Letting of 12/13/2006 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 014-02-0020
Parish: JEFF DAVIS
Routes: US 165
Description: I-10 - FENTON
Type Const: grading, drainage structures, lime treat, subgrade layer, class ii base course,
superpave acp (alt. a-1), pccp (alt. a-2), concrete slab span bridges & related work
Estimated Construction Cost: $27,701,071.34
Maximum Number of Days Allowed for Construction: 700
Calculated Daily User Cost: $2,900.00
 
RankLicenseBidderConstruction Bid Bidder's Proposed
Contract Time
Life Cycle
Cost
Total Bid
1 12487 DIAMOND B CONSTRUCTION CO., L.L.C. $23,463,465.61 600 $2,098,800.00 $27,302,265.61
2 12312 GILCHRIST CONSTRUCTION CO. LLC $26,440,853.97 700 $2,098,800.00 $30,569,653.97
3 39462 DENTON-JAMES LLC $27,382,044.09 700 $896,500.00 $30,308,544.09
4 04089 H & S CONSTRUCTION CO., INC. $29,711,530.71 700 $896,500.00 $32,638,030.71
 
Item Number Item Description Quantity Unit of Measure - 1 -
DIAMOND B CONSTRUCTION CO., L.L.C.
- 2 -
GILCHRIST CONSTRUCTION CO. LLC
- 3 -
DENTON-JAMES LLC
- 4 -
H & S CONSTRUCTION CO., INC.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing and grubbing lump      lump 500,000.00 500,000.00 500,000.00 500,000.00 900,000.00 900,000.00 500,000.00 500,000.00
202-01 removal of structures and obstructions lump      lump 100,000.00 100,000.00 50,000.00 50,000.00 100,000.00 100,000.00 100,000.00 100,000.00
202-02-A removal of bridges (sta. 117+25.63; 18.593 m x 9.750 m
concrete t-girder bridge)
1      ea 15,000.00 15,000.00 12,000.00 12,000.00 22,000.00 22,000.00 25.00 25.00
202-02-C removal of portland cement concrete pavement 23,303      sq m 4.50 104,863.50 6.00 139,818.00 5.50 128,166.50 10.00 233,030.00
202-02-D removal of concrete walks & drives 2,508      sq m 10.00 25,080.00 10.00 25,080.00 9.00 22,572.00 8.00 20,064.00
202-02-H removal of guard rail 330      ln m 20.00 6,600.00 15.00 4,950.00 14.00 4,620.00 20.00 6,600.00
202-02-01 removal of 3.0 m x 3.7 m shed (lt. of sta. 17+00) 1      ea 500.00 500.00 3,000.00 3,000.00 1.00 1.00 500.00 500.00
202-02-02 removal of 23.6 m x 11.9 m brick residence (lt. of
sta. 17+40)(contains non-friable asb. & ext.
transite siding)
1      ea 1,000.00 1,000.00 15,000.00 15,000.00 1.00 1.00 1,500.00 1,500.00
202-02-03 removal of 7.7 m x 6.2 m shed (lt. of sta. 18+15) 1      ea 1,000.00 1,000.00 4,000.00 4,000.00 1.00 1.00 200.00 200.00
202-02-04 removal of 8.8 m x 12.9 wood frame residence (lt. of
sta. 18+25) contains non-friable asbestos)
1      ea 1,000.00 1,000.00 10,000.00 10,000.00 1.00 1.00 1,000.00 1,000.00
202-02-05 removal of sign (lt. of sta. 19+00) 1      ea 1,000.00 1,000.00 400.00 400.00 1.00 1.00 500.00 500.00
202-02-06 removal of 7.6 m x 6.1 m metal commercial building
(lt. of sta. 19+50)
1      ea 1,000.00 1,000.00 6,500.00 6,500.00 1.00 1.00 5,000.00 5,000.00
202-02-07 removal of sign (lt. of sta. 19+75) 1      ea 1,000.00 1,000.00 350.00 350.00 1.00 1.00 500.00 500.00
202-02-08 removal of 12.4 m x 17.0 m wood frame residence(lt. of
sta. 20+90)(contains non-friable asbestos & ext.
transite siding)
1      ea 1,000.00 1,000.00 10,000.00 10,000.00 1.00 1.00 2,000.00 2,000.00
202-02-09 removal of 24.3 m x 8.5 m wood frame residence (lt. of
sta. 22+40)(contains non-friable asbestos & ext.
