Lead Project: 713-55-0101
Parish: TERREBONNE
Routes:
Description: DULAC PONTOON BRIDGE REHABILITATION
Type Const: replace deck boards, timber stringers, floor plates, and related work.
Estimated Construction Cost: $142,499.35
 
RankLicenseBidderConstruction Bid
1 00009 COASTAL CONTRACTORS, INC. $243,834.50
2 26435 C.E.C., INC. $328,734.20
 
Item Number Item Description Quantity Unit of Measure - 1 -
COASTAL CONTRACTORS, INC.
- 2 -
C.E.C., INC.

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
713-01 temporary signs & barricades lump      LUMP 7,000.00 7,000.00 10,000.00 10,000.00        
727-01 mobilization lump      LUMP 30,000.00 30,000.00 25,000.00 25,000.00        
740-01 construction layout lump      LUMP 2,000.00 2,000.00 4,000.00 4,000.00        
812-01-B treated timber (coastal treatment) 35.83   MFBM 4,550.00 163,026.50 6,740.00 241,494.20        
S-001 floor plate (1/4" x 3') 536      LNFT 78.00 41,808.00 90.00 48,240.00        
                       
 CONTRACTOR TOTAL       243,834.50   328,734.20        