| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - COASTAL BRIDGE CO., L.L.C. |
- 2 - JAMES CONSTRUCTION GROUP LLC |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
100,000.00 |
100,000.00 |
400,000.00 |
400,000.00 |
|
|
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
10,000.00 |
10,000.00 |
8,000.00 |
8,000.00 |
|
|
|
|
| 202-02-A-01 |
removal of bridges (sta. 409+00; 28' x 114')
|
1   |
EACH |
100,000.00 |
100,000.00 |
130,000.00 |
130,000.00 |
|
|
|
|
| 202-02-A-02 |
removal of bridges (sta. 510+00; 27.5' x 133')
|
1   |
EACH |
120,000.00 |
120,000.00 |
175,000.00 |
175,000.00 |
|
|
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
2,357.9 |
SQYD |
7.00 |
16,505.30 |
7.00 |
16,505.30 |
|
|
|
|
| 203-01 |
general excavation
|
3,600   |
CUYD |
6.00 |
21,600.00 |
12.00 |
43,200.00 |
|
|
|
|
| 203-02 |
drainage excavation
|
16,739   |
CUYD |
14.00 |
234,346.00 |
12.00 |
200,868.00 |
|
|
|
|
| 203-04 |
embankment
|
2,703   |
CUYD |
16.50 |
44,599.50 |
12.00 |
32,436.00 |
|
|
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
147   |
EACH |
100.00 |
14,700.00 |
30.00 |
4,410.00 |
|
|
|
|
| 204-05-B |
temporary sediment check dams (stone)
|
7   |
EACH |
500.00 |
3,500.00 |
300.00 |
2,100.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
3,716   |
LNFT |
4.00 |
14,864.00 |
3.00 |
11,148.00 |
|
|
|
|
| 302-02-A |
class ii base course (6" thick)
|
1,538.2 |
SQYD |
34.00 |
52,298.80 |
32.00 |
49,222.40 |
|
|
|
|
| 302-02-D |
class ii base course (12" thick)
|
2,829.5 |
SQYD |
42.00 |
118,839.00 |
55.00 |
155,622.50 |
|
|
|
|
| 304-01 |
lime
|
36.08 |
TON |
220.00 |
7,937.60 |
130.00 |
4,690.40 |
|
|
|
|
| 304-04-D |
lime treatment (type d) (12" thick)
|
2,545   |
SQYD |
15.00 |
38,175.00 |
10.00 |
25,450.00 |
|
|
|
|
| 305-01-D |
subgrade layer (12" thick)
|
2,545   |
SQYD |
20.00 |
50,900.00 |
22.00 |
55,990.00 |
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
27   |
CUYD |
200.00 |
5,400.00 |
120.00 |
3,240.00 |
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
30.0 |
CUYD |
200.00 |
6,000.00 |
110.00 |
3,300.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
725.0 |
TON |
100.00 |
72,500.00 |
100.00 |
72,500.00 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
137.1 |
TON |
120.00 |
16,452.00 |
150.00 |
20,565.00 |
|
|
|
|
| 701-06-B |
side drain pipe arch (18" equiv.)
|
36   |
LNFT |
60.00 |
2,160.00 |
60.00 |
2,160.00 |
|
|
|
|
| 701-06-D-01 |
side drain pipe arch (24" equiv.)(erosion)
|
100   |
LNFT |
75.00 |
7,500.00 |
80.00 |
8,000.00 |
|
|
|
|
| 701-06-E |
side drain pipe arch (30" equiv.)
|
24   |
LNFT |
98.00 |
2,352.00 |
85.00 |
2,040.00 |
|
|
|
|
| 702-08-A |
side drain safety end (type 1)
|
1.0 |
ea |
3,500.00 |
3,500.00 |
2,200.00 |
2,200.00 |
|
|
|
|
| 704-03 |
blocked out guard rail
|
300.0 |
LNFT |
22.00 |
6,600.00 |
18.00 |
5,400.00 |
|
|
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
200.0 |
LNFT |
60.00 |
12,000.00 |
50.00 |
10,000.00 |
|
|
|
|
| 704-11-A |
guard rail end treatment (flared)
|
8   |
EACH |
2,500.00 |
20,000.00 |
1,850.00 |
14,800.00 |
|
|
|
|
| 708-01 |
right-of-way monument
|
21   |
EACH |
200.00 |
4,200.00 |
200.00 |
4,200.00 |
|
|
|
|
| 708-02 |
right-of-way monument witness post
|
21   |
EACH |
200.00 |
4,200.00 |
200.00 |
4,200.00 |
|
|
|
|
| 711-01-C |
riprap (30 lb, 6" thick)
|
29   |
SQYD |
60.00 |
1,740.00 |
38.00 |
1,102.00 |
|
|
|
|
| 711-01-D |
riprap (55 lb, 24" thick)
|
3,800   |
SQYD |
81.50 |
309,700.00 |
74.00 |
281,200.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
100,000.00 |
100,000.00 |
70,000.00 |
70,000.00 |
|
|
