| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - AUSTIN BRIDGE & ROAD, LP |
- 2 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 3 - GILCHRIST CONSTRUCTION CO. LLC |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
1,480,000.00 |
1,480,000.00 |
1,000,000.00 |
1,000,000.00 |
1,600,000.00 |
1,600,000.00 |
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
5,000.00 |
5,000.00 |
100,000.00 |
100,000.00 |
50,000.00 |
50,000.00 |
|
|
| 202-02-B-01 |
removal of concrete box culverts(sta. 96+96,1-3'x3')
|
1   |
EACH |
3,000.00 |
3,000.00 |
3,000.00 |
3,000.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-B-02 |
removal of concrete box culverts(sta. 104+55,2-4'x4')
|
1   |
EACH |
8,000.00 |
8,000.00 |
3,000.00 |
3,000.00 |
9,000.00 |
9,000.00 |
|
|
| 202-02-B-03 |
removal of concrete box culverts(sta. 132+48,1-4'x3')
|
1   |
EACH |
3,000.00 |
3,000.00 |
3,000.00 |
3,000.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-B-04 |
removal of concrete box culverts(sta. 150+60,1-3'x3')
|
1   |
EACH |
2,000.00 |
2,000.00 |
3,000.00 |
3,000.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-B-05 |
removal of concrete box culverts(sta. 184+41,1-5'x4')
|
1   |
EACH |
4,500.00 |
4,500.00 |
3,000.00 |
3,000.00 |
7,500.00 |
7,500.00 |
|
|
| 202-02-B-06 |
removal of concrete box culverts(sta. 219+91,1-4'x2')
|
1   |
EACH |
3,500.00 |
3,500.00 |
3,000.00 |
3,000.00 |
6,000.00 |
6,000.00 |
|
|
| 202-02-B-07 |
removal of concrete box culverts(sta. 263+50,1-2'x3')
|
1   |
EACH |
3,000.00 |
3,000.00 |
3,000.00 |
3,000.00 |
4,500.00 |
4,500.00 |
|
|
| 202-02-B-08 |
removal of concrete box culverts(sta. 275+26,2-4'x5')
|
1   |
EACH |
9,000.00 |
9,000.00 |
3,000.00 |
3,000.00 |
10,000.00 |
10,000.00 |
|
|
| 202-02-B-09 |
removal of concrete box culverts(sta. 362+63,1-4'x4')
|
1   |
EACH |
9,500.00 |
9,500.00 |
3,000.00 |
3,000.00 |
10,000.00 |
10,000.00 |
|
|
| 202-02-B-10 |
removal of concrete box culverts(sta. 386+67,2-4'x4')
|
1   |
EACH |
7,500.00 |
7,500.00 |
3,000.00 |
3,000.00 |
10,000.00 |
10,000.00 |
|
|
| 202-02-B-11 |
removal of concrete box culverts(sta. 409+08,1-4'x3')
|
1   |
EACH |
3,000.00 |
3,000.00 |
3,000.00 |
3,000.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-B-12 |
removal of concrete box culverts(sta. 421+38,1-4'x3')
|
1   |
EACH |
2,000.00 |
2,000.00 |
3,000.00 |
3,000.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-B-13 |
removal of concrete box culverts(sta. 429+36,1-3'x3')
|
1   |
EACH |
8,000.00 |
8,000.00 |
3,000.00 |
3,000.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-C |
removal of portland cement concrete pavement
|
140,344   |
SQYD |
3.95 |
554,358.80 |
4.25 |
596,462.00 |
5.00 |
701,720.00 |
|
|
| 202-02-D |
removal of concrete walks & drives
|
3,832   |
SQYD |
7.08 |
27,130.56 |
5.00 |
19,160.00 |
12.00 |
45,984.00 |
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
13,477.8 |
SQYD |
3.20 |
43,128.96 |
3.25 |
43,802.85 |
3.00 |
40,433.40 |
|
|
| 202-02-I |
removal of asphalt drives
|
3,523.0 |
SQYD |
4.53 |
15,959.19 |
5.00 |
17,615.00 |
5.00 |
17,615.00 |
|
|
| 202-02-01 |
removal of 1491 sq. ft. wood frame residence on piers
(lt. of sta. 111+50) |
1   |
EACH |
4,500.00 |
4,500.00 |
1,000.00 |
1,000.00 |
4,000.00 |
4,000.00 |
|
|
| 202-02-02 |
removal of 1334 sq. ft. wood/metal barn on concrete
slab (lt. of sta. 113+40) |
1   |
EACH |
3,000.00 |
3,000.00 |
1,000.00 |
1,000.00 |
4,000.00 |
4,000.00 |
|
|
| 202-02-03 |
removal of 930 sq. ft. metal commercial building on
slab (lt. of sta. 116+30) |
1   |
EACH |
2,000.00 |
2,000.00 |
1,000.00 |
1,000.00 |
4,000.00 |
4,000.00 |
|
|
| 202-02-04 |
removal of sign (welcome to florien)(lt. of sta.
