| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - JAMES CONSTRUCTION GROUP LLC |
- 2 - D & J CONSTRUCTION CO., INC. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
100,000.00 |
100,000.00 |
100,000.00 |
100,000.00 |
|
|
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
24,000.00 |
24,000.00 |
15,000.00 |
15,000.00 |
|
|
|
|
| 202-02-C |
removal of portland cement concrete pavement
|
5,909   |
SQYD |
6.00 |
35,454.00 |
6.00 |
35,454.00 |
|
|
|
|
| 202-02-D |
removal of concrete walks & drives
|
999   |
SQYD |
10.00 |
9,990.00 |
5.00 |
4,995.00 |
|
|
|
|
| 202-02-F |
removal of concrete combination curb & gutter
|
2,563.6 |
LNFT |
4.00 |
10,254.40 |
4.00 |
10,254.40 |
|
|
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
9,155.0 |
SQYD |
3.00 |
27,465.00 |
6.00 |
54,930.00 |
|
|
|
|
| 202-02-I |
removal of paved ditches
|
393   |
SQYD |
9.00 |
3,537.00 |
4.00 |
1,572.00 |
|
|
|
|
| 203-01 |
general excavation
|
33,416   |
CUYD |
5.25 |
175,434.00 |
4.00 |
133,664.00 |
|
|
|
|
| 203-04 |
embankment
|
96,815   |
CUYD |
7.50 |
726,112.50 |
7.00 |
677,705.00 |
|
|
|
|
| 204-02 |
temporary hay or straw bales
|
129   |
EACH |
9.00 |
1,161.00 |
8.00 |
1,032.00 |
|
|
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
55   |
EACH |
140.00 |
7,700.00 |
100.00 |
5,500.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
9,053   |
LNFT |
1.65 |
14,937.45 |
2.50 |
22,632.50 |
|
|
|
|
| 204-07 |
temporary stone construction entrance
|
2   |
EACH |
5,000.00 |
10,000.00 |
1,200.00 |
2,400.00 |
|
|
|
|
| 302-02-A-01 |
class ii base course (6" thick) (stone or recycled
pccp) |
444.5 |
SQYD |
11.00 |
4,889.50 |
28.00 |
12,446.00 |
|
|
|
|
| 302-02-B-01 |
class ii base course (8 1/2" thick) (soil cement,
stone or recycled pccp) |
464.3 |
SQYD |
16.00 |
7,428.80 |
35.00 |
16,250.50 |
|
|
|
|
| 302-02-E-01 |
class ii base course (13" thick) (stone or recycled
pccp) |
2,173.8 |
SQYD |
23.00 |
49,997.40 |
33.00 |
71,735.40 |
|
|
|
|
| 302-02-F-01 |
class ii base course (12 1/2" thick)
|
20,634.3 |
SQYD |
22.00 |
453,954.60 |
23.00 |
474,588.90 |
|
|
|
|
| 302-02-G |
class ii base course (14 " thick)
|
28.0 |
SQYD |
31.00 |
868.00 |
100.00 |
2,800.00 |
|
|
|
|
| 302-02-H-01 |
class ii base course (8" thick) (stone or recycled
pccp) |
13,815.1 |
SQYD |
15.00 |
207,226.50 |
21.00 |
290,117.10 |
|
|
|
|
| 304-01 |
lime
|
349.00 |
TON |
0.01 |
3.49 |
150.00 |
52,350.00 |
|
|
|
|
| 304-04-D |
lime treatment (type d) (12" thick)(9% by volume)
|
7,834   |
SQYD |
6.00 |
47,004.00 |
2.50 |
19,585.00 |
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
1,200.0 |
CUYD |
30.00 |
36,000.00 |
100.00 |
120,000.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
6,007.5 |
TON |
96.00 |
576,720.00 |
96.00 |
576,720.00 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
297.8 |
TON |
146.00 |
43,478.80 |
146.00 |
43,478.80 |
|
|
|
|
| 601-01-K |
portland cement concrete pavement (10" thick)
|
13,345.2 |
SQYD |
60.00 |
800,712.00 |
66.00 |
880,783.20 |
|
|
|
|
| 601-04 |
portland cement concrete pavement coring
|
28   |
EACH |
90.00 |
2,520.00 |
100.00 |
2,800.00 |
|
|
|
|
| 701-01-I |
cross drain pipe (24" rcp/rpvcp)
|
454   |
LNFT |
75.00 |
34,050.00 |
75.00 |
34,050.00 |
|
|
|
|
