Error processing SSI file
Error processing SSI file
Bid Tabs Error processing SSI file
Bid Tabulations Error processing SSI file
February 06, 2014 Error processing SSI file

Letting of 12/13/2006 LA DOTD Headquarters


REBID
go back
Go Back
DBE GOAL FED
Lead Project: 713-02-0114
Parish: ALLEN
Routes:
Description: SAM CLOUD ROAD AND LIVE OAK STREET BRIDGES
Type Const: grading, class ii base course, drainage structures, superpave asphaltic concrete
pavement, concrete slab span bridge and related work
Estimated Construction Cost: $617,290.25
 
RankLicenseBidderConstruction Bid
1 08815 W. E. MCDONALD & SON, LLC. $686,355.37
2 18546 C W & W CONTRACTORS, INC. $778,022.50
3 09090 GUINN BROTHERS, LLC. $798,996.60
4 00060 F. MILLER CONSTRUCTION LLC $904,261.85
 12879 PETERS CONSTRUCTION CO., INC. IRREGULAR
 
Item Number Item Description Quantity Unit of Measure - 1 -
W. E. MCDONALD & SON, LLC.
- 2 -
C W & W CONTRACTORS, INC.
- 3 -
GUINN BROTHERS, LLC.
- 4 -
F. MILLER CONSTRUCTION LLC
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 37,000.00 37,000.00 10,000.00 10,000.00 10,000.00 10,000.00 5,000.00 5,000.00
202-02-A-01 removal of bridge(sta. 105+19.28;20.20' x 39.00'
timber bridge0
1      EACH 10,000.00 10,000.00 5,000.00 5,000.00 6,000.00 6,000.00 20,000.00 20,000.00
202-02-A-02 removal of bridge(sta. 105+38.53;26.40' x 76.80'
timber bridge0
1      EACH 10,000.00 10,000.00 7,000.00 7,000.00 10,000.00 10,000.00 8,000.00 8,000.00
202-02-D removal of concrete walks & drives 16      SQYD 200.00 3,200.00 15.00 240.00 100.00 1,600.00 45.00 720.00
203-06 excavation & embankment lump      LUMP 40,000.00 40,000.00 51,000.00 51,000.00 35,000.00 35,000.00 20,000.00 20,000.00
204-02 temporary hay or straw bales 40      EACH 10.00 400.00 5.00 200.00 0.00 0.00 13.00 520.00
204-03 temporary slope drains 50      LNFT 25.00 1,250.00 5.00 250.00 0.00 0.00 30.00 1,500.00
204-05-A temporary sediment check dams (hay) 8      EACH 500.00 4,000.00 75.00 600.00 0.00 0.00 165.00 1,320.00
204-06 temporary silt fencing 600      LNFT 3.00 1,800.00 3.00 1,800.00 4.00 2,400.00 3.00 1,800.00
302-01 class ii base course 78.6    CUYD 150.00 11,790.00 125.00 9,825.00 115.00 9,039.00 110.00 8,646.00
401-02 aggregate surface course (adjusted vehicular
measurement)
17      CUYD 250.00 4,250.00 200.00 3,400.00 125.00 2,125.00 135.00 2,295.00
502-01 superpave asphaltic concrete 126.7    TON 200.00 25,340.00 300.00 38,010.00 328.00 41,557.60 450.00 57,015.00
509-01 cold planing asphaltic pavement 230      SQYD 10.00 2,300.00 60.00 13,800.00 40.00 9,200.00 72.00 16,560.00
509-02 contractor retained reclaimed asphaltic pavement - 13      CUYD 0.01 - 0.13 1.00 - 13.00 0.00 0.00 5.00 - 65.00
701-05-I-01 side drain pipe (24")(erosion) 60      LNFT 85.00 5,100.00 50.00 3,000.00 90.00 5,400.00 64.00 3,840.00
706-01-A concrete walk (4" thick) 2.5    SQYD 500.00 1,250.00 250.00 625.00 500.00 1,250.00 300.00 750.00
707-01-A concrete curb(special barrier type)(w/ reinforcing) 244.9    LNFT 55.00 13,469.50 60.00 14,694.00 50.00 12,245.00 25.00 6,122.50
711-01-C riprap (30 lb,14" thick) 1,246      SQYD 60.00 74,760.00 90.00 112,140.00 80.00 99,680.00 60.00 74,760.00
711-04 geotextile fabric 1,246      SQYD 3.00 3,738.00 3.00 3,738.00 5.00 6,230.00 3.00 3,738.00
713-01 temporary signs & barricades lump      LUMP 25,000.00 25,000.00 20,000.00 20,000.00 18,000.00 18,000.00 30,000.00 30,000.00
716-01-A mulch (vegetative) 0.50   ACRE 1,500.00 750.00 3,500.00 1,750.00 5,000.00 2,500.00 2,500.00 1,250.00
717-01 seeding 22      LB 100.00 2,200.00 50.00 1,100.00 50.00 1,100.00 25.00 550.00
718-01 fertilizer 500      LB 1.00 500.00 2.50 1,250.00 4.00 2,000.00 2.00 1,000.00
724-02 pavement widening 76.1    SQYD 100.00 7,610.00 100.00 7,610.00 110.00 8,371.00 150.00 11,415.00
726-01 bedding material 134.3    CUYD 100.00 13,430.00 125.00 16,787.50 120.00 16,116.00 130.00 17,459.00
727-01 mobilization lump      LUMP 12,500.00 12,500.00 50,000.00 50,000.00 80,000.00 80,000.00 90,000.00 90,000.00
729-16-B object marker assembly (type 2) 4      EACH 75.00 300.00 70.00 280.00 100.00 400.00 90.00 360.00
729-16-C object marker assembly (type 3) 4      EACH 75.00 300.00 85.00 340.00 120.00 480.00 110.00 440.00
740-01 construction layout lump      LUMP 12,500.00 12,500.00 12,000.00 12,000.00 6,000.00 6,000.00 36,000.00 36,000.00
804-01-C precast concrete piles (16") 1,200      LNFT 65.00 78,000.00 86.00 103,200.00 75.00 90,000.00 69.86 83,832.00
804-12 loading permanent piles 1      EACH 1.00 1.00 500.00 500.00 1.00 1.00 100.00 100.00
805-01-B class a concrete (box culvert headwalls) 24.57   CUYD 1,500.00 36,855.00 1,200.00 29,484.00 1,500.00 36,855.00 875.00 21,498.75
805-10-A bridge superstructure & substructure(90 degree
crossing;24'clear rdwy. w/ sidewalk(c.i.p.)
5      SPAN 27,000.00 135,000.00 27,500.00 137,500.00 28,000.00 140,000.00 55,000.00 275,000.00
805-12-M reinforced concrete box culverts (6'x 6') 126.0    LNFT 700.00 88,200.00 725.00 91,350.00 875.00 110,250.00 600.00 75,600.00
806-01 deformed reinforcing steel 1,854      LB 3.00 5,562.00 3.00 5,562.00 5.50 10,197.00 1.40 2,595.60
S-101 concrete approach slab(24'roadway,90 degree
crossing,tapered barrier rails and sidewalk w/
railing)
2      EACH 9,000.00 18,000.00 12,000.00 24,000.00 12,500.00 25,000.00 12,320.00 24,640.00
    railing)                    
 CONTRACTOR TOTAL       686,355.37   778,022.50   798,996.60   904,261.85
 
