Bid Tabulations
Letting of
09/22/2010
LA DOTD Headquarters
| Lead Project: 063-05-0027 | |
| Parish: St. Charles | |
| Routes: LA 18 | |
| Description: JEFFERSON PARISH LINE - LA 52 | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE PAVEMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, and RELATED WORK. | |
| Estimated Construction Cost: $1,717,827.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $1,375,925.78 |
| 2 | 00481 | Coastal Bridge Co., L.L.C. | $1,380,560.68 |
| 3 | 02179 | Boh Bros. Construction Co., LLC. | $1,666,166.31 |
| 4 | 00849 | F.G. Sullivan, Jr. Contractor LLC | $1,798,698.45 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Coastal Bridge Co., L.L.C. |
- 3 - Boh Bros. Construction Co., LLC. |
- 4 - F.G. Sullivan, Jr. Contractor LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 78 | LNFT | 1.00 | 78.00 | 10.00 | 780.00 | 5.00 | 390.00 | 2.00 | 156.00 |
| 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 100 | CUYD | 5.00 | 500.00 | 15.00 | 1,500.00 | 50.00 | 5,000.00 | 10.00 | 1,000.00 |
| 0003 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 2,163 | CUYD | 25.00 | 54,075.00 | 10.00 | 21,630.00 | 25.00 | 54,075.00 | 25.00 | 54,075.00 |
| 0004 | 502-01-00100 | Superpave Asphaltic Concrete | 9,468.1 | TON | 80.00 | 757,448.00 | 78.50 | 743,245.85 | 90.00 | 852,129.00 | 110.00 | 1,041,491.00 |
| 0005 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 784.2 | TON | 80.00 | 62,736.00 | 78.50 | 61,559.70 | 150.00 | 117,630.00 | 110.00 | 86,262.00 |
| 0006 | 509-01-00100 | Cold Planing Asphaltic Pavement | 85,092 | SQYD | 1.00 | 85,092.00 | 2.10 | 178,693.20 | 2.00 | 170,184.00 | 2.50 | 212,730.00 |
| 0007 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -3,545 | CUYD | 10.00 | -35,450.00 | 0.01 | -35.45 | 10.00 | -35,450.00 | 0.00 | 0.00 |
| 0008 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 1,200 | SQYD | 60.00 | 72,000.00 | 40.00 | 48,000.00 | 90.00 | 108,000.00 | 110.00 | 132,000.00 |
| 0009 | 704-01-02000 | Guard Rail (DoubleThrie Beam) (3'-1 1/2" post spacing) | 87.5 | LNFT | 45.00 | 3,937.50 | 45.00 | 3,937.50 | 50.00 | 4,375.00 | 55.50 | 4,856.25 |
| 0010 | 704-03-00100 | Blocked Out Guard Rail | 181.3 | LNFT | 20.00 | 3,626.00 | 20.00 | 3,626.00 | 22.00 | 3,988.60 | 20.00 | 3,626.00 |
| 0011 | 704-11-00100 | Guard Rail End Treatment (Flared) | 2 | EACH | 1,500.00 | 3,000.00 | 2,200.00 | 4,400.00 | 2,300.00 | 4,600.00 | 1,545.00 | 3,090.00 |
| 0012 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 100,000.00 | 100,000.00 | 57,500.00 | 57,500.00 | 150,000.00 | 150,000.00 | 100,000.00 | 100,000.00 |
| 0013 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 224 | LNFT | 0.05 | 11.20 | 0.25 | 56.00 | 0.10 | 22.40 | 0.10 | 22.40 |
| 0014 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 48 | LNFT | 0.75 | 36.00 | 0.75 | 36.00 | 0.30 | 14.40 | 0.25 | 12.00 |
| 0015 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 13.44 | MILE | 225.00 | 3,024.00 | 400.00 | 5,376.00 | 0.10 | 1.34 | 500.00 | 6,720.00 |