| 701-01-K |
cross drain pipe (30" rcp/rpvcp)
|
67   |
LNFT |
100.00 |
6,700.00 |
95.00 |
6,365.00 |
|
|
|
|
| 701-02-H |
cross drain pipe arch (48" equiv. rcpa)
|
69   |
LNFT |
190.00 |
13,110.00 |
185.00 |
12,765.00 |
|
|
|
|
| 701-03-G |
storm drain pipe (18" rcp/rpvcp)
|
552   |
LNFT |
60.00 |
33,120.00 |
55.00 |
30,360.00 |
|
|
|
|
| 701-03-I |
storm drain pipe (24" rcp/rpvcp)
|
148   |
LNFT |
150.00 |
22,200.00 |
75.00 |
11,100.00 |
|
|
|
|
| 701-04-B |
storm drain pipe arch (18" equiv. rcpa)
|
40   |
LNFT |
80.00 |
3,200.00 |
85.00 |
3,400.00 |
|
|
|
|
| 701-05-G |
side drain pipe (18" rcp/rpvcp)
|
448   |
LNFT |
45.00 |
20,160.00 |
55.00 |
24,640.00 |
|
|
|
|
| 701-10-C |
reinforced concrete pipe (extension)(8")
|
4   |
LNFT |
100.00 |
400.00 |
175.00 |
700.00 |
|
|
|
|
| 702-03-A |
catch basins (cb-01)
|
5   |
EACH |
4,500.00 |
22,500.00 |
3,200.00 |
16,000.00 |
|
|
|
|
| 702-03-B |
catch basins (cb-02)
|
1   |
EACH |
5,500.00 |
5,500.00 |
3,400.00 |
3,400.00 |
|
|
|
|
| 702-03-D |
catch basins (cb-07)
|
2   |
EACH |
5,000.00 |
10,000.00 |
4,000.00 |
8,000.00 |
|
|
|
|
| 702-03-F |
catch basins (cb-08)
|
3   |
EACH |
7,000.00 |
21,000.00 |
4,250.00 |
12,750.00 |
|
|
|
|
| 702-04-A |
adjusting manholes
|
6   |
EACH |
1,500.00 |
9,000.00 |
1,600.00 |
9,600.00 |
|
|
|
|
| 702-04-B |
adjusting catch basins
|
1   |
EACH |
2,500.00 |
2,500.00 |
2,100.00 |
2,100.00 |
|
|
|
|
| 702-08-A |
side drain safety end (type 1)
|
6   |
EACH |
1,300.00 |
7,800.00 |
1,000.00 |
6,000.00 |
|
|
|
|
| 705-06-B |
chain link fence (5-foot height)
|
6,362   |
LNFT |
17.00 |
108,154.00 |
18.50 |
117,697.00 |
|
|
|
|
| 706-01-A |
concrete walk (4" thick)
|
47.1 |
SQYD |
42.00 |
1,978.20 |
36.00 |
1,695.60 |
|
|
|
|
| 706-02-C |
concrete drive (6" thick)
|
870.3 |
SQYD |
55.00 |
47,866.50 |
55.00 |
47,866.50 |
|
|
|
|
| 707-03 |
combination concrete curb & gutter
|
2,313.0 |
LNFT |
17.00 |
39,321.00 |
19.00 |
43,947.00 |
|
|
|
|
| 708-01 |
right-of-way monument
|
27   |
EACH |
200.00 |
5,400.00 |
175.00 |
4,725.00 |
|
|
|
|
| 708-02 |
right-of-way monument witness posts
|
27   |
EACH |
200.00 |
5,400.00 |
100.00 |
2,700.00 |
|
|
|
|
| 712-01-A |
concrete cast-in-place revetment (4" thick)
|
1,544   |
SQYD |
45.00 |
69,480.00 |
40.00 |
61,760.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
45,000.00 |
45,000.00 |
200,000.00 |
200,000.00 |
|
|
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
1.500 |
MILE |
500.00 |
750.00 |
250.00 |
375.00 |
|
|
|
|
| 713-04-A-01 |
temporary pvmt. markings (broken line)(4" w)(4' l)
(type i removable) |
1.000 |
MILE |
850.00 |
850.00 |
1,000.00 |
1,000.00 |
|
|
|
|
| 713-04-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
2.000 |
MILE |
650.00 |
1,300.00 |
800.00 |
1,600.00 |
|
|
|
|
| 713-05-A-01 |
temporary pavement markings (solid line)(4" width)
(type i removable) |
1.000 |
MILE |
10,000.00 |
10,000.00 |
12,000.00 |
12,000.00 |
|
|
|
|
| 713-05-B |
temporary pavement markings (solid line)(4" width)
|
3.500 |
MILE |
600.00 |
2,100.00 |
800.00 |
2,800.00 |
|
|
|
|
| 713-09 |
temporary precast concrete barrier (department
furnished) |
150   |
EACH |
363.96 |
54,594.00 |
150.00 |
22,500.00 |
|
|
|
|
| 716-01-A |
mulch (vegetative)
|
7.02 |
