300.00 160.00 3,520.00 150.00 3,300.00 350.00 7,700.00
732-05 removal of existing markings 13.007  km 2,500.00 32,517.50 2,500.00 32,517.50 2,300.00 29,916.10 2,100.00 27,314.70
735-01 mailboxes 10      ea 1.00 10.00 20.00 200.00 1.00 10.00 30.00 300.00
735-02 mailbox supports (single) 10      ea 185.00 1,850.00 200.00 2,000.00 170.00 1,700.00 175.00 1,750.00
735-03 mailbox supports (double) 2      ea 215.00 430.00 300.00 600.00 190.00 380.00 225.00 450.00
735-04 mailbox supports (multiple) 2      ea 450.00 900.00 500.00 1,000.00 390.00 780.00 350.00 700.00
740-01 construction layout lump      lump 250,000.00 250,000.00 350,000.00 350,000.00 323,700.00 323,700.00 550,000.00 550,000.00
744-01 traffic control management lump      lump 35,000.00 35,000.00 100,000.00 100,000.00 30,000.00 30,000.00 200,000.00 200,000.00
804-01-B precast concrete piles (350 mm) 684.0    ln m 195.00 133,380.00 140.00 95,760.00 180.00 123,120.00 200.00 136,800.00
804-01-F precast concrete piles (600 mm) 574.2    ln m 400.00 229,680.00 270.00 155,034.00 300.00 172,260.00 500.00 287,100.00
804-12 loading permanent piles 2      ea 20,000.00 40,000.00 100.00 200.00 40,000.00 80,000.00 100.00 200.00
804-17 dynamic monitoring 2      ea 1,710.00 3,420.00 100.00 200.00 4,000.00 8,000.00 2,500.00 5,000.00
805-01-B class a concrete (bents)(box culvert headwalls) 5.78   cu m 1,600.00 9,248.00 2,000.00 11,560.00 1,600.00 9,248.00 2,100.00 12,138.00
805-01-F class a concrete (bents) 135.20   cu m 950.00 128,440.00 900.00 121,680.00 900.00 121,680.00 1,200.00 162,240.00
805-03 class aa concrete 361.82   cu m 845.00 305,737.90 1,000.00 361,820.00 1,000.00 361,820.00 900.00 325,638.00
805-08-B precast-prestressed concrete girders (type ii) 606.00   ln m 400.00 242,400.00 260.00 157,560.00 400.00 242,400.00 350.00 212,100.00
805-11 strip seal joints 60.00   ln m 585.00 35,100.00 300.00 18,000.00 700.00 42,000.00 600.00 36,000.00
805-12-I reinforced concrete box culverts (1500 mm x 1500 mm) 39.40   ln m 1,900.00 74,860.00 1,700.00 66,980.00 1,200.00 47,280.00 1,300.00 51,220.00
806-01 deformed reinforcing steel 74,186      kg 2.00 148,372.00 1.56 115,730.16 2.00 148,372.00 2.00 148,372.00
807-06 structural metalwork lump      lump 4,500.00 4,500.00 10,000.00 10,000.00 30,000.00 30,000.00 7,000.00 7,000.00
810-01 concrete railing (barrier) 244.80   ln m 215.00 52,632.00 210.00 51,408.00 275.00 67,320.00 260.00 63,648.00
813-01 concrete approach slabs 576.00   sq m 300.00 172,800.00 190.00 109,440.00 250.00 144,000.00 210.00 120,960.00
S-002 rumble strips(ground-in) 52.3    km 330.00 17,259.00 370.00 19,351.00 400.00 20,920.00 500.00 26,150.00
S-101 dynamic analysis 2      ea 1,500.00 3,000.00 1,200.00 2,400.00 3,000.00 6,000.00 2,600.00 5,200.00
                       
 CONTRACTOR TOTAL       20,789,428.80   21,390,244.61   23,420,401.95   23,536,890.15