| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - JAMES CONSTRUCTION GROUP LLC |
- 2 - F. MILLER CONSTRUCTION LLC |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
150,000.00 |
150,000.00 |
168,000.00 |
168,000.00 |
|
|
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
10,000.00 |
10,000.00 |
49,000.00 |
49,000.00 |
|
|
|
|
| 202-02-A-01 |
removal of bridges (sta. 124+04; 25'x456' steel girder
bridge) |
1   |
EACH |
240,000.00 |
240,000.00 |
213,000.00 |
213,000.00 |
|
|
|
|
| 202-02-B-01 |
removal of concrete box culverts (sta. 124+40 rt.;
4.5'x3'x21' r.c. box) |
1   |
EACH |
2,000.00 |
2,000.00 |
6,900.00 |
6,900.00 |
|
|
|
|
| 202-02-C |
removal of portland cement concrete pavement
|
8,439   |
SQYD |
8.00 |
67,512.00 |
11.00 |
92,829.00 |
|
|
|
|
| 202-02-D |
removal of concrete walks & drives
|
304   |
SQYD |
18.00 |
5,472.00 |
48.00 |
14,592.00 |
|
|
|
|
| 202-02-E |
removal of concrete curbs
|
2,217.0 |
LNFT |
3.00 |
6,651.00 |
8.50 |
18,844.50 |
|
|
|
|
| 203-01 |
general excavation
|
3,107   |
CUYD |
12.00 |
37,284.00 |
6.75 |
20,972.25 |
|
|
|
|
| 203-02 |
drainage excavation
|
4,342   |
CUYD |
12.00 |
52,104.00 |
7.50 |
32,565.00 |
|
|
|
|
| 203-04 |
embankment
|
54,625   |
CUYD |
15.00 |
819,375.00 |
15.02 |
820,467.50 |
|
|
|
|
| 204-02 |
temporary hay or straw bales
|
738   |
EACH |
8.50 |
6,273.00 |
8.50 |
6,273.00 |
|
|
|
|
| 302-01 |
class ii base course
|
4,071.7 |
CUYD |
90.00 |
366,453.00 |
59.00 |
240,230.30 |
|
|
|
|
| 304-01 |
lime
|
217.12 |
TON |
135.00 |
29,311.20 |
222.00 |
48,200.64 |
|
|
|
|
| 304-04-B |
lime treatment (type d) (8.5" thick)
|
19,462   |
SQYD |
2.00 |
38,924.00 |
5.10 |
99,256.20 |
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
36   |
CUYD |
100.00 |
3,600.00 |
120.00 |
4,320.00 |
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
1,000.0 |
CUYD |
60.00 |
60,000.00 |
100.00 |
100,000.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
9,486.4 |
TON |
85.00 |
806,344.00 |
59.00 |
559,697.60 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
105.3 |
TON |
130.00 |
13,689.00 |
59.00 |
6,212.70 |
|
|
|
|
| 701-03-F |
storm drain pipe (15" rcp/pcp)
|
1,117   |
LNFT |
70.00 |
78,190.00 |
36.00 |
40,212.00 |
|
|
|
|
| 701-03-G |
storm drain pipe (18" rcp/pcp)
|
289   |
LNFT |
85.00 |
24,565.00 |
43.00 |
12,427.00 |
|
|
|
|
| 701-03-K |
storm drain pipe (30" rcp/pcp)
|
198   |
LNFT |
110.00 |
21,780.00 |
90.00 |
17,820.00 |
|
|
|
|
| 701-03-M |
storm drain pipe (36" rcp/pcp)
|
117   |
LNFT |
130.00 |
15,210.00 |
102.00 |
11,934.00 |
|
|
|
|
| 701-03-M-01 |
storm drain pipe (36" cmp) (outfall)
|
80   |
LNFT |
150.00 |
12,000.00 |
134.00 |
10,720.00 |
|
|
|
|
| 701-03-N |
storm drain pipe (42" rcp/pcp)
|
46   |
LNFT |
160.00 |
7,360.00 |
166.00 |
7,636.00 |
|
|
|
|
| 701-03-O |
storm drain pipe (48" rcp/pcp)
|