transite siding)
1      ea 1,000.00 1,000.00 10,000.00 10,000.00 1.00 1.00 2,000.00 2,000.00
202-02-10 removal of sign (lamar)(lt. of sta. 22+85) 1      ea 1,000.00 1,000.00 2,000.00 2,000.00 1.00 1.00 1,000.00 1,000.00
202-02-11 removal of sign (lamar)(lt. of sta. 23+70) 1      ea 1,000.00 1,000.00 2,000.00 2,000.00 1.00 1.00 1,000.00 1,000.00
202-02-12 removal of sign (lamar)(lt. of sta. 25+20) 1      ea 1,000.00 1,000.00 2,000.00 2,000.00 1.00 1.00 1,000.00 1,000.00
202-02-13 removal of 14.6 m x 18.3 m cinder block commercial
building (lt. of sta. 27+30)
1      ea 1,000.00 1,000.00 4,000.00 4,000.00 1.00 1.00 8,000.00 8,000.00
202-02-14 removal of 14.3 m x 27.3 m brick residence (lt. of
sta. 28+25)
1      ea 1,000.00 1,000.00 10,000.00 10,000.00 1.00 1.00 6,000.00 6,000.00
202-02-15 removal of entrance gate and fence (lt. of sta. 29+80) 1      ea 500.00 500.00 1,000.00 1,000.00 1.00 1.00 1,500.00 1,500.00
202-02-16 removal of sign (alicia hay farm and woodlawn baptist
church)(lt. of sta. 43+25)
1      ea 500.00 500.00 200.00 200.00 1.00 1.00 500.00 500.00
202-02-17 removal of 9.3 m x 7.3 m wood frame residence (lt. of
sta. 49+65)
1      ea 1,000.00 1,000.00 6,500.00 6,500.00 1.00 1.00 1,500.00 1,500.00
202-02-18 removal of 8.8 m x 19.0 m brick residence (lt. of sta.
52+15)(contains non-friable asbestos)
1      ea 1,000.00 1,000.00 10,000.00 10,000.00 1.00 1.00 5,000.00 5,000.00
202-02-19 removal of 9.6 m x 10.5 m wood frame residence (lt. of
sta. 42+75)(contains non-friable asbestos & ext.
transite siding)
1      ea 1,000.00 1,000.00 10,000.00 10,000.00 1.00 1.00 3,000.00 3,000.00
202-02-20 removal of 6.0 m x 8.1 m shed (lt. of sta. 54+75) 1      ea 1,000.00 1,000.00 1,000.00 1,000.00 1.00 1.00 1,000.00 1,000.00
202-02-21 removal of 2.8 m x 3.8 m shed (lt. of sta. 54+85) 1      ea 500.00 500.00 1,000.00 1,000.00 1.00 1.00 500.00 500.00
202-02-22 removal of 16.0 m x 7.4 m wood frame residence (lt. of
sta. 57+25)
1      ea 1,000.00 1,000.00 6,000.00 6,000.00 1.00 1.00 3,000.00 3,000.00
202-02-23 removal of 13.5 m x 9.6 m shed (lt. of sta. 57+45) 1      ea 1,000.00 1,000.00 3,500.00 3,500.00 1.00 1.00 3,000.00 3,000.00
202-02-24 removal of sign (lamar)(rt. of sta. 60+00) 1      ea 1,000.00 1,000.00 2,000.00 2,000.00 1.00 1.00 1,000.00 1,000.00
202-02-25 removal of 10.9 m x 19.0 m brick residence (lt. of
sta. 60_+50)(contains non-friable asbestos)
1      ea 1,000.00 1,000.00 10,000.00 10,000.00 1.00 1.00 6,000.00 6,000.00
202-02-26 removal of 10.7 m x 9.2 m garage (lt. of sta. 60+75) 1      ea 1,000.00 1,000.00 2,000.00 2,000.00 1.00 1.00 1,000.00 1,000.00
202-02-27 removal of 7.4 m x 10.8 m shed (lt. of sta. 60+85) 1      ea 1,000.00 1,000.00 2,500.00 2,500.00 1.00 1.00 1,000.00 1,000.00
202-02-28 removal of sign (rt. of sta. 61+55) 1      ea 1,000.00 1,000.00 400.00 400.00 1.00 1.00 500.00 500.00
202-02-29 removal of 7.4 m x 5.6 m cinder block building (lt. of
sta. 110+25)
1      ea 1,000.00 1,000.00 6,500.00 6,500.00 1.00 1.00 1,000.00 1,000.00
202-02-30 removal of sign (double lamar)(lt. of sta. 111+15) 1      ea 500.00 500.00 2,000.00 2,000.00 1.00 1.00 1,000.00 1,000.00
202-02-31 removal of 21.6 m x 10.5 m wood frame residence (lt.