118+00) |
1   |
EACH |
1.00 |
1.00 |
100.00 |
100.00 |
500.00 |
500.00 |
|
|
| 202-02-05 |
removal of sign (gulf industries)(lt. of sta. 160+00)
|
1   |
EACH |
1.00 |
1.00 |
100.00 |
100.00 |
500.00 |
500.00 |
|
|
| 202-02-06 |
removal of sign (rt. of sta. 174+50)
|
1   |
EACH |
1.00 |
1.00 |
100.00 |
100.00 |
500.00 |
500.00 |
|
|
| 202-02-07 |
removal of three signs (lt. of sta. 206+00)
|
1   |
EACH |
1.00 |
1.00 |
100.00 |
100.00 |
500.00 |
500.00 |
|
|
| 202-02-08 |
removal of billboard (rt. of sta. 204+00)
|
1   |
EACH |
1,500.00 |
1,500.00 |
100.00 |
100.00 |
2,000.00 |
2,000.00 |
|
|
| 202-02-09 |
removal of sign (lt. of sta. 208+00)
|
1   |
EACH |
1.00 |
1.00 |
100.00 |
100.00 |
500.00 |
500.00 |
|
|
| 202-02-10 |
removal of signs (rt. of sta. 224+00)
|
1   |
EACH |
1,000.00 |
1,000.00 |
100.00 |
100.00 |
500.00 |
500.00 |
|
|
| 202-02-11 |
removal of 3660 sq. ft. metal frame commercial
building on concrete slab (rt. of sta. 342+60) |
1   |
EACH |
5,000.00 |
5,000.00 |
5,000.00 |
5,000.00 |
8,500.00 |
8,500.00 |
|
|
| 202-02-12 |
removal of 1256 sq. ft. brick residence on concrete
slab (rt. of sta. 352+00) |
1   |
EACH |
3,500.00 |
3,500.00 |
2,000.00 |
2,000.00 |
4,000.00 |
4,000.00 |
|
|
| 202-02-13 |
removal of billboard (rt. of sta. 365+00)
|
1   |
EACH |
1,000.00 |
1,000.00 |
500.00 |
500.00 |
2,000.00 |
2,000.00 |
|
|
| 202-02-14 |
removal of sign (welcome to many)(rt. of sta. 380+00)
|
1   |
EACH |
1.00 |
1.00 |
100.00 |
100.00 |
500.00 |
500.00 |
|
|
| 202-02-15 |
removal of sign (ford)(lt. of sta.390+00)
|
1   |
EACH |
2,000.00 |
2,000.00 |
100.00 |
100.00 |
1,000.00 |
1,000.00 |
|
|
| 202-02-16 |
removal of sign (ford)(lt. of sta. 391+40)
|
1   |
EACH |
500.00 |
500.00 |
100.00 |
100.00 |
1,000.00 |
1,000.00 |
|
|
| 202-02-17 |
removal of sign (ford)(lt. of sta. 392+30)
|
1   |
EACH |
3,000.00 |
3,000.00 |
3,000.00 |
3,000.00 |
1,000.00 |
1,000.00 |
|
|
| 202-02-18 |
removal of sign (ford)(lt. of sta. 393+30)
|
1   |
EACH |
1,000.00 |
1,000.00 |
500.00 |
500.00 |
1,000.00 |
1,000.00 |
|
|
| 202-02-19 |
removal of sign (prism)(rt. of sta. 393+50)
|
1   |
EACH |
100.00 |
100.00 |
1,000.00 |
1,000.00 |
1,000.00 |
1,000.00 |
|
|
| 202-02-20 |
removal of sign (lt. of sta. 401+00)
|
1   |
EACH |
1.00 |
1.00 |
3,000.00 |
3,000.00 |
1,000.00 |
1,000.00 |
|
|
| 202-02-21 |
removal of sign (lt. of sta. 404+20)
|
1   |
EACH |
1.00 |
1.00 |
1,000.00 |
1,000.00 |
1,000.00 |
1,000.00 |
|
|
| 202-02-22 |
removal of 2580 sq. ft. metal commercial building on
slab (rt. of sta. 410+50) |
1   |
EACH |
7,750.00 |
7,750.00 |
7,000.00 |
7,000.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-23 |
removal of shelter (rt. of sta. 417+00)
|
1   |
EACH |
1.00 |
1.00 |
1.00 |
1.00 |
4,000.00 |
4,000.00 |
|
|
| 202-02-24 |
removal of all buildings, parcels 17-07 and 17-07ur
(rt. of sta. 426+00) |
1   |
EACH |
3,000.00 |
3,000.00 |
