Bid Tabulations
Letting of
11/17/2010
LA DOTD Headquarters
| DBE GOAL FED | |
| Lead Project: 064-01-0046 | |
| Parish: Jefferson | |
| Routes: LA 1 | |
| Description: LA 1 REPAIRS-HURRICANE IKE, CEDAR ST TO CAMINADA BAY BRIDGE | |
| Type Const: Asphaltic Patching, Surface Prep, Overlay, Striping and Marker Installation, Aggregate Surface Cource, and Borrow | |
| Estimated Construction Cost: $1,374,065.40 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $1,169,919.72 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
|
| Unit Price | Total Amount |
|||||
| 0001 | 203-07-00100 | Borrow (Vehicular Measurement) | 900 | CUYD | 5.00 | 4,500.00 |
| 0002 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 4,048 | CUYD | 25.00 | 101,200.00 |
| 0003 | 502-01-00100 | Superpave Asphaltic Concrete | 4,865.7 | TON | 92.00 | 447,644.40 |
| 0004 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 772 | TON | 92.00 | 71,024.00 |
| 0005 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 500 | SQYD | 80.00 | 40,000.00 |
| 0006 | 701-14-00100 | Cleaning Existing Pipes | 7,250 | LNFT | 10.00 | 72,500.00 |
| 0007 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 110,000.00 | 110,000.00 |
| 0008 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 19.2 | MILE | 0.01 | 0.19 |
| 0009 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 7.66 | MILE | 0.10 | 0.77 |
| 0010 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 18.6 | MILE | 0.10 | 1.86 |
| 0011 | 717-01-00100 | Seeding | 270 | LB | 10.00 | 2,700.00 |
| 0012 | 718-01-00100 | Fertilizer | 8,950 | LB | 0.10 | 895.00 |
| 0013 | 727-01-00100 | Mobilization | 1 | LUMP | 116,000.00 | 116,000.00 |
| 0014 | 731-02-00100 | Reflectorized Raised Pavement Markers | 575 | EACH | 6.00 | 3,450.00 |
| 0015 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 9.3 | MILE | 2,500.00 | 23,250.00 |
| 0016 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.83 | MILE | 850.00 | 3,255.50 |
| 0017 | 735-01-00100 | Mailboxes | 34 | EACH | 6.00 | 204.00 |
| 0018 | 735-02-00100 | Mailbox Supports (Single) | 30 | EACH | 125.00 | 3,750.00 |
| 0019 | 735-03-00100 | Mailbox Supports (Double) | 2 | EACH | 200.00 | 400.00 |
| 0020 | 740-01-00100 | Construction Layout | 1 | LUMP | 47,500.00 | 47,500.00 |
| 0021 | NS-200-00020 | Cleaning Existing Ditches | 20,500 | LNFT | 3.00 | 61,500.00 |
| 0022 | NS-500-00280 | Surface Preparation | 1 | LUMP | 60,000.00 | 60,000.00 |
| 0023 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 14,400 | INLF | 0.01 | 144.00 |
| CONTRACTOR TOTAL | 1,169,919.72 | |||||