| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - MADDEN CONTRACTING CO., INC. |
- 2 - GILCHRIST CONSTRUCTION CO. LLC |
- 3 - DIAMOND B CONSTRUCTION CO., L.L.C. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
2,500.00 |
2,500.00 |
3,000.00 |
3,000.00 |
50,000.00 |
50,000.00 |
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
2,500.00 |
2,500.00 |
3,000.00 |
3,000.00 |
25,000.00 |
25,000.00 |
|
|
| 203-08 |
borrow (vehicular measurement)
|
5,826   |
CUYD |
1.50 |
8,739.00 |
12.75 |
74,281.50 |
15.00 |
87,390.00 |
|
|
| 203-09 |
geotextile fabric
|
217   |
SQYD |
3.00 |
651.00 |
2.50 |
542.50 |
3.00 |
651.00 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
3,850   |
CUYD |
54.50 |
209,825.00 |
64.00 |
246,400.00 |
50.00 |
192,500.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
13,601.0 |
TON |
65.00 |
884,065.00 |
73.00 |
992,873.00 |
68.00 |
924,868.00 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
646.7 |
TON |
40.00 |
25,868.00 |
95.00 |
61,436.50 |
100.00 |
64,670.00 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
889   |
SQYD |
5.00 |
4,445.00 |
1.00 |
889.00 |
13.00 |
11,557.00 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 41   |
CUYD |
0.01 |
- 0.41 |
0.01 |
- 0.41 |
0.10 |
- 4.10 |
|
|
| 701-01-M/N |
cross drain pipe (36" rcp/pcp or 42" cmp)
|
248   |
LNFT |
190.00 |
47,120.00 |
138.00 |
34,224.00 |
150.00 |
37,200.00 |
|
|
| 711-01-E |
riprap (130 lb, 12" thick)
|
62   |
SQYD |
100.00 |
6,200.00 |
75.00 |
4,650.00 |
76.00 |
4,712.00 |
|
|
| 711-04 |
geotextile fabric
|
62   |
SQYD |
3.00 |
186.00 |
2.50 |
155.00 |
3.00 |
186.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
47,000.00 |
47,000.00 |
25,000.00 |
25,000.00 |
20,000.00 |
20,000.00 |
|
|
| 713-04-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
10.227 |
MILE |
325.00 |
3,323.78 |
300.00 |
3,068.10 |
150.00 |
1,534.05 |
|
|
| 713-04-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
8.129 |
MILE |
1.00 |
8.13 |
1.00 |
8.13 |
300.00 |
2,438.70 |
|
|
| 713-05-A |
temporary pavement markings (solid line)(4" width)
|
30.250 |
MILE |
1.00 |
30.25 |
1.00 |
30.25 |
700.00 |
21,175.00 |
|
|
| 717-01 |
seeding
|
235   |
LB |
8.50 |
1,997.50 |
9.00 |
2,115.00 |
10.00 |
2,350.00 |
|
|
| 718-01 |
fertilizer
|
7,820   |
LB |
0.25 |
1,955.00 |
0.30 |
2,346.00 |
0.28 |
2,189.60 |
|
|
| 721-01 |
asphalt mulch
|
18,925   |
GAL |
1.65 |
31,226.25 |
1.80 |
34,065.00 |
1.84 |
34,822.00 |
|
|
| 724-01-B |
pavement patching (12" minimum thickness)
|
9,000   |
SQYD |
50.00 |
450,000.00 |
73.00 |
657,000.00 |
78.00 |
702,000.00 |
|
|
| 726-01 |
bedding material
|
74.0 |
CUYD |
50.00 |
3,700.00 |
70.00 |
5,180.00 |
72.00 |
5,328.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
47,000.00 |
47,000.00 |
63,000.00 |
63,000.00 |
190,000.00 |
190,000.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
4   |
EACH |
100.00 |
400.00 |
85.00 |
340.00 |
84.00 |
336.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
675   |
EACH |
5.00 |
3,375.00 |
4.43 |
2,990.25 |
5.00 |
3,375.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
15.125 |
MILE |
2,150.00 |
32,518.75 |
2,100.00 |
31,762.50 |
2,400.00 |
36,300.00 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
4.064 |
MILE |
700.00 |
2,844.80 |
750.00 |
3,048.00 |
800.00 |
3,251.20 |
|
|
| 735-01 |
mailboxes
|
14   |
EACH |
1.00 |
14.00 |
10.00 |
140.00 |
25.00 |
350.00 |
|
|
| 735-02 |
mailbox supports (single)
|
14   |
EACH |
135.00 |
1,890.00 |
145.00 |
2,030.00 |
200.00 |
2,800.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
15,000.00 |
15,000.00 |
15,000.00 |
15,000.00 |
18,000.00 |
18,000.00 |
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
15,000.00 |
15,000.00 |
35,000.00 |
35,000.00 |
50,000.00 |
50,000.00 |
|
|
| S-001 |
cleaning existing ditches
|
75   |
LNFT |
10.00 |
750.00 |
28.00 |
2,100.00 |
28.00 |
2,100.00 |
|
|
| S-002 |
sack concrete headwall
|
68.7 |
CUYD |
375.00 |
25,762.50 |
650.00 |
44,655.00 |
700.00 |
48,090.00 |
|
|
| S-003 |
saw cutting
|
126,360   |
INFT |
0.01 |
1,263.60 |
0.15 |
18,954.00 |
1.00 |
126,360.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,877,158.15 |
|
2,369,283.32 |
|
2,671,529.45 |
|
|
|