3,000.00 |
3,000.00 |
4,000.00 |
4,000.00 |
|
|
| 202-02-25 |
removal of 1057 sq. ft. wood frame residence on piers
(rt. of sta. 426+50) |
1   |
EACH |
2,500.00 |
2,500.00 |
2,000.00 |
2,000.00 |
4,000.00 |
4,000.00 |
|
|
| 202-02-26 |
removal of 747 sq. ft. asbestos siding residence on
piers (rt. of sta. 427+20) |
1   |
EACH |
4,000.00 |
4,000.00 |
100.00 |
100.00 |
4,000.00 |
4,000.00 |
|
|
| 202-02-27 |
removal of 5489 sq. ft. metal storage building on slab
(rt. of sta. 429+00) |
1   |
EACH |
16,000.00 |
16,000.00 |
1,000.00 |
1,000.00 |
4,000.00 |
4,000.00 |
|
|
| 202-02-28 |
removal of 983 sq. ft. wood frame residence on piers
(rt. of sta.431+80) |
1   |
EACH |
2,500.00 |
2,500.00 |
1,000.00 |
1,000.00 |
4,000.00 |
4,000.00 |
|
|
| 202-02-29 |
removal of 2220 sq. ft. wood frame commercial building
on piers (rt. of sta. 434+00) |
1   |
EACH |
4,400.00 |
4,400.00 |
1,000.00 |
1,000.00 |
4,000.00 |
4,000.00 |
|
|
| 202-02-30 |
removal of 1501 sq. ft. concrete commercial building
on slab (rt. of sta. 434+50) |
1   |
EACH |
3,800.00 |
3,800.00 |
1,000.00 |
1,000.00 |
4,000.00 |
4,000.00 |
|
|
| 202-02-31 |
removal of sign (sta. rt. of sta. 436+00)
|
1   |
EACH |
1.00 |
1.00 |
100.00 |
100.00 |
500.00 |
500.00 |
|
|
| 202-03 |
relocation of cattle guard (lt. of sta. 434+63)
|
1   |
EACH |
1,000.00 |
1,000.00 |
9,000.00 |
9,000.00 |
4,000.00 |
4,000.00 |
|
|
| 203-01 |
general excavation
|
1,142,806   |
CUYD |
3.20 |
3,656,979.20 |
4.00 |
4,571,224.00 |
4.00 |
4,571,224.00 |
|
|
| 203-02 |
drainage excavation
|
10,178   |
CUYD |
6.00 |
61,068.00 |
6.24 |
63,510.72 |
12.00 |
122,136.00 |
|
|
| 203-04 |
embankment
|
689,362   |
CUYD |
2.30 |
1,585,532.60 |
3.55 |
2,447,235.10 |
7.00 |
4,825,534.00 |
|
|
| 203-05-A |
nonplastic embankment (stone)
|
1,124   |
CUYD |
90.40 |
101,609.60 |
85.00 |
95,540.00 |
110.00 |
123,640.00 |
|
|
| 204-02 |
temporary hay or straw bales
|
1,576   |
EACH |
5.50 |
8,668.00 |
15.00 |
23,640.00 |
25.00 |
39,400.00 |
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
193   |
EACH |
75.00 |
14,475.00 |
300.00 |
57,900.00 |
250.00 |
48,250.00 |
|
|
| 204-05-B |
temporary sediment check dams (stone)
|
154   |
EACH |
350.00 |
53,900.00 |
550.00 |
84,700.00 |
800.00 |
123,200.00 |
|
|
| 204-06 |
temporary silt fencing
|
29,491   |
LNFT |
1.50 |
44,236.50 |
4.00 |
117,964.00 |
5.00 |
147,455.00 |
|
|
| 302-01 |
class ii base course
|
84,523.4 |
CUYD |
43.36 |
3,664,934.62 |
60.00 |
5,071,404.00 |
28.00 |
2,366,655.20 |
|
|
| 304-01 |
lime
|
3,735.86 |
TON |
1.00 |
3,735.86 |
10.00 |
37,358.60 |
150.00 |
560,379.00 |
|
|
| 304-04-D |
lime treatment (type d) (12" thick)
|
263,553   |
SQYD |
0.01 |
2,635.53 |
0.50 |
131,776.50 |
1.00 |
263,553.00 |
|
|
| 305-01-C |
subgrade layer (10" thick)
|
283,045.0 |
SQYD |
4.08 |
1,154,823.60 |
6.00 |
1,698,270.00 |
8.00 |
2,264,360.00 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