of sta. 111+25)
1      ea 1,000.00 1,000.00 10,000.00 10,000.00 1.00 1.00 5,000.00 5,000.00
202-02-32 removal of 22.3 m x 9.9 m wood frame residence(lt. of
sta. 111+65)(contains non-friable asbestos & ext.
transite siding)
1      ea 1,000.00 1,000.00 10,000.00 10,000.00 1.00 1.00 5,000.00 5,000.00
202-02-33 removal of 20.7 m x 14.8 m wood frame residence (lt.
of sta. 112+10)
1      ea 1,000.00 1,000.00 7,500.00 7,500.00 1.00 1.00 6,000.00 6,000.00
202-02-34 removal of 18.8 m x 15.2 m wood frame residence (lt.
of sta. 112+50)
1      ea 1,000.00 1,000.00 7,500.00 7,500.00 1.00 1.00 6,000.00 6,000.00
202-02-35 removal of 15.3 m x 30.5 m metal frame building (rt.
of sta. 112+70)
1      ea 1,000.00 1,000.00 6,500.00 6,500.00 1.00 1.00 8,000.00 8,000.00
202-02-36 removal of 14.7 m x 9.3 m wood frame residence(lt. of
sta. 112+90)(contains non-friable asbestos & ext.
transite siding)
1      ea 1,000.00 1,000.00 10,000.00 10,000.00 1.00 1.00 3,000.00 3,000.00
202-02-37 removal of 12.5 m x 12.5 m wood frame residence (lt.
of sta. 113+50)
1      ea 1,000.00 1,000.00 6,500.00 6,500.00 1.00 1.00 3,000.00 3,000.00
202-02-38 removal of 7.5 m x 7.3 m wood frame commercial
building (rt. of sta. 114+25)
1      ea 1,000.00 1,000.00 6,500.00 6,500.00 1.00 1.00 1,000.00 1,000.00
202-02-39 removal of 7.5 m x 13.5 m wood frame residence (lt. of
sta. 114+30)
1      ea 1,000.00 1,000.00 6,500.00 6,500.00 1.00 1.00 3,000.00 3,000.00
202-02-40 removal of 4.0 m x 3.5 m shed (lt. of sta. 114+50) 1      ea 500.00 500.00 2,000.00 2,000.00 1.00 1.00 500.00 500.00
202-02-41 removal of sign (lamar)(rt. of sta. 115+15) 1      ea 500.00 500.00 400.00 400.00 1.00 1.00 1,000.00 1,000.00
202-02-42 removal of 19.3 m x 8.6 m wood frame residence(lt. of
sta. 127+60)(contains non-friable asbestos & ext.
transite siding)
1      ea 1,000.00 1,000.00 7,500.00 7,500.00 1.00 1.00 4,000.00 4,000.00
202-02-43 removal of 7.3 m x 18.5 m mobile home and shed (lt. of
sta. 160+25) (contains non-friable asbestos)
1      ea 1,000.00 1,000.00 6,000.00 6,000.00 1.00 1.00 4,000.00 4,000.00
202-02-44 removal of 8.5 m x 20.4 m mobile home (lt. of sta.