1,212   |
LNFT |
210.00 |
254,520.00 |
155.00 |
187,860.00 |
|
|
|
|
| 701-03-P |
storm drain pipe (54" rcp/pcp)
|
880   |
LNFT |
260.00 |
228,800.00 |
250.00 |
220,000.00 |
|
|
|
|
| 701-03-Q-01 |
storm drain pipe (60" cmp) (outfall)
|
80   |
LNFT |
290.00 |
23,200.00 |
200.00 |
16,000.00 |
|
|
|
|
| 701-05-G |
side drain pipe (18")
|
315   |
LNFT |
50.00 |
15,750.00 |
37.00 |
11,655.00 |
|
|
|
|
| 702-02-A |
manholes (mh-06)
|
4   |
EACH |
5,500.00 |
22,000.00 |
5,200.00 |
20,800.00 |
|
|
|
|
| 702-02-C |
manholes (r-cb-11 mod)
|
2   |
EACH |
7,000.00 |
14,000.00 |
9,300.00 |
18,600.00 |
|
|
|
|
| 702-03-A |
catch basins (cb-01)
|
13   |
EACH |
3,500.00 |
45,500.00 |
3,800.00 |
49,400.00 |
|
|
|
|
| 702-03-B |
catch basins (cb-02)
|
1   |
EACH |
6,500.00 |
6,500.00 |
7,300.00 |
7,300.00 |
|
|
|
|
| 702-03-C |
catch basins (cb-06)
|
21   |
EACH |
5,500.00 |
115,500.00 |
5,100.00 |
107,100.00 |
|
|
|
|
| 702-03-F |
catch basins (cb-08)
|
3   |
EACH |
10,000.00 |
30,000.00 |
11,800.00 |
35,400.00 |
|
|
|
|
| 702-04-A |
adjusting manholes
|
6   |
EACH |
1,400.00 |
8,400.00 |
4,100.00 |
24,600.00 |
|
|
|
|
| 704-03 |
blocked out guard rail
|
200.0 |
LNFT |
18.50 |
3,700.00 |
25.00 |
5,000.00 |
|
|
|
|
| 704-08-B |
guard rail transitions (double thrie-beam)
|
100.0 |
LNFT |
50.00 |
5,000.00 |
75.00 |
7,500.00 |
|
|
|
|
| 704-11-A |
guard rail end treatment (flared)
|
4   |
EACH |
2,000.00 |
8,000.00 |
2,700.00 |
10,800.00 |
|
|
|
|
| 705-02 |
combination mesh & barbed wire fence
|
28   |
LNFT |
50.00 |
1,400.00 |
70.00 |
1,960.00 |
|
|
|
|
| 705-04 |
single swinging driveway gates
|
1   |
EACH |
600.00 |
600.00 |
1,300.00 |
1,300.00 |
|
|
|
|
| 706-02-C |
concrete drive (6" thick)
|
695.3 |
SQYD |
55.00 |
38,241.50 |
61.00 |
42,413.30 |
|
|
|
|
| 707-03 |
combination concrete curb & gutter
|
2,949.0 |
LNFT |
35.00 |
103,215.00 |
27.00 |
79,623.00 |
|
|
|
|
| 708-01 |
right-of-way monument
|
2   |
EACH |
200.00 |
400.00 |
2,100.00 |
4,200.00 |
|
|
|
|
| 708-02 |
right-of-way monument witness post
|
2   |
EACH |
200.00 |
400.00 |
2,100.00 |
4,200.00 |
|
|
|
|
| 712-04 |
flexible revetment
|
736   |
SQYD |
65.00 |
47,840.00 |
86.00 |
63,296.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
60,000.00 |
60,000.00 |
62,900.00 |
62,900.00 |
|
|
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
4.560 |
MILE |
600.00 |
2,736.00 |
3,200.00 |
14,592.00 |
|
|
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
4.560 |
MILE |
835.00 |
3,807.60 |
780.00 |
3,556.80 |
|
|
|
|
| 717-01 |
seeding
|
322   |
LB |
8.50 |
2,737.00 |
12.00 |
3,864.00 |
|
|
|
|
| 718-01 |
fertilizer
|
10,750   |
LB |
0.25 |
2,687.50 |
0.35 |
3,762.50 |
|
|
|
|
| 722-01 |
project site laboratory
|
1   |
EACH |
6,000.00 |
6,000.00 |
5,000.00 |
5,000.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
635,000.00 |
