| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - SHILOH CONTRACTORS, INC. |
- 2 - W. E. MCDONALD & SON, LLC. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
10,000.00 |
10,000.00 |
15,000.00 |
15,000.00 |
|
|
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
1,000.00 |
1,000.00 |
7,000.00 |
7,000.00 |
|
|
|
|
| 202-02-A-01 |
removal of bridge(sta.100+00,23.4' wide x 39.0'long
timber bridge with wing walls) |
1   |
EACH |
10,000.00 |
10,000.00 |
7,500.00 |
7,500.00 |
|
|
|
|
| 202-03-A |
relocate metal gate
|
lump |
LUMP |
500.00 |
500.00 |
1,000.00 |
1,000.00 |
|
|
|
|
| 203-06 |
excavation & embankment
|
lump |
LUMP |
15,000.00 |
15,000.00 |
20,000.00 |
20,000.00 |
|
|
|
|
| 204-02 |
temporary hay or straw bales
|
10   |
EACH |
1.00 |
10.00 |
50.00 |
500.00 |
|
|
|
|
| 204-03 |
temporary slope drains
|
120   |
LNFT |
1.00 |
120.00 |
12.00 |
1,440.00 |
|
|
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
4   |
EACH |
1.00 |
4.00 |
200.00 |
800.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
165   |
LNFT |
3.00 |
495.00 |
3.00 |
495.00 |
|
|
|
|
| 403-01 |
aggregate roadway surfacing (vehicular measurement)
|
76.4 |
CUYD |
90.00 |
6,876.00 |
100.00 |
7,640.00 |
|
|
|
|
| 701-05-G-01 |
side drain pipe (18")(erosion)
|
180   |
LNFT |
30.00 |
5,400.00 |
55.00 |
9,900.00 |
|
|
|
|
| 701-05-I-01 |
side drain pipe (24")(erosion)
|
84   |
LNFT |
45.00 |
3,780.00 |
75.00 |
6,300.00 |
|
|
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
75.0 |
LNFT |
55.00 |
4,125.00 |
52.50 |
3,937.50 |
|
|
|
|
| 704-09 |
guard rail anchor sections (turndown)
|
75.0 |
LNFT |
35.00 |
2,625.00 |
23.50 |
1,762.50 |
|
|
|
|
| 704-11-A |
guard rail end treatment (flared)
|
1   |
EACH |
2,000.00 |
2,000.00 |
2,000.00 |
2,000.00 |
|
|
|
|
| 705-01 |
barbed wire fence
|
346   |
LNFT |
10.00 |
3,460.00 |
8.00 |
2,768.00 |
|
|
|
|
| 705-04 |
single swinging driveway gates
|
1   |
EACH |
450.00 |
450.00 |
500.00 |
500.00 |
|
|
|
|
| 711-01-C |
riprap (30 lb,14" thick)
|
594   |
SQYD |
55.00 |
32,670.00 |
75.00 |
44,550.00 |
|
|
|
|
| 711-04 |
geotextile fabric
|
594   |
SQYD |
2.50 |
1,485.00 |
3.00 |
1,782.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
5,000.00 |
5,000.00 |
10,000.00 |
10,000.00 |
|
|
|
|
| 716-01-A |
mulch (vegetative)
|
0.15 |
ACRE |
2,000.00 |
300.00 |
10,000.00 |
1,500.00 |
|
|
|
|
| 717-01 |
seeding
|
7   |
LB |
20.00 |
140.00 |
50.00 |
350.00 |
|
|
|
|
| 718-01 |
fertilizer
|
146   |
LB |
1.00 |
146.00 |
10.00 |
1,460.00 |
|
|
|
|
| 720-01-A |
erosion control system, slope protection (type a)
|
117   |
SQYD |
5.00 |
585.00 |
5.00 |
585.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
35,000.00 |
35,000.00 |
12,000.00 |
12,000.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
7   |
EACH |
70.00 |
490.00 |
70.00 |
490.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
4,500.00 |
4,500.00 |
7,500.00 |
7,500.00 |
|
|
|
|
| 804-01-B |
precast concrete piles (14")
|
765   |
LNFT |
50.00 |
38,250.00 |
50.00 |
38,250.00 |
|
|
|
|
| 804-12 |
loading permanent piles
|
1   |
EACH |
FREE |
FREE |
1.00 |
1.00 |
|
|
|
|
| 805-10-A |
bridge superstructure & substructure(24' clear rdwy;
90 degree crossing) |
4   |
SPAN |
22,000.00 |
88,000.00 |
24,000.00 |
96,000.00 |
|
|
|
|
| S-001 |
water gate
|
1   |
ea |
650.00 |
650.00 |
1,500.00 |
1,500.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
273,061.00 |
|
304,511.00 |
|
|
|
|
|