Letting of 2/28/2007 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 165-01-0021
Parish: FRANKLIN
Routes: LA 562
Description: JCT LA 875 - TURKEY CREEK BRIDGE
Type Const: grading, lime treatment, cement treated base course, drainage structures, cold planing
asphaltic pavement, superpace asphaltic concrete pavement and related work.
Estimated Construction Cost: $3,666,446.38
 
RankLicenseBidderConstruction Bid
1 12312 GILCHRIST CONSTRUCTION CO. LLC $3,041,789.83
2 05789 D & J CONSTRUCTION CO., INC. $3,104,958.44
3 12487 DIAMOND B CONSTRUCTION CO., L.L.C. $3,149,596.36
 
Item Number Item Description Quantity Unit of Measure - 1 -
GILCHRIST CONSTRUCTION CO. LLC
- 2 -
D & J CONSTRUCTION CO., INC.
- 3 -
DIAMOND B CONSTRUCTION CO., L.L.C.

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 5,000.00 5,000.00 40,000.00 40,000.00 20,000.00 20,000.00    
202-02 removal of structures and obstructions 1      EACH 5,000.00 5,000.00 25,000.00 25,000.00 10,000.00 10,000.00    
202-02-H removal of guard rail 512      LNFT 6.00 3,072.00 12.00 6,144.00 7.00 3,584.00    
203-02 drainage excavation 149      CUYD 20.00 2,980.00 28.00 4,172.00 19.00 2,831.00    
203-08 borrow (vehicular measurement) 3,264      CUYD 20.00 65,280.00 18.00 58,752.00 16.00 52,224.00    
203-08-A borrow (vehicular meas.)(selected soils) 327      CUYD 40.00 13,080.00 18.00 5,886.00 19.00 6,213.00    
304-01 lime 152.59   TON 140.00 21,362.60 160.00 24,414.40 165.00 25,177.35    
304-04-D lime treatment (type d) (12" thick) 9,688      SQYD 3.00 29,064.00 4.00 38,752.00 1.00 9,688.00    
308-01-A in-place cement treated base course (12" thick) 85,314      SQYD 7.50 639,855.00 8.25 703,840.50 7.50 639,855.00    
401-02 aggregate surface course (adjusted vehicular
measurement)
398      CUYD 42.00 16,716.00 40.00 15,920.00 24.00 9,552.00    
502-01 superpave asphaltic concrete 17,137.1    TON 88.00 1,508,064.80 82.00 1,405,242.20 88.00 1,508,064.80    
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
1,159.9    TON 130.00 150,787.00 82.00 95,111.80 135.00 156,586.50    
509-01 cold planing asphaltic pavement 74,521      SQYD 1.70 126,685.70 2.00 149,042.00 2.50 186,302.50    
509-02 contractor retained reclaimed asphaltic pavement - 5,677      CUYD 0.01 - 56.77 0.01 - 56.77 0.10 - 567.70    
701-01-Q cross drain pipe (60" cmp) 160      LNFT 300.00 48,000.00 225.00 36,000.00 324.00 51,840.00    
701-02-H cross drain pipe arch (48" equiv. cmpa) 148      LNFT 295.00 43,660.00 200.00 29,600.00 233.00 34,484.00    
701-05-K side drain pipe (30") 150      LNFT 75.00 11,250.00 185.00 27,750.00 155.00 23,250.00    
701-08 relaying pipe 4      LNFT 200.00 800.00 500.00 2,000.00 325.00 1,300.00    
701-10-I reinforced concrete pipe (extension)(24") 16      LNFT 225.00 3,600.00 175.00 2,800.00 130.00 2,080.00    
701-15 concrete collar 3      EACH 800.00 2,400.00 1,250.00 3,750.00 1,300.00 3,900.00    
704-01-A guard rail (single thrie beam)(3'-1 1/2" post spacing) 200.0    LNFT 40.00 8,000.00 50.00 10,000.00 50.00 10,000.00    
704-01-B guard rail (single thrie beam)(6'-3" post spacing) 306.0    LNFT 52.00 15,912.00 55.00 16,830.00 60.00 18,360.00    
704-03 blocked out guard rail 125.0    LNFT 20.00 2,500.00 21.00 2,625.00 25.00 3,125.00    
704-11-B guard rail end treatment (tangent) 8      EACH 2,500.00 20,000.00 2,800.00 22,400.00 3,000.00 24,000.00    
705-09 rebuilt fence 100      LNFT 22.00 2,200.00 22.00 2,200.00 30.00 3,000.00    
713-01 temporary signs & barricades lump      LUMP 12,000.00 12,000.00 85,000.00 85,000.00 20,000.00 20,000.00    
713-04-A temporary pavement markings (broken line)(4" width)(4'
length)
12.702  MILE 500.00 6,351.00 250.00 3,175.50 167.00 2,121.23    
713-04-B temporary pavement markings (broken line)(4" width)
(10' length)
9.971  MILE 500.00 4,985.50 1.00 9.97 388.00 3,868.75    
713-05-A temporary pavement markings (solid line)(4" width) 32.839  MILE 850.00 27,913.15 1.00 32.84 775.00 25,450.23    
716-01-A mulch (vegetative) 0.93   ACRE 2,500.00 2,325.00 1,550.00 1,441.50 1,700.00 1,581.00    
717-01 seeding 28      LB 20.00 560.00 12.00 336.00 13.00 364.00    
718-01 fertilizer 930      LB 1.20 1,116.00 1.00 930.00 1.00 930.00    
722-01 project site laboratory 1      EACH 12,000.00 12,000.00 15,000.00 15,000.00 3,000.00 3,000.00    
726-01 bedding material 137.1    CUYD 85.00 11,653.50 90.00 12,339.00 100.00 13,710.00    
727-01 mobilization lump      LUMP 70,000.00 70,000.00 125,000.00 125,000.00 175,000.00 175,000.00    
729-16-C object marker assembly (type 3) 16      EACH 75.00 1,200.00 75.00 1,200.00 90.00 1,440.00    
731-02 reflectorized raised pavement markers 841      EACH 5.50 4,625.50 6.25 5,256.25 6.00 5,046.00    
732-02-A plastic pavement striping (solid line) (4" width) 16.419  MILE 2,400.00 39,405.60 2,750.00 45,152.25 2,800.00 45,973.20    
732-03-A plastic pavement striping (broken line)(4" width) 4.985  MILE 850.00 4,237.25 1,200.00 5,982.00 900.00 4,486.50    
735-01 mailboxes 27      EACH 50.00 1,350.00 1.00 27.00 20.00 540.00    
735-02 mailbox supports (single) 15      EACH 160.00 2,400.00 140.00 2,100.00 150.00 2,250.00    
735-03 mailbox supports (double) 3      EACH 225.00 675.00 195.00 585.00 250.00 750.00    
735-04 mailbox supports (multiple) 2      EACH 250.00 500.00 340.00 680.00 350.00 700.00    
740-01 construction layout lump      LUMP 12,000.00 12,000.00 35,000.00 35,000.00 10,000.00 10,000.00    
744-01 traffic control management lump      LUMP 75,000.00 75,000.00 30,000.00 30,000.00 20,000.00 20,000.00    
S-002 clean and seal existing bridge deck joints 1,256      LNFT 5.00 6,280.00 6.00 7,536.00 6.00 7,536.00    
                       
 CONTRACTOR TOTAL       3,041,789.83   3,104,958.44   3,149,596.36    