Bid Tabulations
Letting of
09/29/2010
LA DOTD Headquarters
| Lead Project: 062-05-0042 | |
| Parish: Plaquemines | |
| Routes: LA 23 | |
| Description: LA 23 OVERLAY (EMPIRE TO FORT JACKSON) | |
| Type Const: ASPHALTIC OVERLAY OF ASPHALTIC PAVEMENT | |
| Estimated Construction Cost: $12,003,975.98 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $11,729,900.55 |
| 2 | 02179 | Boh Bros. Construction Co., LLC. | $16,722,801.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Boh Bros. Construction Co., LLC. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 7,650 | LNFT | 5.00 | 38,250.00 | 11.00 | 84,150.00 |
| 0002 | 202-02-06140 | Removal of Curbs (Concrete) | 4,890 | LNFT | 4.00 | 19,560.00 | 11.00 | 53,790.00 |
| 0003 | 202-02-14500 | Removal of Guard Rail | 245 | LNFT | 7.00 | 1,715.00 | 8.00 | 1,960.00 |
| 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 9,754 | CUYD | 8.00 | 78,032.00 | 30.00 | 292,620.00 |
| 0005 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) RAP Only | 1,832.7 | CUYD | 9.00 | 16,494.30 | 25.00 | 45,817.50 |
| 0006 | 502-01-00100 | Superpave Asphaltic Concrete | 86,602.9 | TON | 79.00 | 6,841,629.10 | 100.00 | 8,660,290.00 |
| 0007 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 400.5 | TON | 150.00 | 60,075.00 | 160.00 | 64,080.00 |
| 0008 | 509-01-00100 | Cold Planing Asphaltic Pavement | 200,448 | SQYD | 2.00 | 400,896.00 | 3.20 | 641,433.60 |
| 0009 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -5,568.5 | CUYD | 5.00 | -27,842.50 | 1.00 | -5,568.50 |
| 0010 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 1,175 | SQYD | 70.00 | 82,250.00 | 70.00 | 82,250.00 |
| 0011 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 2,950 | SQYD | 90.00 | 265,500.00 | 110.00 | 324,500.00 |
| 0012 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 213,790 | LNFT | 0.80 | 171,032.00 | 1.16 | 247,996.40 |
| 0013 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 134,390 | LNFT | 1.50 | 201,585.00 | 1.50 | 201,585.00 |
| 0014 | 701-14-00100 | Cleaning Existing Pipes | 46,000 | LNFT | 2.00 | 92,000.00 | 4.00 | 184,000.00 |
| 0015 | 702-02-00001 | Manhole (Remove and Replace Frame and Cover) "Northeast Service Road" | 1 | EACH | 2,000.00 | 2,000.00 | 1,500.00 | 1,500.00 |
| 0016 | 702-04-00100 | Adjusting Manholes "Northeast Service Road" | 1 | EACH | 2,000.00 | 2,000.00 | 1,100.00 | 1,100.00 |
| 0017 | 702-04-00200 | Adjusting Catch Basins | 95 | EACH | 725.00 | 68,875.00 | 2,400.00 | 228,000.00 |
| 0018 | 704-03-00100 | Blocked Out Guard Rail | 200 | LNFT | 18.00 | 3,600.00 | 19.00 | 3,800.00 |
| 0019 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 12.5 | LNFT | 26.00 | 325.00 | 28.00 | 350.00 |
| 0020 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 25 | LNFT | 60.00 | 1,500.00 | 60.00 | 1,500.00 |
| 0021 | 704-11-00100 | Guard Rail End Treatment (Flared) | 1 | EACH | 2,300.00 | 2,300.00 | 2,400.00 | 2,400.00 |
| 0022 | 707-01-00100 | Concrete Curb | 4,150 | LNFT | 17.00 | 70,550.00 | 33.50 | 139,025.00 |
| 0023 | 707-01-00200 | Concrete Curb (Barrier) | 210 | LNFT | 30.00 | 6,300.00 | 30.00 | 6,300.00 |