161+70)
1      ea 1,000.00 1,000.00 3,000.00 3,000.00 1.00 1.00 4,000.00 4,000.00
202-02-45 removal of sign (quiet oaks)(lt. of sta. 167+25) 1      ea 500.00 500.00 400.00 400.00 1.00 1.00 500.00 500.00
202-02-46 removal of 5.0 m x 4.8 m shed (lt. of sta. 175+40) 1      ea 500.00 500.00 4,500.00 4,500.00 1.00 1.00 500.00 500.00
202-02-47 removal of water well and tank (lt. of sta. 175+10) 1      ea 1,000.00 1,000.00 2,000.00 2,000.00 1.00 1.00 3,500.00 3,500.00
203-01 general excavation 145,355      cu m 4.00 581,420.00 5.00 726,775.00 4.50 654,097.50 5.00 726,775.00
203-02 drainage excavation 10,204      cu m 6.00 61,224.00 10.00 102,040.00 11.00 112,244.00 10.00 102,040.00
203-03 muck excavation 3,671      cu m 11.00 40,381.00 15.00 55,065.00 16.00 58,736.00 12.00 44,052.00
203-04 embankment 159,454      cu m 8.00 1,275,632.00 13.00 2,072,902.00 10.00 1,594,540.00 12.00 1,913,448.00
203-05-A non-plastic embankment (stone) 3,234      cu m 100.00 323,400.00 100.00 323,400.00 130.00 420,420.00 100.00 323,400.00
204-02 temporary hay or straw bales 424      ea 12.00 5,088.00 30.00 12,720.00 8.00 3,392.00 6.00 2,544.00
204-03 temporary slope drains 240      ln m 25.00 6,000.00 15.00 3,600.00 45.00 10,800.00 30.00 7,200.00
204-05-A temporary sediment check dams (hay) 34      ea 275.00 9,350.00 250.00 8,500.00 100.00 3,400.00 75.00 2,550.00
204-05-B temporary sediment check dams (stone) 15      ea 600.00 9,000.00 1,000.00 15,000.00 700.00 10,500.00 1,000.00 15,000.00
204-06 temporary silt fencing 16,978      ln m 7.00 118,846.00 5.00 84,890.00 4.30 73,005.40 3.30 56,027.40
204-07 temporary stone construction entrance 2      ea 1,500.00 3,000.00 2,200.00 4,400.00 2,000.00 4,000.00 3,000.00 6,000.00
302-02-E-01 class ii base course (125 mm thick)(stone or recycled
pccp)
14,717.0    sq m 13.00 191,321.00 16.00 235,472.00 15.00 220,755.00 13.00 191,321.00
302-02-H-01 class ii base course (350 mm thick)(stone or recycled
pccp)
40,538.4    sq m 30.75 1,246,555.80 31.00 1,256,690.40 33.00 1,337,767.20 35.00 1,418,844.00
304-05 lime treatment (type e) 1,621.25   Mg 200.00 324,250.00 100.00 162,125.00 290.00 470,162.50 175.00 283,718.75
305-01-D subgrade layer (300 mm thick) 202,661      sq m 6.50 1,317,296.50 7.25 1,469,292.25 8.00 1,621,288.00 8.00 1,621,288.00
401-01 aggregate surface course (net section) 975.2    cu m 90.00 87,768.00 85.00 82,892.00 70.00 68,264.00 100.00 97,520.00
402-01 traffic maintenance aggregate (adjusted vehicular
measurement)
750.0    cu m 90.00 67,500.00 90.00 67,500.00 75.00 56,250.00 100.00 75,000.00
701-01-G cross drain pipe (450 mm rcp/pcp) 578.5    ln m 165.00 95,452.50 285.00 164,872.50 240.00 138,840.00 300.00 173,550.00
701-01-I cross drain pipe (600 mm rcp/pcp) 193.9    ln m 200.00 38,780.00 300.00 58,170.00 310.00 60,109.00 400.00 77,560.00
701-01-N cross drain pipe (1050 mm rcp/pcp) 18.1    ln m 379.00 6,859.90 530.00 9,593.00 390.00 7,059.00 800.00 14,480.00
701-02-B cross drain pipe arch (450 mm equiv. rcpa) 85.8    ln m 180.00 15,444.00 320.00 27,456.00 260.00 22,308.00 350.00 30,030.00
701-02-D cross drain pipe arch (600 mm equiv. rcpa) 279.7    ln m 243.00 67,967.10 350.00 97,895.00 290.00 81,113.00 500.00 139,850.00