9,366   |
CUYD |
21.94 |
205,490.04 |
16.00 |
149,856.00 |
85.00 |
796,110.00 |
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
1,000.0 |
CUYD |
65.00 |
65,000.00 |
65.00 |
65,000.00 |
60.00 |
60,000.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
63,915.2 |
TON |
77.75 |
4,969,406.80 |
70.00 |
4,474,064.00 |
88.00 |
5,624,537.60 |
|
|
| 502-01-A |
superpave asphaltic concrete drives, turnouts and
miscellaneous |
5,415.1 |
TON |
84.15 |
455,680.67 |
95.00 |
514,434.50 |
140.00 |
758,114.00 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
140,344   |
SQYD |
1.60 |
224,550.40 |
2.25 |
315,774.00 |
2.00 |
280,688.00 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 13,645   |
CUYD |
0.01 |
- 136.45 |
0.10 |
- 1,364.50 |
0.01 |
- 136.45 |
|
|
| 601-01-K |
portland cement concrete pavement (10" thick)
|
58,271.1 |
SQYD |
60.21 |
3,508,502.93 |
56.00 |
3,263,181.60 |
65.00 |
3,787,621.50 |
|
|
| 601-01-M |
portland cement concrete pavement (11" thick)
|
8,415.0 |
SQYD |
68.50 |
576,427.50 |
61.00 |
513,315.00 |
85.00 |
715,275.00 |
|
|
| 601-02-K |
portland cement concrete pavement (10" thick)
(crossovers & turnouts) |
3,188.1 |
SQYD |
74.81 |
238,501.76 |
71.00 |
226,355.10 |
80.00 |
255,048.00 |
|
|
| 601-04 |
portland cement concrete pavement coring
|
18   |
EACH |
125.00 |
2,250.00 |
160.00 |
2,880.00 |
100.00 |
1,800.00 |
|
|
| 701-01-G |
cross drain pipe (18" rcp)
|
218   |
LNFT |
45.00 |
9,810.00 |
60.00 |
13,080.00 |
80.00 |
17,440.00 |
|
|
| 701-01-I |
cross drain pipe (24" rcp)
|
537   |
LNFT |
60.00 |
32,220.00 |
70.00 |
37,590.00 |
90.00 |
48,330.00 |
|
|
| 701-01-K |
cross drain pipe (30" rcp)
|
1,022   |
LNFT |
75.00 |
76,650.00 |
80.00 |
81,760.00 |
100.00 |
102,200.00 |
|
|
| 701-01-M |
cross drain pipe (36" rcp)
|
815   |
LNFT |
90.00 |
73,350.00 |
100.00 |
81,500.00 |
120.00 |
97,800.00 |
|
|
| 701-01-N |
cross drain pipe (42" rcp)
|
1,504   |
LNFT |
110.00 |
165,440.00 |
145.00 |
218,080.00 |
165.00 |
248,160.00 |
|
|
| 701-01-O |
cross drain pipe (48" rcp)
|
2,066   |
LNFT |
150.00 |
309,900.00 |
165.00 |
340,890.00 |
190.00 |
392,540.00 |
|
|
| 701-01-P |
cross drain pipe (54" rcp)
|
174   |
LNFT |
240.00 |
41,760.00 |
180.00 |
31,320.00 |
275.00 |
47,850.00 |
|
|
| 701-01-S-01 |
cross drain pipe (72" rcp)(class iv)
|
760   |
LNFT |
500.00 |
380,000.00 |
400.00 |
304,000.00 |
470.00 |
357,200.00 |
|
|
| 701-02-D |
cross drain pipe arch (24" equiv. rcpa)
|
440   |
LNFT |
85.00 |
37,400.00 |
75.00 |
33,000.00 |
100.00 |
44,000.00 |
|
|
| 701-02-E |
cross drain pipe arch (30" equiv. rcpa)
|
273   |
LNFT |
100.00 |
27,300.00 |
100.00 |
27,300.00 |
158.00 |
43,134.00 |
|
|
| 701-02-F |
cross drain pipe arch (36" equiv. rcpa)
|
106   |
LNFT |
110.00 |
11,660.00 |
125.00 |
13,250.00 |
200.00 |
21,200.00 |
|
|
| 701-02-G |
cross drain pipe arch (42" equiv. rcpa)
