Letting of 7/26/2006 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 451-08-0068
Parish: MADISON
Routes: I-20
Description: RICHLAND PARISH LINE TO JCT. US 80
Type Const: traffic signing and related work.
Estimated Construction Cost: $916,100.60
 
RankLicenseBidderConstruction Bid
1 23811 UNITED RENTALS HWY TECHNOLOGIES INC $705,442.10
2 34068 ALPHA SERVICE AND PRODUCTS, INC. $749,137.30
3 38764 ATWOOD FENCE COMPANY INC. $799,794.05
4 27043 JACK B. HARPER CONTRACTOR, INC. $822,306.52
 
Item Number Item Description Quantity Unit of Measure - 1 -
UNITED RENTALS HWY TECHNOLOGIES INC
- 2 -
ALPHA SERVICE AND PRODUCTS, INC.
- 3 -
ATWOOD FENCE COMPANY INC.
- 4 -
JACK B. HARPER CONTRACTOR, INC.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-02-01 removal of sign and support(s) 395      EACH 75.00 29,625.00 95.00 37,525.00 165.00 65,175.00 236.25 93,318.75
202-02-02 removal of sign face(s) 348      EACH 55.00 19,140.00 45.00 15,660.00 55.00 19,140.00 128.25 44,631.00
706-03-C incidental concrete paving (6" thick) 252.0    SQYD 125.00 31,500.00 40.00 10,080.00 55.00 13,860.00 36.45 9,185.40
713-01 temporary signs & barricades lump      LUMP 5,000.00 5,000.00 24,000.00 24,000.00 5,500.00 5,500.00 6,750.00 6,750.00
727-01 mobilization lump      LUMP 45,000.00 45,000.00 96,000.00 96,000.00 15,000.00 15,000.00 47,000.00 47,000.00
729-01 sign (type a) 3,145.5    SQFT 17.00 53,473.50 16.00 50,328.00 18.50 58,191.75 16.20 50,957.10
729-02 sign (type b) 131.4    SQFT 20.00 2,628.00 18.50 2,430.90 19.00 2,496.60 18.90 2,483.46
729-04 sign (type d) 7,279.3    SQFT 23.50 171,063.55 18.00 131,027.40 24.00 174,703.20 20.25 147,405.83
729-05 sign (type e) 590.3    SQFT 23.50 13,872.05 20.00 11,806.00 25.00 14,757.50 21.60 12,750.48
729-06 sign (overhead mounted) 110.0    SQFT 25.00 2,750.00 20.00 2,200.00 25.00 2,750.00 22.95 2,524.50
729-08-A mounting (2 1/2" post) 99      EACH 500.00 49,500.00 575.00 56,925.00 700.00 69,300.00 573.75 56,801.25
729-08-B mounting (3 1/2" post) 102      EACH 600.00 61,200.00 675.00 68,850.00 750.00 76,500.00 641.25 65,407.50
729-08-E mounting (s3 x 5.7) 8      EACH 650.00 5,200.00 600.00 4,800.00 825.00 6,600.00 607.50 4,860.00
729-08-F mounting (w6 x 12) 120      EACH 700.00 84,000.00 850.00 102,000.00 975.00 117,000.00 877.50 105,300.00
729-08-F-01 mounting (w6 x 12)(structure mounted) 2      EACH 750.00 1,500.00 1.00 2.00 1,150.00 2,300.00 405.00 810.00
729-08-G mounting (w8 x 18) 70      EACH 900.00 63,000.00 1,100.00 77,000.00 1,250.00 87,500.00 1,012.50 70,875.00
729-08-H mounting (w8 x 24) 14      EACH 1,500.00 21,000.00 1,450.00 20,300.00 1,575.00 22,050.00 1,485.00 20,790.00
729-13 mounting (bridge fascia mounted) 2      EACH 5,000.00 10,000.00 1.00 2.00 5,000.00 10,000.00 5,670.00 11,340.00
729-17 milepost assembly (ground mounted) 60      EACH 40.00 2,400.00 95.00 5,700.00 95.00 5,700.00 108.00 6,480.00
729-18 milepost assembly (structure mounted) 4      EACH 45.00 180.00 100.00 400.00 125.00 500.00 87.75 351.00
729-21 u-channel post 11      EACH 60.00 660.00 196.00 2,156.00 75.00 825.00 67.50 742.50
740-01 construction layout lump      LUMP 5,000.00 5,000.00 5,000.00 5,000.00 7,500.00 7,500.00 9,450.00 9,450.00
744-01 traffic control management lump      LUMP 2,500.00 2,500.00 10,000.00 10,000.00 9,500.00 9,500.00 20,250.00 20,250.00
S-001 remove and remount logo panel 21      ea 250.00 5,250.00 45.00 945.00 45.00 945.00 87.75 1,842.75
S-002 dynamic message sign unit 2      ea 10,000.00 20,000.00 7,000.00 14,000.00 6,000.00 12,000.00 15,000.00 30,000.00
                       
 CONTRACTOR TOTAL       705,442.10   749,137.30   799,794.05   822,306.52