701-02-E cross drain pipe arch (750 mm equiv. rcpa) 37.6    ln m 283.00 10,640.80 360.00 13,536.00 310.00 11,656.00 600.00 22,560.00
701-02-F cross drain pipe arch (900 mm equiv. rcpa) 261.7    ln m 344.00 90,024.80 460.00 120,382.00 420.00 109,914.00 700.00 183,190.00
701-02-G cross drain pipe arch (1050 mm equiv. rcpa) 61.0    ln m 440.00 26,840.00 585.00 35,685.00 460.00 28,060.00 1,000.00 61,000.00
701-03-G storm drain pipe (450 mm rcp/pcp) 212.5    ln m 170.00 36,125.00 240.00 51,000.00 160.00 34,000.00 300.00 63,750.00
701-05-G side drain pipe (450 mm) 146.7    ln m 160.00 23,472.00 250.00 36,675.00 170.00 24,939.00 300.00 44,010.00
701-05-I side drain pipe (600 mm) 232.5    ln m 200.00 46,500.00 275.00 63,937.50 190.00 44,175.00 400.00 93,000.00
701-05-K side drain pipe (750 mm) 123.0    ln m 255.00 31,365.00 285.00 35,055.00 210.00 25,830.00 500.00 61,500.00
701-05-K-01 side drain pipe (750 mm)(erosion) 40.0    ln m 260.00 10,400.00 450.00 18,000.00 180.00 7,200.00 200.00 8,000.00
701-05-M-01 side drain pipe (900 mm)(erosion) 64.0    ln m 335.00 21,440.00 475.00 30,400.00 220.00 14,080.00 200.00 12,800.00
701-05-N side drain pipe (1050 mm) 55.0    ln m 410.00 22,550.00 800.00 44,000.00 270.00 14,850.00 800.00 44,000.00
701-06-E side drain pipe arch (750 mm equiv.) 141.4    ln m 290.00 41,006.00 350.00 49,490.00 200.00 28,280.00 500.00 70,700.00
701-06-F side drain pipe arch (900 mm equiv.) 360.7    ln m 350.00 126,245.00 360.00 129,852.00 240.00 86,568.00 700.00 252,490.00
701-06-G side drain pipe arch (1050 mm equiv.) 76.1    ln m 468.70 35,668.07 500.00 38,050.00 260.00 19,786.00 1,000.00 76,100.00
701-06-H side drain pipe arch (1200 mm equiv.) 19.6    ln m 585.00 11,466.00 800.00 15,680.00 360.00 7,056.00 1,100.00 21,560.00
701-06-I side drain pipe arch (1350 mm equiv.) 53.9    ln m 685.00 36,921.50 850.00 45,815.00 400.00 21,560.00 1,300.00 70,070.00
701-10-G reinforced concrete pipe (extension)(450 mm) 3.1    ln m 375.00 1,162.50 1,200.00 3,720.00 680.00 2,108.00 650.00 2,015.00
701-10-K reinforced concrete pipe (extension)(750 mm) 4.2    ln m 380.00 1,596.00 1,000.00 4,200.00 600.00 2,520.00 700.00 2,940.00
702-02-A manholes (mh-06m) 2      ea 6,000.00 12,000.00 7,000.00 14,000.00 4,000.00 8,000.00 3,000.00 6,000.00
702-03-A catch basins (cb-01m) 46      ea 2,000.00 92,000.00 2,500.00 115,000.00 2,600.00 119,600.00 3,000.00 138,000.00
704-01-B guard rail (single thrie beam)(1905 mm post spacing) 37.00   ln m 100.00 3,700.00 115.00 4,255.00 95.00 3,515.00 95.00 3,515.00
704-03 blocked out guard rail 600.47   ln m 62.00 37,229.14 60.00 36,028.20 57.00 34,226.79 57.00 34,226.79
704-08-B guard rail transitions (double thrie beam) 76.20   ln m 134.00 10,210.80 180.00 13,716.00 125.00 9,525.00 125.00 9,525.00
704-11-A guard rail end treatment (flared) 10      ea 2,100.00 21,000.00 2,100.00 21,000.00 2,000.00 20,000.00 2,000.00 20,000.00
705-01 barbed wire fence 1,002      ln m 17.00 17,034.00 18.00 18,036.00 15.50 15,531.00 15.50 15,531.00
705-04 single swinging driveway gates 6      ea 500.00 3,000.00 550.00 3,300.00 450.00 2,700.00 450.00 2,700.00
705-06-A chain link fence (1200 mm height) 658      ln m 50.00 32,900.00 70.00 46,060.00 46.00 30,268.00 50.00 32,900.00