|
238   |
LNFT |
140.00 |
33,320.00 |
155.00 |
36,890.00 |
210.00 |
49,980.00 |
|
|
| 701-02-I |
cross drain pipe arch (54" equiv. rcpa)
|
256   |
LNFT |
200.00 |
51,200.00 |
215.00 |
55,040.00 |
270.00 |
69,120.00 |
|
|
| 701-03-F |
storm drain pipe (15" rcp)
|
7,348   |
LNFT |
40.00 |
293,920.00 |
40.00 |
293,920.00 |
78.00 |
573,144.00 |
|
|
| 701-03-G |
storm drain pipe (18" rcp)
|
3,571   |
LNFT |
45.00 |
160,695.00 |
50.00 |
178,550.00 |
82.00 |
292,822.00 |
|
|
| 701-03-I |
storm drain pipe (24" rcp)
|
550   |
LNFT |
60.00 |
33,000.00 |
70.00 |
38,500.00 |
100.00 |
55,000.00 |
|
|
| 701-03-K |
storm drain pipe (30" rcp)
|
95   |
LNFT |
75.00 |
7,125.00 |
90.00 |
8,550.00 |
110.00 |
10,450.00 |
|
|
| 701-05-F |
side drain pipe (15" rcp)
|
26   |
LNFT |
40.00 |
1,040.00 |
60.00 |
1,560.00 |
95.00 |
2,470.00 |
|
|
| 701-05-G |
side drain pipe (18" rcp)
|
909   |
LNFT |
45.00 |
40,905.00 |
70.00 |
63,630.00 |
58.00 |
52,722.00 |
|
|
| 701-05-I |
side drain pipe (24" rcp)
|
362   |
LNFT |
60.00 |
21,720.00 |
100.00 |
36,200.00 |
76.00 |
27,512.00 |
|
|
| 701-05-I-01 |
side drain pipe (24")(erosion)
|
48   |
LNFT |
60.00 |
2,880.00 |
75.00 |
3,600.00 |
55.00 |
2,640.00 |
|
|
| 701-05-K |
side drain pipe (30" rcp)
|
145   |
LNFT |
75.00 |
10,875.00 |
100.00 |
14,500.00 |
95.00 |
13,775.00 |
|
|
| 701-05-M |
side drain pipe (36" rcp)
|
72   |
LNFT |
90.00 |
6,480.00 |
120.00 |
8,640.00 |
135.00 |
9,720.00 |
|
|
| 701-06-B |
side drain pipe arch (18" equiv.)
|
256   |
LNFT |
75.00 |
19,200.00 |
65.00 |
16,640.00 |
78.00 |
19,968.00 |
|
|
| 701-06-D |
side drain pipe arch (24" equiv.)
|
44   |
LNFT |
85.00 |
3,740.00 |
95.00 |
4,180.00 |
120.00 |
5,280.00 |
|
|
| 702-02-A |
manholes (mh-06)
|
4   |
EACH |
3,000.00 |
12,000.00 |
5,500.00 |
22,000.00 |
12,000.00 |
48,000.00 |
|
|
| 702-02-C |
manholes (r-cb-11 mod)
|
2   |
EACH |
3,500.00 |
7,000.00 |
6,000.00 |
12,000.00 |
8,000.00 |
16,000.00 |
|
|
| 702-02-E-01 |
manholes (r-cb-32)(mod)
|
1   |
EACH |
3,500.00 |
3,500.00 |
6,000.00 |
6,000.00 |
8,500.00 |
8,500.00 |
|
|
| 702-02-G |
manholes (r-cb-36)
|
7   |
EACH |
4,000.00 |
28,000.00 |
6,000.00 |
42,000.00 |
4,500.00 |
31,500.00 |
|
|
| 702-03-A |
catch basins (cb-01)
|
37   |
EACH |
2,500.00 |
92,500.00 |
3,000.00 |
111,000.00 |
4,000.00 |
148,000.00 |
|
|
| 702-03-B |
catch basins (cb-02)
|
1   |
EACH |
3,700.00 |
3,700.00 |
7,500.00 |
7,500.00 |
6,800.00 |
6,800.00 |
|
|
| 702-03-C |
catch basins (cb-06)
|
45   |
EACH |
4,000.00 |
180,000.00 |
4,500.00 |
202,500.00 |
7,000.00 |
315,000.00 |
|
|
| 702-03-D |
catch basins (cb-07)
|
59   |
EACH |
4,200.00 |
247,800.00 |
6,000.00 |
354,000.00 |
8,500.00 |
501,500.00 |
|
|
| 702-03-F |
catch basins (cb-08)
|
27   |
EACH |
7,000.00 |
189,000.00 |
8,500.00 |
229,500.00 |
12,000.00 |
324,000.00 |
|
|
| 703-01 |
shoulder underdrain systems
|
18,113   |
LNFT |
10.34 |