| 0016 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 9.34 | MILE | 100.00 | 934.00 | 1.00 | 9.34 | 0.15 | 1.40 | 200.00 | 1,868.00 |
| 0017 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 33.84 | MILE | 100.00 | 3,384.00 | 1.00 | 33.84 | 0.20 | 6.77 | 100.00 | 3,384.00 |
| 0018 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 2 | EACH | 40.00 | 80.00 | 45.00 | 90.00 | 10.00 | 20.00 | 25.00 | 50.00 |
| 0019 | 717-01-00100 | Seeding | 133 | LB | 8.50 | 1,130.50 | 8.50 | 1,130.50 | 9.00 | 1,197.00 | 10.00 | 1,330.00 |
| 0020 | 718-01-00100 | Fertilizer | 4,436 | LB | 0.50 | 2,218.00 | 0.50 | 2,218.00 | 0.50 | 2,218.00 | 0.65 | 2,883.40 |
| 0021 | 727-01-00100 | Mobilization | 1 | LUMP | 135,000.00 | 135,000.00 | 140,000.00 | 140,000.00 | 160,000.00 | 160,000.00 | 45,000.00 | 45,000.00 |
| 0022 | 729-16-00300 | Object Marker Assembly (Type 3) | 2 | EACH | 80.00 | 160.00 | 80.00 | 160.00 | 80.00 | 160.00 | 62.00 | 124.00 |
| 0023 | 729-19-00300 | Dead End Road Installations (Type C) | 1 | EACH | 900.00 | 900.00 | 750.00 | 750.00 | 500.00 | 500.00 | 900.00 | 900.00 |
| 0024 | 731-02-00100 | Reflectorized Raised Pavement Markers | 822 | EACH | 5.50 | 4,521.00 | 5.25 | 4,315.50 | 5.50 | 4,521.00 | 5.25 | 4,315.50 |
| 0025 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 112 | LNFT | 1.35 | 151.20 | 1.35 | 151.20 | 1.50 | 168.00 | 1.35 | 151.20 |
| 0026 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 24 | LNFT | 5.00 | 120.00 | 4.50 | 108.00 | 4.75 | 114.00 | 4.50 | 108.00 |
| 0027 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 16.92 | MILE | 3,000.00 | 50,760.00 | 2,500.00 | 42,300.00 | 2,600.00 | 43,992.00 | 2,500.00 | 42,300.00 |
| 0028 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.67 | MILE | 850.00 | 3,969.50 | 850.00 | 3,969.50 | 900.00 | 4,203.00 | 850.00 | 3,969.50 |
| 0029 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 1 | EACH | 200.00 | 200.00 | 215.00 | 215.00 | 225.00 | 225.00 | 215.00 | 215.00 |
| 0030 | 735-01-00100 | Mailboxes | 65 | EACH | 1.00 | 65.00 | 5.00 | 325.00 | 6.00 | 390.00 | 1.00 | 65.00 |
| 0031 | 735-02-00100 | Mailbox Supports (Single) | 52 | EACH | 115.00 | 5,980.00 | 125.00 | 6,500.00 | 130.00 | 6,760.00 | 115.00 | 5,980.00 |
| 0032 | 735-03-00100 | Mailbox Supports (Double) | 2 | EACH | 150.00 | 300.00 | 200.00 | 400.00 | 210.00 | 420.00 | 180.00 | 360.00 |
| 0033 | 735-04-00100 | Mailbox Supports (Multiple) | 3 | EACH | 300.00 | 900.00 | 400.00 | 1,200.00 | 400.00 | 1,200.00 | 385.00 | 1,155.00 |
| 0034 | 740-01-00100 | Construction Layout | 1 | LUMP | 55,000.00 | 55,000.00 | 7,500.00 | 7,500.00 | 2,000.00 | 2,000.00 | 35,000.00 | 35,000.00 |
| 0035 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 3,888 | INLF | 0.01 | 38.88 | 10.00 | 38,880.00 | 0.80 | 3,110.40 | 0.90 | 3,499.20 |
| CONTRACTOR TOTAL | 1,375,925.78 | 1,380,560.68 | 1,666,166.31 | 1,798,698.45 | ||||||||