| 0024 | 707-01-00300 | Concrete Curb (Mountable) | 230 | LNFT | 30.00 | 6,900.00 | 30.00 | 6,900.00 |
| 0025 | 707-03-00100 | Combination Concrete Curb and Gutter | 8,150 | LNFT | 28.00 | 228,200.00 | 33.00 | 268,950.00 |
| 0026 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 500,000.00 | 500,000.00 | 2,300,000.00 | 2,300,000.00 |
| 0027 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 7,435 | LNFT | 0.15 | 1,115.25 | 0.10 | 743.50 |
| 0028 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 44.2 | MILE | 275.00 | 12,155.00 | 10.00 | 442.00 |
| 0029 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 44.2 | MILE | 425.00 | 18,785.00 | 15.00 | 663.00 |
| 0030 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 98.86 | MILE | 450.00 | 44,487.00 | 20.00 | 1,977.20 |
| 0031 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 19 | EACH | 25.00 | 475.00 | 10.00 | 190.00 |
| 0032 | 717-01-00100 | Seeding | 646 | LB | 6.00 | 3,876.00 | 10.00 | 6,460.00 |
| 0033 | 718-01-00100 | Fertilizer | 22,613 | LB | 0.30 | 6,783.90 | 0.50 | 11,306.50 |
| 0034 | 727-01-00100 | Mobilization | 1 | LUMP | 1,100,000.00 | 1,100,000.00 | 1,600,000.00 | 1,600,000.00 |
| 0035 | 729-16-00300 | Object Marker Assembly (Type 3) | 1 | EACH | 85.00 | 85.00 | 94.00 | 94.00 |
| 0036 | 731-02-00100 | Reflectorized Raised Pavement Markers | 4,435 | EACH | 5.50 | 24,392.50 | 5.80 | 25,723.00 |
| 0037 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 7,135 | LNFT | 1.40 | 9,989.00 | 1.50 | 10,702.50 |
| 0038 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 50.49 | MILE | 2,600.00 | 131,274.00 | 2,500.00 | 126,225.00 |
| 0039 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 22.1 | MILE | 900.00 | 19,890.00 | 930.00 | 20,553.00 |
| 0040 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 13 | EACH | 230.00 | 2,990.00 | 240.00 | 3,120.00 |
| 0041 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 6 | EACH | 230.00 | 1,380.00 | 240.00 | 1,440.00 |
| 0042 | 735-01-00100 | Mailboxes | 14 | EACH | 6.00 | 84.00 | 7.00 | 98.00 |
| 0043 | 735-02-00100 | Mailbox Supports (Single) | 11 | EACH | 200.00 | 2,200.00 | 220.00 | 2,420.00 |
| 0044 | 735-04-00100 | Mailbox Supports (Multiple) | 1 | EACH | 500.00 | 500.00 | 500.00 | 500.00 |
| 0045 | 740-01-00100 | Construction Layout | 1 | LUMP | 30,000.00 | 30,000.00 | 75,000.00 | 75,000.00 |
| 0046 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphaltic Concrete Overlay | 213,790 | LNFT | 1.15 | 245,858.50 | 0.88 | 188,135.20 |
| 0047 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphaltic Concrete Overlay | 134,390 | LNFT | 1.15 | 154,548.50 | 1.21 | 162,611.90 |
| 0048 | NS-500-00260 | Sawcuts in Asphaltic Concrete Lifts | 708,760 | LNFT | 1.00 | 708,760.00 | 0.72 | 510,307.20 |
| 0049 | NS-500-00280 | Surface Preparation | 1 | LUMP | 50,000.00 | 50,000.00 | 100,000.00 | 100,000.00 |
| 0050 | NS-702-00001 | Cleaning Existing Catch Basin | 95 | EACH | 90.00 | 8,550.00 | 200.00 | 19,000.00 |
| 0051 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 32.72 | MILE | 550.00 | 17,996.00 | 500.00 | 16,360.00 |
| CONTRACTOR TOTAL | 11,729,900.55 | 16,722,801.00 | ||||||