187,288.42 |
7.00 |
126,791.00 |
12.00 |
217,356.00 |
|
|
| 705-01 |
barbed wire fence
|
3,721   |
LNFT |
5.00 |
18,605.00 |
5.50 |
20,465.50 |
6.00 |
22,326.00 |
|
|
| 705-02 |
combination mesh & barbed wire fence
|
1,774   |
LNFT |
11.50 |
20,401.00 |
6.00 |
10,644.00 |
7.00 |
12,418.00 |
|
|
| 705-03 |
single swinging walk gates
|
2   |
EACH |
525.00 |
1,050.00 |
550.00 |
1,100.00 |
600.00 |
1,200.00 |
|
|
| 705-06-A |
chain link fence (4-foot height)
|
230   |
LNFT |
18.00 |
4,140.00 |
17.00 |
3,910.00 |
20.00 |
4,600.00 |
|
|
| 705-06-B |
chain link fence (5-foot height)
|
43   |
LNFT |
20.00 |
860.00 |
32.00 |
1,376.00 |
35.00 |
1,505.00 |
|
|
| 705-06-D |
chain link fence (7-foot height)
|
14   |
LNFT |
25.00 |
350.00 |
54.00 |
756.00 |
55.00 |
770.00 |
|
|
| 705-09 |
rebuilt fence
|
595   |
LNFT |
28.00 |
16,660.00 |
30.00 |
17,850.00 |
13.00 |
7,735.00 |
|
|
| 706-02-C |
concrete drive (6" thick)
|
5,606.7 |
SQYD |
53.96 |
302,537.53 |
45.00 |
252,301.50 |
50.00 |
280,335.00 |
|
|
| 707-01-A |
concrete curb (mountable)
|
18,558.0 |
LNFT |
5.06 |
93,903.48 |
9.00 |
167,022.00 |
10.00 |
185,580.00 |
|
|
| 707-01-B |
concrete curb (barrier)
|
1,393.5 |
LNFT |
6.85 |
9,545.48 |
13.00 |
18,115.50 |
12.00 |
16,722.00 |
|
|
| 708-01 |
right-of-way monument
|
338   |
EACH |
200.00 |
67,600.00 |
100.00 |
33,800.00 |
350.00 |
118,300.00 |
|
|
| 708-02 |
right-of-way monument witness post
|
217   |
EACH |
200.00 |
43,400.00 |
100.00 |
21,700.00 |
350.00 |
75,950.00 |
|
|
| 710-01 |
flowable fill
|
350   |
CUYD |
155.45 |
54,407.50 |
100.00 |
35,000.00 |
150.00 |
52,500.00 |
|
|
| 711-01-C |
riprap (30 lb)
|
1,247   |
SQYD |
153.61 |
191,551.67 |
68.00 |
84,796.00 |
100.00 |
124,700.00 |
|
|
| 711-04 |
geotextile fabric
|
1,247   |
SQYD |
16.29 |
20,313.63 |
1.00 |
1,247.00 |
2.00 |
2,494.00 |
|
|
| 712-01-A |
concrete cast-in-place revetment
|
480   |
SQYD |
61.42 |
29,481.60 |
120.00 |
57,600.00 |
65.00 |
31,200.00 |
|
|
| 712-02 |
sacked concrete revetment
|
411   |
SQYD |
270.65 |
111,237.15 |
68.00 |
27,948.00 |
65.00 |
26,715.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
500,000.00 |
500,000.00 |
200,000.00 |
200,000.00 |
260,000.00 |
260,000.00 |
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
18.051 |
MILE |
774.09 |
13,973.10 |
830.00 |
14,982.33 |
800.00 |
14,440.80 |
|
|
| 713-08 |
temporary precast concrete barrier (contractor
furnished) |
499   |
EACH |
894.90 |
446,555.10 |
950.00 |
474,050.00 |
900.00 |
449,100.00 |
|
|
| 716-01-A |
mulch (vegetative)
|
3.05 |
ACRE |
2,000.00 |
6,100.00 |
965.00 |
2,943.25 |
1,000.00 |
3,050.00 |
|
|
| 717-01 |
seeding
|
14,947   |
LB |
6.00 |
89,682.00 |
7.50 |
112,102.50 |
7.60 |
113,597.20 |
|
|
| 718-01 |
fertilizer
|
249,116   |
LB |
0.22 |
54,805.52 |
0.27 |
67,261.32 |
0.30 |
74,734.80 |
|
|
| 718-02 |
agricultural lime
|
249.0 |
TON |
67.91 |
16,909.59 |
85.00 |