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
2.312 |
MILE |
2,500.00 |
5,780.00 |
700.00 |
1,618.40 |
|
|
|
|
| 713-08 |
temporary precast concrete barrier (contractor
furnished) |
400   |
EACH |
300.00 |
120,000.00 |
900.00 |
360,000.00 |
|
|
|
|
| 713-09 |
temporary precast concrete barrier (department
furnished) |
400   |
EACH |
100.00 |
40,000.00 |
350.00 |
140,000.00 |
|
|
|
|
| 716-01-A |
mulch (vegetative)
|
1.00 |
ACRE |
2,000.00 |
2,000.00 |
1,200.00 |
1,200.00 |
|
|
|
|
| 717-01 |
seeding
|
397   |
LB |
10.00 |
3,970.00 |
8.00 |
3,176.00 |
|
|
|
|
| 718-01 |
fertilizer
|
9,261   |
LB |
0.50 |
4,630.50 |
0.50 |
4,630.50 |
|
|
|
|
| 720-01-A |
erosion control system, slope protection (type a)
|
2,150   |
SQYD |
1.75 |
3,762.50 |
3.00 |
6,450.00 |
|
|
|
|
| 720-01-C |
erosion control system, flexible channel liner (type c)
|
443   |
SQYD |
3.50 |
1,550.50 |
3.50 |
1,550.50 |
|
|
|
|
| 720-01-D |
erosion control system, flexible channel liner (type d)
|
438   |
SQYD |
3.50 |
1,533.00 |
5.00 |
2,190.00 |
|
|
|
|
| 720-01-E |
erosion control system, flexible channel liner (type e)
|
1,000   |
SQYD |
5.00 |
5,000.00 |
7.00 |
7,000.00 |
|
|
|
|
| 720-01-F |
erosion control system, flexible channel liner (type f)
|
29   |
SQYD |
5.00 |
145.00 |
12.00 |
348.00 |
|
|
|
|
| 722-01 |
project site laboratory
|
2   |
EACH |
2,000.00 |
4,000.00 |
6,000.00 |
12,000.00 |
|
|
|
|
| 725-02 |
temporary detour roads
|
8,602.4 |
SQYD |
110.00 |
946,264.00 |
80.00 |
688,192.00 |
|
|
|
|
| 726-01 |
bedding material
|
8.3 |
CUYD |
150.00 |
1,245.00 |
100.00 |
830.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
700,000.00 |
700,000.00 |
720,000.00 |
720,000.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
8   |
EACH |
100.00 |
800.00 |
75.00 |
600.00 |
|
|
|
|
| 731-01 |
nonreflectorized raised pavement markers
|
20   |
EACH |
15.00 |
300.00 |
12.00 |
240.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
89   |
EACH |
15.00 |
1,335.00 |
10.00 |
890.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
2.620 |
MILE |
4,000.00 |
10,480.00 |
2,500.00 |
6,550.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
170,000.00 |
170,000.00 |
160,000.00 |
160,000.00 |
|
|
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
40,000.00 |
40,000.00 |
8,000.00 |
8,000.00 |
|
|
|
|
| 804-01-C |
precast concrete piles (16")
|
4,536   |
LNFT |
70.00 |
317,520.00 |
65.00 |
294,840.00 |
|
|
|
|
| 804-01-F |
precast concrete piles (24")
|
4,900   |
LNFT |
118.00 |
578,200.00 |
120.00 |
588,000.00 |
|
|
|
|
| 805-01-F |
class a concrete (bents)
|
308.93 |
CUYD |
1,500.00 |
463,395.00 |
800.00 |
247,144.00 |
|
|
|
|
| 805-03 |
class aa concrete
|
842.86 |
CUYD |
900.00 |
758,574.00 |
550.00 |
463,573.00 |
|
|
|
|
| 805-08-H |
precast-prestressed concrete girders (type quad beam)
|
1,896.0 |
LNFT |
100.00 |
189,600.00 |
75.00 |
142,200.00 |
|
|
|
|
| 806-01 |
deformed reinforcing steel
|
239,777   |
LB |
0.75 |
179,832.75 |
0.80 |
191,821.60 |
|
|
|
|
| 807-06 |
structural metalwork
|
lump |
LUMP |
20,000.00 |
20,000.00 |
15,000.00 |
15,000.00 |
|
|
|
|
| 810-01 |
concrete railing (barrier)
|
800.00 |
LNFT |
65.00 |
52,000.00 |
60.00 |
48,000.00 |
|
|
|
|
| 813-01 |
concrete approach slabs
|
1,068.88 |
SQYD |
200.00 |
213,776.00 |
200.00 |
213,776.00 |
|
|
|
|
| S-001 |
temporary construction sheeting
|
lump |
LUMP |
830,000.00 |
830,000.00 |
1,200,000.00 |
1,200,000.00 |
|
|
|
|
| S-101 |
impact attenuators (construction zone)
|
4   |
EACH |
25,000.00 |
100,000.00 |
25,000.00 |
100,000.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
7,288,262.45 |
|
7,449,369.60 |
|
|
|
|
|