Bid Tabulations
Letting of
03/17/2010
LA DOTD Headquarters
| Lead Project: 064-06-0049 | |
| Parish: Lafourche | |
| Routes: | |
| Description: LA 1 SIGNAGE IMPROVEMENTS | |
| Type Const: GRADING AND RELATED WORK. | |
| Estimated Construction Cost: $61,242.95 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 01165 | Ernest P. Breaux Electrical, Inc. | $99,595.00 |
| 2 | 05473 | Jack B. Harper Electrical Inc. | $144,518.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Ernest P. Breaux Electrical, Inc. |
- 2 - Jack B. Harper Electrical Inc. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 3,250.00 | 3,250.00 | 2,500.00 | 2,500.00 |
| 0002 | 203-07-00300 | Borrow (Vehicular Measurement) (Plastic Soils) | 20 | CUYD | 185.00 | 3,700.00 | 20.00 | 400.00 |
| 0003 | 701-05-01080 | Side Drain Pipe (30" RCP/PP/CMP) | 20 | LNFT | 135.00 | 2,700.00 | 150.00 | 3,000.00 |
| 0004 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 6,500.00 | 6,500.00 | 4,750.00 | 4,750.00 |
| 0005 | 727-01-00100 | Mobilization | 1 | LUMP | 5,675.00 | 5,675.00 | 8,500.00 | 8,500.00 |
| 0006 | 730-01-00100 | Trenching and Backfilling | 45 | LNFT | 7.00 | 315.00 | 8.00 | 360.00 |
| 0007 | 730-02-01040 | Conduit with Conductors (PVC/HDPE) (1") Conduit (SCH. 40 PVC/HDPE)(1") | 120 | LNFT | 3.75 | 450.00 | 3.90 | 468.00 |
| 0008 | 730-07-10000 | Luminaire Luminare (Four 17 watt LED fixture consisting of 12 LEDs per welcome sign) | 12 | EACH | 380.00 | 4,560.00 | 1,500.00 | 18,000.00 |
| 0009 | 730-09-00100 | Electrical System | 1 | LUMP | 33,300.00 | 33,300.00 | 49,500.00 | 49,500.00 |
| 0010 | 730-18-00100 | Service Pole | 3 | EACH | 1,700.00 | 5,100.00 | 4,000.00 | 12,000.00 |
| 0011 | 730-22-00220 | Underground Marker Tape (3")(Detectable) | 45 | LNFT | 1.00 | 45.00 | 2.00 | 90.00 |
| 0012 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,500.00 | 2,500.00 | 2,500.00 | 2,500.00 |
| 0013 | NS-ENH-19100 | Sign (Gateway) Welcome Sign (with foundation in accordance with AASHTO 2001 standards for breakaway post mounting) | 3 | EACH | 10,500.00 | 31,500.00 | 14,150.00 | 42,450.00 |
| CONTRACTOR TOTAL | 99,595.00 | 144,518.00 | ||||||