21,165.00 |
95.00 |
23,655.00 |
|
|
| 720-01-A |
erosion control system, slope protection (type a)
|
69,880   |
SQYD |
1.20 |
83,856.00 |
2.00 |
139,760.00 |
1.30 |
90,844.00 |
|
|
| 720-01-C |
erosion control system, flexible channel liner (type c)
|
6,706   |
SQYD |
1.50 |
10,059.00 |
3.00 |
20,118.00 |
3.00 |
20,118.00 |
|
|
| 720-01-D |
erosion control system, flexible channel liner (type d)
|
15,502   |
SQYD |
2.00 |
31,004.00 |
3.00 |
46,506.00 |
3.00 |
46,506.00 |
|
|
| 720-01-E |
erosion control system, flexible channel liner (type e)
|
3,940   |
SQYD |
2.00 |
7,880.00 |
3.50 |
13,790.00 |
4.15 |
16,351.00 |
|
|
| 720-01-F |
erosion control system, flexible channel liner (type f)
|
1,648   |
SQYD |
2.00 |
3,296.00 |
3.50 |
5,768.00 |
4.00 |
6,592.00 |
|
|
| 722-02 |
project site laboratory (equipped)
|
1   |
EACH |
20,000.00 |
20,000.00 |
50,000.00 |
50,000.00 |
100,000.00 |
100,000.00 |
|
|
| 725-02 |
temporary detour roads
|
22,491.1 |
SQYD |
31.63 |
711,393.49 |
35.00 |
787,188.50 |
60.00 |
1,349,466.00 |
|
|
| 726-01 |
bedding material
|
10,167.9 |
CUYD |
70.00 |
711,753.00 |
75.00 |
762,592.50 |
80.00 |
813,432.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
3,400,000.00 |
3,400,000.00 |
3,000,000.00 |
3,000,000.00 |
4,000,000.00 |
4,000,000.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
46   |
EACH |
90.00 |
4,140.00 |
80.00 |
3,680.00 |
90.00 |
4,140.00 |
|
|
| 729-19-C |
dead end installations (type a)
|
2   |
EACH |
2,000.00 |
4,000.00 |
2,000.00 |
4,000.00 |
2,200.00 |
4,400.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
2,973   |
EACH |
5.17 |
15,370.41 |
5.50 |
16,351.50 |
5.50 |
16,351.50 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
876   |
LNFT |
2.94 |
2,575.44 |
3.00 |
2,628.00 |
3.00 |
2,628.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
28.616 |
MILE |
2,399.39 |
68,660.94 |
2,500.00 |
71,540.00 |
2,500.00 |
71,540.00 |
|
|
| 732-03-A |
plastic pavement striping (broken line) (4" width)
|
4.166 |
MILE |
696.99 |
2,903.66 |
750.00 |
3,124.50 |
700.00 |
2,916.20 |
|
|
| 732-04-A |
plastic pavement legends and symbols (arrow)
|
299   |
EACH |
157.25 |
47,017.75 |
168.00 |
50,232.00 |
160.00 |
47,840.00 |
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
108   |
EACH |
197.84 |
21,366.72 |
200.00 |
21,600.00 |
200.00 |
21,600.00 |
|
|
| 735-01 |
mailboxes
|
22   |
EACH |
50.00 |
1,100.00 |
15.00 |
330.00 |
20.00 |
440.00 |
|
|
| 735-02 |
mailbox supports (single)
|
22   |
EACH |
195.00 |
4,290.00 |
150.00 |
3,300.00 |
250.00 |
5,500.00 |
|
|
| 735-04 |
mailbox supports (multiple)
|
2   |
EACH |
425.00 |
850.00 |
300.00 |
600.00 |
500.00 |
1,000.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
500,000.00 |
500,000.00 |
200,000.00 |
200,000.00 |
500,000.00 |
500,000.00 |
|
|
| 740-02 |
utility oversight and coordination
|
lump |
LUMP |
10,000.00 |