Item Number Item Description Quantity Unit of Measure
PETERS CONSTRUCTION CO., INC.

 

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 21,000.00 21,000.00            
202-02-A-01 removal of bridge(sta. 105+19.28;20.20' x 39.00'
timber bridge0
1      EACH 4,500.00 4,500.00            
202-02-A-02 removal of bridge(sta. 105+38.53;26.40' x 76.80'
timber bridge0
1      EACH 8,000.00 8,000.00            
202-02-D removal of concrete walks & drives 16      SQYD 10.00 160.00            
203-06 excavation & embankment lump      LUMP 15,000.00 15,000.00            
204-02 temporary hay or straw bales 40      EACH 8.00 320.00            
204-03 temporary slope drains 50      LNFT 6.00 300.00            
204-05-A temporary sediment check dams (hay) 8      EACH 50.00 400.00            
204-06 temporary silt fencing 600      LNFT 3.00 1,800.00            
302-01 class ii base course 78.6    CUYD 63.00 4,951.80            
401-02 aggregate surface course (adjusted vehicular
measurement)
17      CUYD 50.00 850.00            
502-01 superpave asphaltic concrete 126.7    TON 250.00 31,675.00            
509-01 cold planing asphaltic pavement 230      SQYD 12.00 2,760.00            
509-02 contractor retained reclaimed asphaltic pavement - 13      CUYD FREE FREE            
701-05-I-01 side drain pipe (24")(erosion) 60      LNFT 50.00 3,000.00            
706-01-A concrete walk (4" thick) 2.5    SQYD 100.00 250.00            
707-01-A concrete curb(special barrier type)(w/ reinforcing) 244.9    LNFT 35.00 8,571.50            
711-01-C riprap (30 lb,14" thick) 1,246      SQYD 50.00 62,300.00            
711-04 geotextile fabric 1,246      SQYD 1.60 1,993.60            
713-01 temporary signs & barricades lump      LUMP 15,000.00 15,000.00            
716-01-A mulch (vegetative) 0.50   ACRE 1,000.00 500.00            
717-01 seeding 22      LB 6.00 132.00            
718-01 fertilizer 500      LB 1.00 500.00            
724-02 pavement widening 76.1    SQYD 50.00 3,805.00            
726-01 bedding material 134.3    CUYD 50.00 6,715.00            
727-01 mobilization lump      LUMP 5,000.00 5,000.00            
729-16-B object marker assembly (type 2) 4      EACH 80.00 320.00            
729-16-C object marker assembly (type 3) 4      EACH 80.00 320.00            
740-01 construction layout lump      LUMP 10,000.00 10,000.00            
804-01-C precast concrete piles (16") 1,200      LNFT 67.00 80,400.00            
804-12 loading permanent piles 1      EACH 1.00 1.00            
805-01-B class a concrete (box culvert headwalls) 24.57   CUYD 900.00 22,113.00            
805-10-A bridge superstructure & substructure(90 degree
crossing;24'clear rdwy. w/ sidewalk(c.i.p.)
5      SPAN 40,000.00 200,000.00            
805-12-M reinforced concrete box culverts (6'x 6') 126.0    LNFT 565.00 71,190.00            
806-01 deformed reinforcing steel 1,854      LB 1.00 1,854.00            
S-101 concrete approach slab(24'roadway,90 degree
crossing,tapered barrier rails and sidewalk w/
railing)
2      EACH 11,000.00 22,000.00            
    railing)                    
 CONTRACTOR TOTAL       IRREGULAR            

Error processing SSI file