705-06-B chain link fence (1500 mm height) 224      ln m 70.00 15,680.00 80.00 17,920.00 66.00 14,784.00 70.00 15,680.00
705-08-A 4.0-meter double gates for chain link fence (1200mm
height)
1      dbgt 1,200.00 1,200.00 1,000.00 1,000.00 1,200.00 1,200.00 1,200.00 1,200.00
706-02-C concrete drive (150 mm thick) 657.1    sq m 50.00 32,855.00 60.00 39,426.00 60.00 39,426.00 60.00 39,426.00
708-01 right-of-way monument 115      ea 100.00 11,500.00 400.00 46,000.00 120.00 13,800.00 160.00 18,400.00
708-02 right-of-way monument witness post 115      ea 100.00 11,500.00 400.00 46,000.00 120.00 13,800.00 160.00 18,400.00
709-01 steel cattle guard 3      ea 10,000.00 30,000.00 13,000.00 39,000.00 15,000.00 45,000.00 13,000.00 39,000.00
712-04 flexible revetment 3,897      sq m 80.00 311,760.00 90.00 350,730.00 70.00 272,790.00 55.00 214,335.00
713-01 temporary signs & barricades lump      lump 100,000.00 100,000.00 160,000.00 160,000.00 150,000.00 150,000.00 300,000.00 300,000.00
713-07 temporary reflectorized raised pavement markers 624      ea 0.38 237.12 1.30 811.20 0.35 218.40 1.20 748.80
716-01-A mulch (vegetative) 7.4    hctr 1,800.00 13,320.00 1,800.00 13,320.00 1,630.00 12,062.00 1,500.00 11,100.00
717-01 seeding 1,800      kg 18.00 32,400.00 16.00 28,800.00 17.00 30,600.00 15.00 27,000.00
718-01 fertilizer 43,000      kg 0.59 25,370.00 0.70 30,100.00 0.55 23,650.00 0.50 21,500.00
720-01-A erosion control system, slope protection (type a) 17,391      sq m 2.00 34,782.00 1.63 28,347.33 1.30 22,608.30 1.50 26,086.50
720-01-D erosion control system, flexible channel liner (type d) 2,559      sq m 3.00 7,677.00 3.00 7,677.00 2.90 7,421.10 2.00 5,118.00
722-02 project site laboratory (equipped) 1      ea 25,000.00 25,000.00 60,000.00 60,000.00 30,000.00 30,000.00 50,000.00 50,000.00
724-02-C pavement patching (400 mm thick) 353      sq m 95.00 33,535.00 185.00 65,305.00 100.00 35,300.00 50.00 17,650.00
725-02 temporary detour roads 5,155.2    sq m 75.00 386,640.00 75.00 386,640.00 70.00 360,864.00 100.00 515,520.00
726-01 bedding material 1,381.7    cu m 100.00 138,170.00 100.00 138,170.00 75.00 103,627.50 100.00 138,170.00
727-01 mobilization lump      lump 2,125,000.00 2,125,000.00 2,400,000.00 2,400,000.00 2,700,000.00 2,700,000.00 2,700,000.00 2,700,000.00
729-16-C object marker assembly (type 3) 10      ea 80.00 800.00 75.00 750.00 75.00 750.00 75.00 750.00
729-19-C dead end road installation (type c) 3      ea 1,500.00 4,500.00 1,000.00 3,000.00 1,700.00 5,100.00 1,450.00 4,350.00
731-02 reflectorized raised pavement markers 2,511      ea 6.00 15,066.00 5.50 13,810.50 5.00 12,555.00 5.50 13,810.50
732-01-C plastic pavement striping (200 mm width) 503      ln m 3.54 1,780.62 1.50 754.50 3.30 1,659.90 1.50 754.50
732-01-E plastic pavement striping (600 mm width) 151      ln m 10.61 1,602.11 4.00 604.00 9.90 1,494.90 4.00 604.00
732-02-A plastic pavement striping (solid line)(100 mm width) 44.985  km 1,422.62 63,996.56 1,600.00 71,976.00 1,330.00 59,830.05 1,500.00 67,477.50
732-04-A plastic pavement legends & symbols (arrow) 15      ea 160.81 2,412.15 140.00 2,100.00 150.00 2,250.00 150.00 2,250.00
