Letting of 8/30/2006 LA DOTD Headquarters


REBID
go back
Go Back
 
Lead Project: 450-13-0042
Parish: ST JOHN
Routes: I-10
Description: LAPLACE PIT SCALE MAINLINE SORTNG SYSTEM
Type Const: grading, cold planing asphaltic pavement, pavement patching, superpave asphaltic
concrete pavement, mainline sorting system, pccp resurfacing, and related work.
Estimated Construction Cost: $2,288,020.52
 
RankLicenseBidderConstruction Bid
1 01692 TOOMER ELECTRICAL CO., INC. $2,968,896.74
 
Item Number Item Description Quantity Unit of Measure - 1 -
TOOMER ELECTRICAL CO., INC.

 

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-01 removal of structures & obstructions lump      lump 36,672.00 36,672.00            
203-06 excavation & embankment lump      lump 24,000.00 24,000.00            
204-02 temporary hay or straw bales 40      ea 25.00 1,000.00            
204-06 temporary silt fencing 1,000      LNFT 6.00 6,000.00            
302-01 class ii base course 7.0    CUYD 160.00 1,120.00            
502-01 superpave asphaltic concrete 108.4    TON 275.00 29,810.00            
509-01 cold planing asphaltic pavement 2,534      SQYD 7.70 19,511.80            
509-02 contractor retained reclaimed asphaltic pavement - 341      CUYD 10.00 - 3,410.00            
602-07 patching continuously reinforced concrete pavement 90.0    SQYD 605.00 54,450.00            
713-01 temporary signs & barricades lump      LUMP 52,000.00 52,000.00            
713-05-A temporary pavement markings (solid line)(4" width) 1.654  MILE 880.00 1,455.52            
713-07 temporary reflectorized raised pavement markers 100      EACH 23.00 2,300.00            
713-09 temporary precast concrete barrier (department
furnished)
122      EACH 425.00 51,850.00            
725-02 temporary detour roads 8,500.0    SQYD 71.00 603,500.00            
727-01 mobilization lump      LUMP 288,000.00 288,000.00            
729-04 sign (type d) 1,298.0    SQFT 21.00 27,258.00            
729-08-F mounting (w6 x 12) 14      EACH 880.00 12,320.00            
729-08-G mounting (w8 x 18) 18      EACH 1,235.00 22,230.00            
729-13 mounting (bridge fascia mounted) 2      EACH 8,250.00 16,500.00            
731-02 reflectorized raised pavement markers 110      EACH 6.00 660.00            
732-02-A plastic pavement striping (solid line) (4" width) 3.083  MILE 2,740.00 8,447.42            
740-01 construction layout lump      LUMP 23,568.00 23,568.00            
744-01 traffic control management lump      LUMP 48,672.00 48,672.00            
S-001 mainline sorting system lump      LUMP 1,385,268.00 1,385,268.00            
S-002 p.c.c.p resurfacing (6 1/2" thick) 272.6    CUYD 660.00 179,916.00            
S-003 saw cut p.c.c pavement (full depth) 160      LNFT 11.00 1,760.00            
S-004 rumble strips (ground-in) 0.2    MILE 17,880.00 3,576.00            
S-005 dynamic message sign unit 5      EACH 8,250.00 41,250.00            
S-006 extended maintenance lump      LUMP 28,512.00 28,512.00            
S-007 sawcuts in asphaltic concrete (6.5" depth) 100      LNFT 7.00 700.00            
                       
 CONTRACTOR TOTAL       2,968,896.74            