10,000.00 |
15,000.00 |
15,000.00 |
120,000.00 |
120,000.00 |
|
|
| 742-01 |
sanitary sewer pipe (8")
|
1,427   |
LNFT |
37.48 |
53,483.96 |
27.00 |
38,529.00 |
15.00 |
21,405.00 |
|
|
| 742-02 |
adjusting sanitary sewer house connections
|
8   |
EACH |
2,000.00 |
16,000.00 |
1,500.00 |
12,000.00 |
300.00 |
2,400.00 |
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
30,000.00 |
30,000.00 |
45,000.00 |
45,000.00 |
180,000.00 |
180,000.00 |
|
|
| 805-01-A |
class a concrete (pipe headwalls)
|
15.07 |
CUYD |
1,250.00 |
18,837.50 |
1,100.00 |
16,577.00 |
1,600.00 |
24,112.00 |
|
|
| 805-01-B |
class a concrete (box culvert headwalls)
|
79.19 |
CUYD |
1,250.00 |
98,987.50 |
1,100.00 |
87,109.00 |
1,300.00 |
102,947.00 |
|
|
| 805-12-E |
reinforced concrete box culverts (4'x4')
|
494.0 |
LNFT |
400.00 |
197,600.00 |
220.00 |
108,680.00 |
350.00 |
172,900.00 |
|
|
| 805-12-G |
reinforced concrete box culverts (6'x4')
|
90.0 |
LNFT |
640.00 |
57,600.00 |
350.00 |
31,500.00 |
550.00 |
49,500.00 |
|
|
| 805-12-J |
reinforced concrete box culverts (6'x 5')
|
240.0 |
LNFT |
720.00 |
172,800.00 |
360.00 |
86,400.00 |
560.00 |
134,400.00 |
|
|
| 805-12-M |
reinforced concrete box culverts (6'x6')
|
474.0 |
LNFT |
750.00 |
355,500.00 |
370.00 |
175,380.00 |
580.00 |
274,920.00 |
|
|
| 806-01 |
deformed reinforcing steel
|
6,840   |
LB |
0.35 |
2,394.00 |
2.47 |
16,894.80 |
2.00 |
13,680.00 |
|
|
| S-001 |
rumble strips (ground-in)
|
20.3 |
MILE |
705.83 |
14,328.35 |
1.00 |
20.30 |
600.00 |
12,180.00 |
|
|
| S-002 |
removal of painted transition
|
lump |
LUMP |
2,500.00 |
2,500.00 |
2,700.00 |
2,700.00 |
3,000.00 |
3,000.00 |
|
|
| S-003 |
curb inlet special detail (station 91+47 lt. and rt.)
|
4   |
EACH |
12,000.00 |
48,000.00 |
15,000.00 |
60,000.00 |
15,000.00 |
60,000.00 |
|
|
| S-004 |
partial removal of sewer manholes
|
3   |
EACH |
2,000.00 |
6,000.00 |
1,000.00 |
3,000.00 |
1,200.00 |
3,600.00 |
|
|
| S-005 |
saw-cutting
|
3,272   |
LNFT |
6.00 |
19,632.00 |
4.00 |
13,088.00 |
5.00 |
16,360.00 |
|
|
| S-006 |
curb inlet special detail (stations 96+93 and 96+94)
|
2   |
EACH |
12,000.00 |
24,000.00 |
13,000.00 |
26,000.00 |
16,000.00 |
32,000.00 |
|
|
| S-007 |
catch basin special detail
|
3   |
EACH |
12,000.00 |
36,000.00 |
11,000.00 |
33,000.00 |
16,000.00 |
48,000.00 |
|
|
| S-008 |
junction box special detail
|
1   |
EACH |
12,000.00 |
12,000.00 |
9,000.00 |
9,000.00 |
13,000.00 |
13,000.00 |
|
|
| S-009 |
paved gutter drains
|
2   |
EACH |
3,500.00 |
7,000.00 |
5,000.00 |
10,000.00 |
6,500.00 |
13,000.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | ITEM TOTAL (CONSTRUCTION BID) |
|
|
|
34,613,537.16 |
|
36,481,843.47 |
|
44,901,905.75 |
|
|
| | NUMBER OF DAYS BID AT $1,000 PER DAY. |
|
|
|
750,000.00 |
|
750,000.00 |
|
750,000.00 |
|
|
| | TOTAL BID |
|
|
|
35,363,537.16 |
|
37,231,843.47 |
|
45,651,905.75 |
|
|
|