635,000.00 |
600,000.00 |
600,000.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
4   |
EACH |
75.00 |
300.00 |
100.00 |
400.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
506   |
EACH |
4.75 |
2,403.50 |
6.00 |
3,036.00 |
|
|
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
818   |
LNFT |
1.00 |
818.00 |
1.30 |
1,063.40 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
370   |
LNFT |
3.00 |
1,110.00 |
4.00 |
1,480.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
2.175 |
MILE |
2,500.00 |
5,437.50 |
3,400.00 |
7,395.00 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
1.822 |
MILE |
800.00 |
1,457.60 |
1,100.00 |
2,004.20 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
100,000.00 |
100,000.00 |
126,000.00 |
126,000.00 |
|
|
|
|
| 741-09 |
adjusting water house connections
|
4   |
EACH |
500.00 |
2,000.00 |
2,700.00 |
10,800.00 |
|
|
|
|
| 804-01-D |
precast concrete piles (18")
|
1,820   |
LNFT |
60.00 |
109,200.00 |
60.00 |
109,200.00 |
|
|
|
|
| 804-01-F |
precast concrete piles (24")
|
5,530   |
LNFT |
95.00 |
525,350.00 |
115.70 |
639,821.00 |
|
|
|
|
| 804-05 |
precast concrete test piles
|
1   |
EACH |
20,000.00 |
20,000.00 |
27,000.00 |
27,000.00 |
|
|
|
|
| 804-09 |
loading test piles
|
1   |
EACH |
5,000.00 |
5,000.00 |
25,000.00 |
25,000.00 |
|
|
|
|
| 804-10 |
reloading test piles
|
1   |
EACH |
1,000.00 |
1,000.00 |
6,000.00 |
6,000.00 |
|
|
|
|
| 804-11 |
redriving test piles
|
1   |
EACH |
500.00 |
500.00 |
100.00 |
100.00 |
|
|
|
|
| 804-12 |
loading permanent piles
|
1   |
EACH |
500.00 |
500.00 |
100.00 |
100.00 |
|
|
|
|
| 804-17 |
dynamic monitoring
|
3   |
EACH |
2,000.00 |
6,000.00 |
2,200.00 |
6,600.00 |
|
|
|
|
| 805-01-F |
class a concrete (bents)
|
371.14 |
CUYD |
700.00 |
259,798.00 |
650.00 |
241,241.00 |
|
|
|
|
| 805-03 |
class aa concrete
|
921.10 |
CUYD |
650.00 |
598,715.00 |
845.00 |
778,329.50 |
|
|
|
|
| 805-08-B |
precast-prestressed concrete girder (type ii)
|
4,455.0 |
LNFT |
85.00 |
378,675.00 |
141.00 |
628,155.00 |
|
|
|
|
| 805-11 |
strip seal joints
|
210.00 |
LNFT |
150.00 |
31,500.00 |
150.00 |
31,500.00 |
|
|
|
|
| 806-01 |
deformed reinforcing steel
|
285,126   |
LB |
1.00 |
285,126.00 |
0.84 |
239,505.84 |
|
|
|
|
| 807-06 |
structural metalwork
|
lump |
LUMP |
5,000.00 |
5,000.00 |
2,400.00 |
2,400.00 |
|
|
|
|
| 810-01 |
concrete railing (barrier)
|
1,048.00 |
LNFT |
60.00 |
62,880.00 |
63.00 |
66,024.00 |
|
|
|
|
| 813-01 |
concrete approach slabs
|
622.22 |
SQYD |
170.00 |
105,777.40 |
255.00 |
158,666.10 |
|
|
|
|
| S-101 |
dynamic analysis
|
3   |
EACH |
1,000.00 |
3,000.00 |
1,200.00 |
3,600.00 |
|
|
|
|
| S-102 |
retroflective sheeting panels
|
lump |
LUMP |
3,000.00 |
3,000.00 |
5,000.00 |
5,000.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
7,074,579.80 |
|
7,335,213.33 |
|
|
|
|
|