732-04-C plastic pavement legends & symbols (only) 15      ea 160.81 2,412.15 160.00 2,400.00 150.00 2,250.00 150.00 2,250.00
732-04-D plastic pavement legends & symbols (rr crossing) 1      ea 428.82 428.82 500.00 500.00 400.00 400.00 450.00 450.00
732-05 removal of existing markings 29.580  km 100.00 2,958.00 2,400.00 70,992.00 2,500.00 73,950.00 3,600.00 106,488.00
735-01 mailboxes 65      ea 15.00 975.00 50.00 3,250.00 1.00 65.00 6.00 390.00
735-02 mailbox supports (single) 65      ea 150.00 9,750.00 200.00 13,000.00 130.00 8,450.00 145.00 9,425.00
740-01 construction layout lump      lump 150,000.00 150,000.00 320,000.00 320,000.00 260,000.00 260,000.00 300,000.00 300,000.00
740-02 utility oversight and coordination lump      lump 25,000.00 25,000.00 80,000.00 80,000.00 30,000.00 30,000.00 80,000.00 80,000.00
744-01 traffic control management lump      lump 30,000.00 30,000.00 120,000.00 120,000.00 30,000.00 30,000.00 140,000.00 140,000.00
804-01-C precast concrete piles (400 mm) 1,515.8    ln m 200.00 303,160.00 170.00 257,686.00 200.00 303,160.00 200.00 303,160.00
804-01-D precast concrete piles (450 mm) 810.0    ln m 226.00 183,060.00 185.00 149,850.00 250.00 202,500.00 300.00 243,000.00
805-01-B class a concrete (box culvert headwalls) 171.32   cu m 1,200.00 205,584.00 1,200.00 205,584.00 1,100.00 188,452.00 1,200.00 205,584.00
805-01-F class a concrete (bents) 169.27   cu m 1,200.00 203,124.00 950.00 160,806.50 1,100.00 186,197.00 1,200.00 203,124.00
805-03 class aa concrete 665.26   cu m 850.00 565,471.00 650.00 432,419.00 650.00 432,419.00 1,000.00 665,260.00
805-12-E reinforced concrete box culverts (1200 mm x 1200 mm) 359.00   ln m 850.00 305,150.00 900.00 323,100.00 800.00 287,200.00 1,100.00 394,900.00
805-12-F-01 reinforced concrete box culverts (extension)(1500 mm x
1200 mm)
51.70   ln m 1,100.00 56,870.00 1,900.00 98,230.00 1,050.00 54,285.00 1,400.00 72,380.00
805-12-I reinforced concrete box culverts (1500 mm x 1500 mm) 242.40   ln m 100.00 24,240.00 1,000.00 242,400.00 1,100.00 266,640.00 1,700.00 412,080.00
805-12-I-01 reinforced concrete box culverts (extension)(1500 mm x
1500 mm)
268.00   ln m 1,200.00 321,600.00 950.00 254,600.00 1,200.00 321,600.00 1,500.00 402,000.00
806-01 deformed reinforcing steel 94,465      kg 2.00 188,930.00 1.75 165,313.75 1.80 170,037.00 3.50 330,627.50
810-01 concrete railing (barrier) 288.00   ln m 256.00 73,728.00 180.00 51,840.00 150.00 43,200.00 275.00 79,200.00
813-01 concrete approach slabs 1,180.80   sq m 200.00 236,160.00 190.00 224,352.00 200.00 236,160.00 250.00 295,200.00
S-001 rumble strips (ground-in) 26.3    km 400.00 10,520.00 500.00 13,150.00 440.00 11,572.00 360.00 9,468.00
S-002 rice levees 4,662      ln m 5.25 24,475.50 15.00 69,930.00 50.00 233,100.00 12.00 55,944.00
S-003 plugging existing water wells 1      ea 6,000.00 6,000.00 3,000.00 3,000.00 2,500.00 2,500.00 250.00 250.00
S-004 protected prairie grass area signs 237      ea 19.00 4,503.00 260.00 61,620.00 30.00 7,110.00 100.00 23,700.00
S-101 retroreflective sheeting panels lump      lump 8,000.00 8,000.00 1,500.00 1,500.00 5,000.00 5,000.00 250.00 250.00
S-102 settlement plate installation and monitoring 4      ea 2,500.00 10,000.00 2,000.00 8,000.00 2,500.00 10,000.00 1,000.00 4,000.00