ACRE |
900.00 |
6,318.00 |
850.00 |
5,967.00 |
|
|
|
|
| 717-01 |
seeding
|
680   |
LB |
8.00 |
5,440.00 |
9.00 |
6,120.00 |
|
|
|
|
| 718-01 |
fertilizer
|
16,000   |
LB |
0.25 |
4,000.00 |
0.60 |
9,600.00 |
|
|
|
|
| 719-04 |
landscaping
|
lump |
LUMP |
18,000.00 |
18,000.00 |
12,000.00 |
12,000.00 |
|
|
|
|
| 720-01-A |
erosion control system, slope protection (type a)
|
49,500   |
SQYD |
1.20 |
59,400.00 |
1.80 |
89,100.00 |
|
|
|
|
| 720-01-C |
erosion control system, flexible channel liner (type c)
|
334   |
SQYD |
3.25 |
1,085.50 |
3.50 |
1,169.00 |
|
|
|
|
| 722-01 |
project site laboratory
|
1   |
EACH |
8,000.00 |
8,000.00 |
11,000.00 |
11,000.00 |
|
|
|
|
| 726-01 |
bedding material
|
253.1 |
CUYD |
80.00 |
20,248.00 |
80.00 |
20,248.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
500,000.00 |
500,000.00 |
535,000.00 |
535,000.00 |
|
|
|
|
| 729-01 |
sign (type a)
|
145.9 |
SQFT |
26.00 |
3,793.40 |
50.00 |
7,295.00 |
|
|
|
|
| 729-08-A |
mounting (2 1/2" post)
|
22   |
EACH |
850.00 |
18,700.00 |
1,200.00 |
26,400.00 |
|
|
|
|
| 729-08-B |
mounting (3 1/2" post)
|
3   |
EACH |
960.00 |
2,880.00 |
1,600.00 |
4,800.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
219   |
EACH |
9.00 |
1,971.00 |
7.00 |
1,533.00 |
|
|
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
1,580   |
LNFT |
3.25 |
5,135.00 |
3.50 |
5,530.00 |
|
|
|
|
| 732-01-D |
plastic pavement striping (12" width)
|
435   |
LNFT |
2.00 |
870.00 |
7.00 |
3,045.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
454   |
LNFT |
5.00 |
2,270.00 |
8.00 |
3,632.00 |
|
|
|
|
| 732-02-A-04 |
plastic pvmt striping (solid line)(4" width) (90 mil
thickness) |
2.382 |
MILE |
2,000.00 |
4,764.00 |
3,300.00 |
7,860.60 |
|
|
|
|
| 732-03-A-04 |
plast pvmt striping(broken line) (4" width) ( 90 mil
thickness) |
1.216 |
MILE |
1,000.00 |
1,216.00 |
1,200.00 |
1,459.20 |
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
9   |
EACH |
300.00 |
2,700.00 |
350.00 |
3,150.00 |
|
|
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
4   |
EACH |
350.00 |
1,400.00 |
350.00 |
1,400.00 |
|
|
|
|
| 732-05 |
removal of existing markings
|
1.000 |
MILE |
8,500.00 |
8,500.00 |
4,000.00 |
4,000.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
75,000.00 |
75,000.00 |
155,000.00 |
155,000.00 |
|
|
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
5,000.00 |
5,000.00 |
75,000.00 |
75,000.00 |
|
|
|
|
| 805-01-B |
class a concrete (box culvert headwalls)
|
43.83 |
CUYD |
1,200.00 |
52,596.00 |
1,200.00 |
52,596.00 |
|
|
|
|
| 805-12-S |
reinforced concrete box culverts (8'x 8') (extensions)
|
177.5 |
LNFT |
750.00 |
133,125.00 |
750.00 |
133,125.00 |
|
|
|
|
| 806-01 |
deformed reinforcing steel
|
2,885   |
LB |
1.50 |
4,327.50 |
1.65 |
4,760.25 |
|
|
|
|
| S-001 |
remove and remount existing sign faces (single post)
|
18   |
EACH |
1,800.00 |
32,400.00 |
1,800.00 |
32,400.00 |
|
|
|
|
| S-002 |
remove and remount existing sign faces (multiple post)
|
10   |
EACH |
2,200.00 |
22,000.00 |
2,000.00 |
20,000.00 |
|
|
|
|
| S-003 |
dynamic message sign unit
|
3   |
EACH |
12,500.00 |
37,500.00 |
11,000.00 |
33,000.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
5,018,921.54 |
|
5,596,879.95 |
|
|
|
|
|