| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BEST-YET BUILDERS, LLC |
- 2 - BENTON & BROWN, LLC. |
- 3 - MADDEN CONTRACTING CO., INC. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-H |
removal of guard rail
|
229   |
LNFT |
7.00 |
1,603.00 |
3.50 |
801.50 |
5.00 |
1,145.00 |
|
|
| 203-08 |
borrow (vehicular measurement)
|
5,000   |
CUYD |
10.50 |
52,500.00 |
16.00 |
80,000.00 |
12.50 |
62,500.00 |
|
|
| 308-01-A |
in-place cement treated base course (12" thick)
|
25,385.0 |
SQYD |
8.00 |
203,080.00 |
7.50 |
190,387.50 |
6.90 |
175,156.50 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
100   |
CUYD |
40.00 |
4,000.00 |
50.00 |
5,000.00 |
30.00 |
3,000.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
7,916.6 |
TON |
77.00 |
609,578.20 |
70.00 |
554,162.00 |
78.50 |
621,453.10 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
2,100.0 |
TON |
80.00 |
168,000.00 |
70.00 |
147,000.00 |
110.00 |
231,000.00 |
|
|
| 509-01-A |
cold planing asphaltic pavement (2" average depth)
|
9,635   |
SQYD |
1.40 |
13,489.00 |
2.20 |
21,197.00 |
2.25 |
21,678.75 |
|
|
| 509-01-B |
cold planing asphaltic pavement (1 1/2" maximum depth)
|
10,800   |
SQYD |
1.35 |
14,580.00 |
2.20 |
23,760.00 |
2.25 |
24,300.00 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 339   |
CUYD |
0.01 |
- 3.39 |
1.00 |
- 339.00 |
1.00 |
- 339.00 |
|
|
| 701-08 |
relaying pipe
|
8   |
LNFT |
100.00 |
800.00 |
335.00 |
2,680.00 |
150.00 |
1,200.00 |
|
|
| 701-15 |
concrete collar
|
4   |
EACH |
950.00 |
3,800.00 |
620.00 |
2,480.00 |
1,000.00 |
4,000.00 |
|
|
| 704-01-A |
guard rail (single thrie beam)(3'-1 1/2" post spacing)
|
100.0 |
LNFT |
36.00 |
3,600.00 |
55.00 |
5,500.00 |
33.00 |
3,300.00 |
|
|
| 704-03 |
blocked out guard rail
|
56.3 |
LNFT |
20.00 |
1,126.00 |
28.00 |
1,576.40 |
19.80 |
1,114.74 |
|
|
| 704-11-A |
guard rail end treatment (flared)
|
2   |
EACH |
2,450.00 |
4,900.00 |
2,500.00 |
5,000.00 |
2,200.00 |
4,400.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
10,000.00 |
10,000.00 |
65,000.00 |
65,000.00 |
95,000.00 |
95,000.00 |
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
6.000 |
MILE |
425.00 |
2,550.00 |
345.00 |
2,070.00 |
325.00 |
1,950.00 |
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
24.000 |
MILE |
880.00 |
21,120.00 |
1.00 |
24.00 |
770.00 |
18,480.00 |
|
|
| 713-06-A |
temporary pavement legends and symbols (arrow)
|
1   |
EACH |
60.00 |
60.00 |
1.00 |
1.00 |
88.00 |
88.00 |
|
|
| 713-06-C |
temporary pavement legends and symbols (only)
|
1   |
EACH |
60.00 |
60.00 |
1.00 |
1.00 |
88.00 |
88.00 |
|
|
| 716-01-A |
mulch (vegetative)
|
5.00 |
ACRE |
1,100.00 |
5,500.00 |
925.00 |
4,625.00 |
1,540.00 |
7,700.00 |
|
|
| 722-02 |
project site laboratory (equipped)
|
1   |
EACH |
10,000.00 |
10,000.00 |
4,000.00 |
4,000.00 |
10,000.00 |
10,000.00 |
|
|
| 724-01-A |
pavement patching (6" minimum thickness)
|
340   |
SQYD |
60.00 |
20,400.00 |
45.00 |
15,300.00 |
65.00 |
22,100.00 |
|
|
| 724-03 |
pavement joint repair
|
6.0 |
TON |
85.00 |
510.00 |
800.00 |
4,800.00 |
500.00 |
3,000.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
50,000.00 |
50,000.00 |
65,000.00 |
65,000.00 |
95,000.00 |
95,000.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
2   |
EACH |
85.00 |
170.00 |
115.00 |
230.00 |
82.50 |
165.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
396   |
EACH |
5.50 |
2,178.00 |
6.00 |
2,376.00 |
5.50 |
2,178.00 |
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
687   |
LNFT |
1.15 |
790.05 |
1.10 |
755.70 |
1.10 |
755.70 |
|
|
| 732-01-D |
plastic pavement striping (12" width)
|
220   |
LNFT |
3.25 |
715.00 |
3.10 |
682.00 |
1.65 |
363.00 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
86   |
LNFT |
6.50 |
559.00 |
6.25 |
537.50 |
3.30 |
283.80 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
12.000 |
MILE |
2,565.00 |
30,780.00 |
2,500.00 |
30,000.00 |
2,750.00 |
33,000.00 |
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
1   |
EACH |
185.00 |
185.00 |
155.00 |
155.00 |
192.50 |
192.50 |
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
1   |
EACH |
205.00 |
205.00 |
165.00 |
165.00 |
192.50 |
192.50 |
|
|
| 735-01 |
mailboxes
|
40   |
EACH |
10.00 |
400.00 |
1.00 |
40.00 |
1.10 |
44.00 |
|
|
| 735-02 |
mailbox supports (single)
|
40   |
EACH |
130.00 |
5,200.00 |
160.00 |
6,400.00 |
140.80 |
5,632.00 |
|
|
| 739-01 |
hydro-seeding
|
5.00 |
ACRE |
1,575.00 |
7,875.00 |
1,900.00 |
9,500.00 |
1,760.00 |
8,800.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
10,000.00 |
10,000.00 |
15,000.00 |
15,000.00 |
30,000.00 |
30,000.00 |
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
10,000.00 |
10,000.00 |
15,000.00 |
15,000.00 |
15,000.00 |
15,000.00 |
|
|
| 805-01-B |
class a concrete (box culvert headwalls)
|
1.54 |
CUYD |
1,000.00 |
1,540.00 |
2,000.00 |
3,080.00 |
3,250.00 |
5,005.00 |
|
|
| 806-01 |
deformed reinforcing steel
|
182   |
LB |
1.00 |
182.00 |
5.00 |
910.00 |
5.50 |
1,001.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,272,031.86 |
|
1,284,857.60 |
|
1,509,927.59 |
|
|
|