 SUBTOTAL GENERAL       13,867,958.94   16,306,385.63   16,259,442.04   18,241,161.24
                       
ALTERNATE A pavement alternates                    
                       
ALTERNATE A1 superpave asphaltic concrete pavement                    
302-02-G-01 class ii base course (225 mm thick)(stone or recycled
pccp)
156,353.3    sq m 20.00 3,127,066.00 22.00 3,439,772.60 0.00 0.00 0.00 0.00
502-01 superpave asphaltic concrete 68,001.8    Mg 92.00 6,256,165.60 95.00 6,460,171.00 0.00 0.00 0.00 0.00
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
1,280.2    Mg 132.00 168,986.40 145.00 185,629.00 0.00 0.00 0.00 0.00
713-04-B temporary pavement markings (broken line)(100 mm width)
(3.0 m length)
4.500  km 240.00 1,080.00 475.00 2,137.50 0.00 0.00 0.00 0.00
713-05-A temporary pavement markings (solid line)(100 mm width) 19.383  km 396.00 7,675.67 480.00 9,303.84 0.00 0.00 0.00 0.00
713-05-A-01 temporary pavement markings (solid line)(100 mm width)
(type i removable)
2.730  km 8,000.00 21,840.00 10,000.00 27,300.00 0.00 0.00 0.00 0.00
732-03-A plastic pavement striping (broken line)(100 mm width) 25.386  km 500.00 12,693.00 400.00 10,154.40 0.00 0.00 0.00 0.00
 SUBTOTAL ALT A1       9,595,506.67   10,134,468.34        
                       
ALTERNATE A2 portland cement concrete pavement                    
302-02-F-01 class ii base course (200 mm thick)(stone or recycled
pccp)
153,018.1    sq m 0.00 0.00 0.00 0.00 18.50 2,830,834.85 20.00 3,060,362.00
302-02-G-01 class ii base course (225 mm thick)(stone or recycled
pccp)
3,335.2    sq m 0.00 0.00 0.00 0.00 25.00 83,380.00 25.00 83,380.00
502-01 superpave asphaltic concrete 5,307.9    Mg 0.00 0.00 0.00 0.00 100.00 530,790.00 100.00 530,790.00
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
204.9    Mg 0.00 0.00 0.00 0.00 200.00 40,980.00 120.00 24,588.00
601-01-G portland cement concrete pavement (200 mm thick) 128,033.9    sq m 0.00 0.00 0.00 0.00 46.00 5,889,559.40 47.00 6,017,593.30
601-02-G portland cement concrete pavement (200 mm thick)
(crossovers & turnouts)
24,984.2    sq m 0.00 0.00 0.00 0.00 64.00 1,598,988.80 65.00 1,623,973.00
713-04-B-01 temporary pvmt. markings (broken line)(100 mm w)(3.0 m
l)(type i removable)
4.500  km 0.00 0.00 0.00 0.00 2,100.00 9,450.00 150.00 675.00
713-05-A temporary pavement markings (solid line)(100 mm width) 9.931  km 0.00 0.00 0.00 0.00 400.00 3,972.40 455.00 4,518.61
713-05-A-01 temporary pavement markings (solid line)(100 mm width)
(type i removable)
6.204  km 0.00 0.00 0.00 0.00 8,200.00 50,872.80 10,000.00 62,040.00
732-03-A-01 temporary pavement markings (broken line)(100 mm width)
(preformed marking tape - type v)
25.386  km 0.00 0.00 0.00 0.00 3,300.00 83,773.80 2,460.00 62,449.56
 SUBTOTAL ALT A2               11,122,602.05   11,470,369.47
                       
 ITEM TOTAL (CONSTRUCTION BID)       23,463,465.61   26,440,853.97   27,382,044.09   29,711,530.71
 NUMBER OF DAYS BID AT $2,900 PER DAY.       1,740,000.00   2,030,000.00   2,030,000.00   2,030,000.00
 LIFE CYCLE COST       2,098,800.00   2,098,800.00   896,500.00   896,500.00
 TOTAL BID       27,302,265.61   30,569,653.97   30,308,544.09   32,638,030.71